Articles · Construction Estimating
Ready-mix prices are on the supplier quote; concrete bids are won or lost on crew hours per 1,000 square feet, overtime premiums, and full labor burden.
Concrete labor cost per square foot equals crew hours per 1,000 square feet multiplied by the fully burdened hourly rate (straight-time wage, overtime premium, FICA, workers compensation, health coverage, unemployment taxes, and seasonal hiring cost), divided by 1,000. In our worked contractor case, burdened field labor runs $3.33 per square foot on residential flatwork (88 crew hours per 1,000 sq ft) versus $2.08 on builder foundations (55 crew hours), and a 12-hour crew overrun on a warehouse slab wipes out $116,455 in labor alone.
Worked in full in The Concrete Contractor by Julian R. Sterling, with five Excel workbooks including the job cost model.Get the DRM-free PDF, $19.99 →
Estimators often price labor using an average field wage (say $29.15 per hour across foremen, finishers, laborers, and operators) and add a rough 15% payroll markup. That shortcut misses four real cash costs that scale directly with crew hours and seasonality:
Overtime premium (FLSA 29 CFR Part 778). Concrete cannot wait once the ready-mix truck arrives. Rain delays, late afternoon pours, and night slabs push crews over 40 hours in a workweek. Under the Fair Labor Standards Act, non-exempt field workers earn 1.5 times their regular rate for overtime hours, and the extra 0.5x premium cannot be passed through on a fixed-price bid.
FICA and workers compensation. Employer FICA adds 7.65% on wages up to the Social Security wage base, while concrete trade workers compensation often runs $8 to $12 per $100 of payroll ($9.80 per $100 in our case). Together, those two lines add 17.45% on top of straight-time wages and overtime.
Health coverage, unemployment taxes, and seasonal hiring. Concrete crews expand in spring and shrink in winter. Federal unemployment tax (FUTA, $42 per worker on the first $7,000) and state unemployment tax (SUTA) reset every January 1 and restart for every seasonal hire. Add screening, silica safety training, and gear ($650 to $670 per hire), plus employer health contributions, and full labor burden easily adds 29% to 40% above straight-time wages.
Take two core work types from Orrinford Concrete (the fictional contractor in The Concrete Contractor) in 2025. Average straight-time field wage is $29.15 per hour, overtime runs 7.0% of crew hours, employer FICA is 7.65%, workers compensation is $9.80 per $100 of wages, and health coverage is $1.712 per crew hour. Residential flatwork takes 88 crew hours per 1,000 square feet; builder foundations take 55 crew hours per 1,000 square feet of footprint.
| Field Labor Line (per 1,000 sq ft) | Residential Flatwork (88 hrs) | Builder Foundations (55 hrs) |
|---|---|---|
| Wages at straight time ($29.15/hr) | $2,565.20 | $1,603.25 |
| Overtime premium (0.5x on 7.0% of hours) | $89.78 | $56.11 |
| Payroll taxes (7.65%) and workers comp ($9.80/$100) | $463.29 | $289.56 |
| Health coverage ($1.712/crew hr) | $150.66 | $94.16 |
| Unemployment taxes and seasonal hiring | $62.97 | $39.35 |
| Total burdened field labor (per 1,000 sq ft) | $3,331.90 | $2,082.43 |
| Burdened labor per square foot | $3.33 | $2.08 |
| Effective burdened cost per crew hour | $37.86 | $37.86 |
| Total direct cost (incl. ready-mix, materials, pump, equip., GL) | $7,115.59 | $8,491.77 |
| Contract price per 1,000 sq ft | $9,964.00 | $9,690.00 |
| Contribution per 1,000 sq ft (and margin) | $2,848.41 (28.6%) | $1,198.23 (12.4%) |
Notice the effective hourly rate: $3,331.90 divided by 88 crew hours is $37.86 per hour, which is 29.9% above the $29.15 straight-time wage. Flatwork carries $1,249.47 more labor per 1,000 square feet than foundations, yet earns more than double the contribution ($2,848.41 vs $1,198.23) because foundations require twice as much ready-mix concrete (26.00 vs 12.97 cubic yards per 1,000 square feet).
Plug in your square footage, slab thickness, ready-mix quote, crew hours per 1,000 square feet, wage, overtime, and payroll taxes in the free Concrete Job Bid Calculator, or explore all five workbooks on The Concrete Contractor page.
