Managed 2,000 kW subscription charging ($1,136,400/yr) vs. unmanaged 2,700 kW peaks ($2,037,600/yr), PG&E BEV-2-S, SCE TOU-EV-9, and NEC 625.42.
Unmanaged plug-and-go charging on a general-service tariff can push a commercial truck depot's electricity bill from $0.206 to $0.369 per kWh, wiping out most of the electric fuel advantage. Here is the exact OCPP 2.0.1 load-management math on a 2.70 MW depot, window by window.
Worked in full in The Fleet Electrification Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
In The Fleet Electrification Handbook, Pacific Crest's Inland Valley Terminal installs 15 dual-port 180 kW DC fast chargers (30 dispensers, 2,700 kW nameplate) behind a 2.50 MVA transformer ($2,400,000 gross customer-side capex; $1,800,000 net after $600,000 utility make-ready rebate). Delivering 5,520,000 kWh per year (20,073 kWh per operating day) takes two staggered groups of 15 tractors: each group charges at midday for 90 minutes at 2,000 kW, and the CSMS levels the overnight block at about 1,759 kW. Energy delivered equals power multiplied by the hours trucks are plugged in, and the windows add up to the daily need with a 9.6 percent margin. Unmanaged, every cabinet runs at full output on arrival:
| Annual Electricity Line Item (5,520,000 kWh) | Unmanaged (2,700 kW) | Managed (2,000 kW) | Annual Savings |
|---|---|---|---|
| Monthly Peak Demand / Subscription Rate | 2,700 kW @ $22.00 | 2,000 kW @ $14.00 | -700 kW (-25.9%) |
| Annual Demand / Subscription Charges | $712,800 | $336,000 | $376,800 |
| Blended TOU Energy Charges | $1,324,800 ($0.240) | $800,400 ($0.145) | $524,400 |
| Total Gross Electricity / Year | $2,037,600 ($0.369) | $1,136,400 ($0.206) | $901,200 |
| Net Electricity After LCFS ($472,159) | $2,037,600 less LCFS ($0.284/kWh) | $664,241 ($0.120) | $901,200 |
Enrolling a separately metered EV depot on a dedicated commercial EV tariff (such as PG&E BEV-2-S subscription blocks or SCE TOU-EV-9 phased Facilities-Related Demand) paired with an OCPP 2.0.1 CSMS and ISO 15118-20 Plug & Charge raises depot load factor from 23.3 percent to 31.5 percent and blocks 4:00 PM to 9:00 PM On-Peak charging completely. Under NEC Article 625.42, a UL-listed fail-safe Energy Management System also allows engineers to size the service transformer to managed load (2.50 MVA) rather than 125 percent of sum-of-nameplate capacity, saving capital and months of utility transformer lead time.
Review full 8-year truck TCO in Class 8 electric truck TCO vs. diesel math, lock down HVIP/LCFS and TRAC financing in post-45W fleet incentives (HVIP, LCFS) and TRAC lease financing, and test your own utility demand rates in the free Fleet Electrification TCO and Financing Model (Excel).
Under unmanaged charging at the 2,700 kW nameplate peak ($22/kW-month), demand charges alone cost Pacific Crest $712,800 per year, pushing total gross electricity to $2,037,600 ($0.369/kWh). Capping peak load at 2,000 kW via OCPP 2.0.1 smart charging and staggered charging groups saves $901,200 per year.
A dedicated EV meter is required to qualify for specialized commercial EV subscription/TOU tariffs (like PG&E BEV-2-S and SCE TOU-EV-9), prevents truck charging peaks from triggering warehouse building demand ratchets, and provides ANSI C12.20 revenue-grade kWh data for CARB LCFS credits.
A stationary BESS pencils when a terminal faces punitive non-EV demand charges ($25-$35/kW-mo), 36-month utility CIAC transformer delays, or life-safety transit resilience mandates (such as Metro Valley Transit Authority's 1.0 MWh unit). Where OCPP 2.0.1 smart charging and EV subscription tariffs already exist, software beats hardware.
This guide is drawn from The Fleet Electrification Handbook, following commercial electric truck and transit bus deployments from telematics screening and depot engineering through HVIP/LCFS monetization, TRAC leases, and daily operations.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Fleet Electrification TCO and Financing Model (Excel).