Cubic yards per square foot: concrete math for bids

Thickness, waste and the cubic yard, the yards per 1,000 square feet of four kinds of work, and the costs a yard count does not carry.

A 4-inch slab with 5 percent waste takes 12.97 cubic yards per 1,000 square feet; an 8-inch slab with 4 percent waste takes 25.68. In the worked case, ready-mix at $170.64 a yard was the largest line of an 8-inch slab, but labor and the pump explained most of the bid's miss.

Worked in full in The Concrete Contractor by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback

Free: the concrete job bid calculator in Excel, prefilled with the worked case of the book.

The arithmetic

A cubic yard is 27 cubic feet. A slab of a given area and thickness holds area × thickness in feet ÷ 27 cubic yards, and the order adds a waste allowance for subgrade variation, spillage and the last partial load.

Cubic yards to order = square feet × (thickness in inches ÷ 12) ÷ 27 × (1 + waste)

Cubic yards per 1,000 square feet in the worked case.
Cubic yards per 1,000 square feet (fictional case)ThicknessWasteYards
Residential flatwork4 inches5 percent12.97
Commercial site concrete6 inches5 percent19.44
Large slab on grade8 inches4 percent25.68
Builder foundations (footings and walls, per 1,000 sq ft of footprint)variesincluded26.00

The yards are where the price of concrete enters the bid. In The Concrete Contractor, the case company paid $158.00 a cubic yard delivered in 2024 and $170.64 in 2025, after its supplier's 8.0 percent increase. On an 8-inch slab, ready-mix was the largest single line of the cost: $4,382.04 per 1,000 square feet in 2025, against $4,057.44 in a bid estimate that had used the 2024 price.

What the yards do not tell you

The concrete is only part of the cost. The same 8-inch slab took 38 crew hours per 1,000 square feet against 26 in the estimate, with overtime at 20.0 percent of crew hours instead of 6.0 percent, and the pump cost $260.00 per 1,000 square feet against $120.00 assumed. Together, labor, ready-mix and pump made up 93.0 percent of a $1,194.80 gap per 1,000 square feet between the bid and the actual.

Read yards ordered against yards placed on every job, every week. A waste allowance that keeps creeping up is a cost the bid did not carry.

Cutting and grinding: the silica rule

Saw cutting joints and grinding the slab create respirable crystalline silica. As read in November 2026, the federal construction standard (29 CFR 1926.1153) applies unless exposure stays below 25 micrograms per cubic meter as an 8-hour average under any foreseeable conditions. Its Table 1 sets controls by task, for example a walk-behind saw with water fed continuously to the blade, used without a respirator outdoors and with one indoors or in an enclosed area; a written exposure control plan, reviewed at least annually, and a competent person are required. The water, the plan and the training belong in the cost of the job.

Sources

  1. eCFR: 29 CFR 1926.1153, respirable crystalline silica in construction

Rules as read in November 2026. The company in the examples is fictional; nothing here is legal, tax, payroll, accounting, engineering or investment advice.

Questions readers ask

How many cubic yards of concrete for 1,000 square feet?

At 4 inches with 5 percent waste, 12.97 cubic yards; at 6 inches, 19.44; at 8 inches with 4 percent waste, 25.68 (the worked case).

What is the formula for cubic yards of concrete?

Square feet x (thickness in inches / 12) / 27, plus a waste allowance.

How much waste should a concrete order include?

It depends on the subgrade, the forms and the job. The worked case uses 5 percent on flatwork and 4 percent on a large slab; compare yards ordered with yards placed on your own jobs.

Is ready-mix the biggest cost of a slab?

On a thick slab it is the largest single line, but labor, overtime and the pump decide whether a fixed price holds. In the case they made most of the gap between bid and actual.