A renewal is a decision to spend capital now for margin later, so the test is the price at which the margin repays the spend. A small change in that price moves the value a long way.
A 1,000 MW nuclear station with five years left on its licence can spend $480m to run for another 20. At a flat power price of $55.00 a MWh the renewal is worth $425.3m at an 8.0% discount rate. It breaks even at $47.10 a MWh, $7.90 below the base price, and every $1.00 a MWh moves the value by $53.9m.
| Item | Value |
|---|---|
| Net capacity | 1,000 MW |
| Capacity factor | 92.0% |
| Output (1,000 MW × 8,760 hours × 92.0%) | 8,059,200 MWh a year |
| Fuel and operating cost | $32.00 a MWh |
| Sustaining capital spending after renewal | $60.0m a year |
| Licence extension capital spending | $480.0m, $160.0m in each of years 1 to 3 |
| Current licence ends | End of year 5 |
| Renewed licence | 20 years, years 6 to 25 |
| Discount rate | 8.0% |
Without the renewal the station closes at the end of year 5. Decommissioning is paid either way, only 20 years later with the renewal, so it is left out; counting it would make the renewal look better, not worse. Tax, inflation and any capacity or clean-energy payments are also left out so that the price stands alone.
Margin = MWh × (price − operating cost) − sustaining capital spending
At $55.00: 8,059,200 × (55.00 − 32.00) − 60.0m = $125.4m
Excel: =Output*(Price-Cost)-Sustaining
Revenue is $443.3m and operating cost $257.9m, so the station keeps $185.4m before the $60.0m of sustaining spending. The renewal is worth that margin for 20 years, but only from year 6, so each year is discounted five or more years.
Annuity factor, years 6 to 25 at 8.0% = 6.682
PV of margin = 125.4m × 6.682 = $837.7m
PV of the extension spend = 160.0m × (1.08−1 + 1.08−2 + 1.08−3) = $412.3m
Value of the renewal = 837.7 − 412.3 = $425.3m
Excel: =(Margin*(PV(8%,20,-1)/1.08^5))-NPV(8%,160,160,160)
Value = 0 when price = cost + (sustaining × factor + PV of spend) / (MWh × factor)
= 32.00 + (60.0m × 6.682 + 412.3m) / (8,059,200 × 6.682) = $47.10 a MWh
| Power price | Annual margin | PV of margin | Value of renewal |
|---|---|---|---|
| $40.00 | 4.5 | 29.9 | -382.4 |
| $45.00 | 44.8 | 299.2 | -113.2 |
| $50.00 | 85.1 | 568.4 | 156.1 |
| $55.00 | 125.4 | 837.7 | 425.3 |
| $60.00 | 165.7 | 1,106.9 | 694.6 |
| $65.00 | 206.0 | 1,376.2 | 963.9 |
The value is a straight line in the price. It is negative at $40.00 and $45.00, turns positive between $45.00 and $50.00 and then rises by $269.3m for every $5.00. A renewal that looks safe at $55.00 has a cushion of only 14.4% before the value reaches zero, because most of the price is operating cost that does not go away.
| Case | Break-even price | Change vs base |
|---|---|---|
| Base case | $47.10 | – |
| Extension capex $720m instead of $480m | $50.93 | +$3.83 |
| Discount rate 10.0% | $48.78 | +$1.68 |
| Capacity factor 90.0% | $47.44 | +$0.34 |
| Operating cost $36.00 a MWh | $51.10 | +$4.00 |
A 50% overrun on the extension spend raises the break-even by $3.83, against $1.68 for a two-point rise in the discount rate. The price still matters more than either: a $5.00 move in the power price changes the value of the renewal by $269.3m.
Compare the present value of the extra years of margin, after fuel, operating cost and sustaining spending, with the present value of the extension spend. Here $125.4m a year for 20 years from year 6 is worth $837.7m against $412.3m of spend.
$47.10 a MWh for a 1,000 MW station at a 92.0% capacity factor, $32.00 of operating cost, $60.0m of sustaining spending and $480m of extension spend at 8.0%.
Operating cost is fixed in dollars per MWh, so a change in price drops straight into the margin. Each $1.00 a MWh moves the value of the renewal by $53.9m.
The free companion files for The Nuclear Energy Investor value a fictional two-unit nuclear station under four cases (licence renewal, a hyperscaler power contract, an uprate), with fuel, contracts, debt, decommissioning, new build and SMR models. The station in this article is invented and is not in them. No account and no email address.
Not on Amazon: 19 paperbacks by Julian R. Sterling on energy, infrastructure and land, printed on demand and shipped worldwide. Browse the bookshop →
Reading guide: infrastructure, data centres and energy → · All 1908 articles →