Free Concrete Bid Calculator Book Page & Companion FilesIn March 2025, Orrinford bid a 180,000 square foot, 8-inch distribution warehouse slab at a fixed price of $6.60 per square foot ($1,188,000 total). The bid assumed 26 crew hours per 1,000 square feet at the 2024 wage ($27.50/hr), 6.0% overtime, zero seasonal hiring or unemployment cost, and 2024 ready-mix pricing. In the field, night pours and tight floor-flatness tolerances pushed actual crew hours to 38 per 1,000 square feet at the 2025 wage ($29.15/hr) and 20.0% overtime.
| Cost Line (per 1,000 sq ft) | Bid Estimate | Actual 2025 | Variance |
|---|---|---|---|
| Wages at straight time | $715.00 | $1,107.70 | +$392.70 |
| Overtime premium (6% bid vs 20% actual) | $21.45 | $110.77 | +$89.32 |
| Payroll taxes and workers comp | $128.51 | $212.62 | +$84.11 |
| Health coverage | $41.60 | $65.06 | +$23.46 |
| Unemployment taxes and hiring costs | $0.00 | $57.38 | +$57.38 |
| Subtotal: burdened field labor | $906.56 | $1,553.53 | +$646.97 |
| Ready-mix, rebar/materials, pump, equip., GL | $5,253.24 | $5,801.07 | +$547.83 |
| Total direct cost per 1,000 sq ft | $6,159.80 | $7,354.60 | +$1,194.80 |
| Fixed bid price per 1,000 sq ft | $6,600.00 | $6,600.00 | $0.00 |
| Job contribution per 1,000 sq ft | $440.20 | -$754.60 | -$1,194.80 |
Field labor alone accounted for $646.97 of the $1,194.80 per 1,000 square feet overrun (54.1% of the cost blowup), adding $116,455 in unbudgeted payroll across 180,000 square feet. Combined with ready-mix (+$324.60) and pump service (+$140.00), total direct contribution swung from +$79,236 to -$135,828. After subtracting $49,400 for the dedicated job superintendent, the warehouse slab lost $185,228, dragging company-wide EBITDA down $299,391 and pushing the bank fixed charge coverage ratio to 0.98 against a 1.25 covenant.
At the actual direct cost of $7.35 per square foot, earning even a 15.0% contribution margin required pricing the bid at $7.35 / (1 - 0.15) = $8.65 per square foot, more than $2.00 above the $6.60 fixed price.
The trap: Two payroll mistakes quietly erode concrete margins. First, bidding with last year's crew wage and ignoring seasonal hiring and January FUTA/SUTA resets: those omitted lines cost $57.38 per 1,000 square feet on the warehouse slab. Second, treating production bonuses or flat travel stipends as outside the overtime base: under 29 CFR 778.109 and 778.217, non-discretionary bonuses and disguised per diems must be added to the weekly regular rate before calculating time-and-a-half.
Start with crew hours per 1,000 square feet, multiply by the average straight-time field wage, add the overtime premium, then layer FICA (7.65%), workers compensation, health coverage, unemployment taxes, and seasonal hiring cost. Divide the total by 1,000 to get burdened labor cost per square foot.
Residential driveways and patios have high edge-to-area ratios, tight access, and hand finishing, requiring around 80 to 90 crew hours per 1,000 square feet in our worked case. Large open warehouse slabs use laser screeds and ride-on trowels, cutting crew hours to 30 to 38 per 1,000 square feet, though night pours and flatness specs can spike overtime.
Under 29 CFR Part 778, overtime must be paid at 1.5 times the employee's regular rate for hours over 40 in a workweek. Non-discretionary production or safety bonuses and disguised per diems must be folded into the regular rate before computing the half-time overtime premium.
In our 180,000 square foot warehouse slab case, running 38 crew hours per 1,000 square feet instead of 26 (with 20% overtime instead of 6% and higher 2025 wages) raised field labor cost by $646.97 per 1,000 square feet, or $116,455 across the job, turning a projected $79,236 contribution into a $135,828 direct loss.
Figures verified November 23, 2026. Orrinford Concrete and all job costs, wages, and workers compensation rates are fictional teaching assumptions, not market norms or legal/payroll advice.
The Concrete Contractor ties square feet, cubic yards, crew hours, overtime, payroll taxes, job contribution, retainage cash flow, the borrowing base, and bank covenants into five editable Excel workbooks.