Financing a Desalination Plant

Private activity bonds for water facilities, WIFIA loans and sponsor equity, with the sources and uses, coverage, stress cases and public delivery comparison of a fictional 25 mgd plant.

A privately financed desalination plant is paid for with tax-exempt private activity bonds, sometimes a federal WIFIA loan, and sponsor equity, all repaid from one water purchase agreement. A worked $872.2 million example shows the sources and uses, coverage of 1.45x, the value of the tax exemption and the cost difference against public delivery.

Worked in full in The Desalination and Water Reuse Project Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Two Ways to Pay for the Same Plant

A water agency that needs a desalination or potable reuse plant can own it and finance it on its own credit, with revenue bonds, a federal loan and grants, using a design-build or design-build-operate contract. Or it can sign a long-term water purchase agreement with a project company that raises the money, builds the plant and is paid only for water made available. The second route is project finance, and the reference American transaction is the Carlsbad plant in California, whose financing closed in December 2012 with 734 million dollars of tax-exempt bonds and private equity, for a total project cost of about one billion dollars. For the contract itself, see how a take-or-pay water purchase agreement works.

Sources and Uses

The example is from The Desalination and Water Reuse Project Finance Handbook: a 25 mgd seawater plant with its intake, outfall and pipeline. Calder Point Water Company, the Calder Point Seawater Desalination Plant and the Arroyo Coast Water Authority are fictional, and the costs and prices are planning assumptions, not quotations. This article is educational and is not legal, tax, engineering or investment advice.

Uses of fundsAmount
Construction budget$700,000,000
Capitalized interest, 3 years$107,100,000
Debt service reserve fund$46,891,057
Costs of issuance$10,200,000
Working capital and pre-operating costs$8,000,000
Total$872,191,057
Sources of fundsAmountShare
Tax-exempt private activity bonds at 5.25 percent$680,000,00078.0 percent
Sponsor equity$192,191,05722.0 percent

Financing costs and reserves are 19.7 percent of the total. A project company has no revenue during construction, so interest for 3 years, a full year of debt service in reserve and working capital must all be raised at closing.

Private Activity Bonds for Water

A private company can borrow at tax-exempt rates through exempt facility bonds. Section 142(a)(4) of the Internal Revenue Code lists facilities for the furnishing of water, and section 142(e) requires that the water be made available to the general public and that either a governmental unit operate the facility or the rates be established or approved by a state or political subdivision or a similar body. In a wholesale project, the public buyer's approval of the price schedule in the water purchase agreement is the usual basis for the second condition. Bond counsel determines qualification on the facts.

The bonds are issued by a governmental conduit and need an allocation of the state's private activity bond volume cap under section 146. At least 95 percent of net proceeds must pay qualifying costs, costs of issuance paid from proceeds are limited to 2 percent, and the issue needs public approval after a hearing.

Tax-exempt at 5.25 percentTaxable at 6.75 percent
Annual debt service on $680.0 million over 28 years$46,891,057$54,680,801
Coverage in Year 2 at the same contract price1.45x1.25x

The exemption is worth $7,789,744 a year in the example, or $324.57 per acre-foot of the minimum commitment.

WIFIA

The federal Water Infrastructure Finance and Innovation Act program, created in 2014 and run by the Environmental Protection Agency, lends up to 49 percent of eligible project costs at a rate tied to the Treasury's for a similar maturity, with final maturity up to 35 years after substantial completion and repayment deferral of up to five years. Desalination, water recycling, aquifer recharge and alternative water supply projects are eligible by statute, and private borrowers with a public sponsor can apply. The agency's 2025 annual report counts 147 loans closed for 22 billion dollars. Federal requirements, including environmental review, prevailing wages and domestic sourcing rules, apply to the whole project.

Coverage and What Can Break It

In Year 2 the buyer pays $112,477,915. Operating costs are $42,852,947, the renewal and replacement deposit is $1,537,500, and cash flow available for debt service is $68,087,468 against debt service of $46,891,057: a debt service coverage ratio of 1.45x. Because fixed charges are paid on a minimum commitment, the ratio is the same whether the buyer orders its minimum or its maximum.

Year 2 stressCoverage
Base case1.45x
Buyer takes only the minimum1.45x
Energy consumption 350 kWh per acre-foot above the guarantee1.42x
Fixed operating costs 15 percent over budget1.38x
Availability of 80 percent1.32x
Availability of 60 percent0.87x
Severe: 60 percent availability, high energy use, costs 10 percent over0.80x

Debt service is exactly covered at an availability of 65.8 percent. In the severe case the annual shortfall is $9,268,060, and the reserve fund covers about 61 months of it. The sponsor's projected return is 9.8 percent from financial close over the life of the contract.

What Private Finance Costs

If the buyer delivered the same $700.0 million plant itself, financing 49 percent with a WIFIA loan at 4.60 percent and the rest with its own revenue bonds at 4.25 percent, its annual debt service would be $41,390,970 against a capital charge of $67,891,057 under the water purchase agreement. The difference, $26,500,087 a year or $996.24 per acre-foot, is the price of transferring construction, performance and development risk. A construction overrun alone would have to reach about 63 percent of cost to erase it, so the case for private delivery rests on performance and development risk, not on overruns. The unit prices under both models are built up in the cost of desalinated water per acre-foot.

Diligence in Five Headings

The free Water Purchase Agreement Model (Excel) covers the contract side of this analysis. The full case workbook on the book page adds sources and uses, the 30-year projection, the stress table and the buyer's view.

Questions practitioners ask

Can a privately owned desalination plant use tax-exempt bonds?

Yes, in principle. Facilities for the furnishing of water are one of the exempt facility categories of Internal Revenue Code section 142, subject to conditions on public availability and rate approval, a state volume cap allocation and other rules. Qualification is determined by bond counsel.

What share of a desalination project can a WIFIA loan finance?

Up to 49 percent of eligible project costs, with total federal assistance limited to 80 percent. Desalination and water recycling projects are eligible by statute.

What debt service coverage do lenders look for on a desalination project?

It depends on the contract and the plant. Availability-type water contracts with strong public buyers are financed at lower ratios than merchant projects. The worked example has a base case of 1.45x, a distribution lock-up at 1.20x and break-even availability of 65.8 percent.

How much equity does a desalination project need?

The Carlsbad financing was reported at about 82 percent tax-exempt debt and 18 percent equity. The worked example uses 78.0 percent debt and 22.0 percent equity.

Read the full handbook

This guide is drawn from The Desalination and Water Reuse Project Finance Handbook, which follows the fictional Calder Point Seawater Desalination Plant through its water purchase agreement, its construction, its bond financing and its stress cases.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Water Purchase Agreement Model (Excel).

Illustrative figures computed by the book model; the Calder Point case is fictional and its costs and prices are planning assumptions. Education only, not legal, tax, engineering, or investment advice.