Weekly payroll against slow pay applications, retainage held for months, the borrowing base and the gap between EBITDA and cash.
A concrete contractor pays crews every week and is paid by general contractors months later, minus retainage. In the worked case, one warehouse slab paid four months after billing pushed receivables and retainage up $573,427, put the company on its line in September 2025, and made cash fall $562,980 in a year with EBITDA of $1,077,108.
Worked in full in The Concrete Contractor by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback
Free: the concrete job bid calculator in Excel, prefilled with the worked case of the book.
A concrete contractor pays its crews every week and its ready-mix supplier the month after delivery, while its clients pay on their own schedule. In the worked case, homeowners pay a deposit and the balance at completion; home builders pay the month after; general contractors pay 90 percent of each monthly pay application two months after billing and hold 10 percent retainage, released six months after billing.
One large job changes the picture. Orrinford Concrete, the fictional company of The Concrete Contractor, poured a warehouse slab from June to October 2025 for a general contractor that paid 90 percent of each pay application in the fourth month after billing and held 10 percent retainage until seven months after the last pour.
| Month end 2025 (fictional case) | Cash | Line drawn | Receivables (retainage excluded) |
|---|---|---|---|
| February | $1,089,836 | $0 | $392,028 |
| May | $970,800 | $0 | $804,279 |
| August | $478,970 | $0 | $1,500,376 |
| September | $300,000 | $155,152 | $1,689,974 |
| December | $456,469 | $0 | $973,328 |
The owner's policy is to keep at least $300,000 of cash at every month end. Cash closed exactly at that floor only at the end of September 2025, and only because the line of credit was drawn for the first time that month: $155,152, still drawn at the end of October and November and repaid in December.
The case line lends 80 percent of eligible receivables, progress billings no older than 90 days, up to $1,250,000; retainage is never eligible. From September 2025 the oldest unpaid pay application of the slab, $213,840 at the end of September, was more than 90 days old and outside the base. Retainage held by general contractors rose from $138,030 to $263,732 over the year, of which $118,800 on the slab, not due before May 2026.
On federal construction contracts, as read in November 2026, the Federal Acquisition Regulation lets the contracting officer withhold retainage only when progress is not satisfactory, at most 10 percent of the approved estimate, paid promptly at completion. Private and state work follow their contracts and state law. Whether retainage is shown as a receivable or as a contract asset under the revenue standard has varied between contractors; agree it with your outside accountant.
| Cash bridge 2025 (fictional case) | $ |
|---|---|
| EBITDA 2025 | 1,077,108 |
| Increase in receivables and retainage | -573,427 |
| Increase in payroll owed at year end | +2,137 |
| Increase in ready-mix and materials owed at year end | +18,537 |
| Capital expenditure | -80,000 |
| Term loan payments | -524,135 |
| Interest on the line | -3,200 |
| Owner distributions | -480,000 |
| Net draw on the line | +0 |
| Change in cash | -562,980 |
EBITDA was $1,077,108 and cash still fell $562,980. The largest use was the $573,427 increase in receivables and retainage, mostly the slab's pay applications waiting four months and its retainage. Before signing a large subcontract, plan the line and the floor month by month from the payment timing and retainage you expect, not from the terms you hope for.
Rules as read in November 2026. The company in the examples is fictional; nothing here is legal, tax, payroll, accounting, engineering or investment advice.
A share of each progress payment, 10 percent in the worked case, that the client holds until a later date set by the contract, such as several months after completion.
Not in the worked case: the bank lends 80 percent of progress billings no older than 90 days and never counts retainage. Each bank sets its own terms; ask yours.
In the case, receivables and retainage rose $573,427, and loan payments, distributions and capital expenditure were paid in cash; EBITDA counts none of these.
The payment timing the general contractor actually practices, the retainage and its release date, the payroll and ready-mix the job adds each month, the effect on the borrowing base, and the month-end cash against the floor.
This article is one calculation from The Concrete Contractor, a practitioner’s guide to the numbers of a concrete company: the price per square foot, the cost of 1,000 square feet, crew hours, ready-mix and pump, job margins, retainage, cash and the bank covenant.
DRM-free PDF, $19.99 · Paperback, $32.99, shipped worldwide · Free Excel calculator