Every open legal or operational claim goes through one probability matrix at year-end to decide whether to accrue, disclose or keep monitoring, while insurance recoveries stay gross on the balance sheet.
An ASC 450 loss contingency accrual requires two conditions together: a probable liability at the balance sheet date and a reasonably estimable amount. On Corvane Hydraulics’ 31 December 2026 claims inventory of four open matters, only one is accrued ($1,750,000), one is disclosed ($300,000 to $650,000), two are neither accrued nor disclosed, and a separate $750,000 insurance recovery is presented gross as an asset.
Worked in full in The Contingencies and Provisions Handbook by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the ebook and paperback
Free: the contingencies and provisions model in Excel, including the full probability matrix, warranty roll-forward and ARO layer schedule with automated checks.
Under FASB ASC 450-20, preparers sort every loss contingency into three likelihood tiers: probable (likely to occur, generally interpreted in practice around 75 percent or higher), remote (slight chance), and reasonably possible (more than remote, less than probable). Accrual and footnote disclosure follow a fixed decision table:
| Likelihood | Amount estimable? | Accrue liability? | Disclose in notes? |
|---|---|---|---|
| Probable | Yes (point or range) | Yes (best estimate or low end) | Yes (nature and amount; excess if range) |
| Probable | No | No | Yes (nature and why not estimable) |
| Reasonably possible | Yes or no | No | Yes (nature and range, or state not estimable) |
| Remote | Not applicable | No | No (except financial guarantees under ASC 460) |
Unasserted claims (potential claims that nobody has filed or threatened yet) add a mandatory gatekeeper step under ASC 450-20-50-6. Management first decides whether it is probable that a claim will be asserted. If assertion is not probable, the matter is neither accrued nor disclosed. Only when assertion is probable does the preparer test whether an unfavorable outcome is probable or reasonably possible.
Corvane Hydraulics, Inc. is the fictional industrial pump maker followed in The Contingencies and Provisions Handbook. Its 2026 financial statements are available to be issued on 18 March 2027. At 31 December 2026, the controller and general counsel review four open matters plus one company-initiated claim that closed during the year:
| Matter | Claimed ($) | Assessment | Accrued ($) | Disclosure |
|---|---|---|---|---|
| 1. Tallowmere distributor suit | 4,500,000 | Probable (settled 5 Feb 2027) | 1,750,000 | Settlement amount & payment date |
| 2. Municipal utility product claim | 1,400,000 | Reasonably possible | 0 | Range $300,000 to $650,000 |
| 3. Competitor patent letter | Not stated | Remote | 0 | None (kept on inventory) |
| 4. Unasserted supplier cancellation | 200,000 | Assertion not probable | 0 | None (fails Step 1 test) |
| Total open litigation accrual | 1,750,000 |
Each line illustrates a distinct close rule:
A fifth matter closed before year-end: Corvane’s own $800,000 claim against a castings supplier for defective housings. Under ASC 450-30, gain contingencies are never recognized until realized or realizable, so Corvane booked $0 at 31 December 2025. When the claim settled on 14 October 2026 and $500,000 cash arrived on 30 October 2026, Corvane booked Dr Cash $500,000, Cr Gain on settlement of claim $500,000.
1. Tallowmere subsequent settlement adjustment: Dr Litigation expense $550,000 / Cr Accrued litigation liability $550,000 (brings liability from $1,200,000 to $1,750,000).
2. Supplier claim gain realized (30 Oct 2026): Dr Cash $500,000 / Cr Gain on settlement of claim $500,000.
3. Insurance recovery receivable (Mill Run): Dr Insurance recovery receivable $750,000 / Cr Environmental remediation expense $750,000.
The trap: removing a remote matter from the claims inventory or netting an insurance recovery against the accrued liability. A matter leaves the inventory only when settled, paid, dismissed or withdrawn; otherwise, a change in facts next quarter can be missed. And balance-sheet netting hides the gross obligation if the insurer later disputes coverage.
When a loss contingency is partially covered by insurance, US GAAP separates the liability from the recovery asset. At the Mill Run disposal site (accounted for under ASC 410-30), Corvane’s cumulative recognized remediation losses reach $2,120,000 by 31 December 2026 ($420,000 in 2024, $1,140,000 in 2025 and $560,000 in 2026), with $680,000 paid to date and an ending liability of $1,440,000.
In 2026, Corvane’s historical general liability insurer accepts coverage for 50 percent of Corvane’s study ($300,000) and remedy ($1,560,000) shares, subject to a $750,000 policy cap. Fifty percent of $1,860,000 equals $930,000, which is capped at $750,000. Because recovery is probable and does not exceed cumulative losses recognized ($2,120,000), Corvane records $750,000 as a separate asset and credits 2026 environmental remediation expense:
| Financial statement line | 2026 amount ($) | Presentation rule |
|---|---|---|
| Environmental remediation liability (ending) | 1,440,000 | Gross liability (no netting) |
| Insurance recovery receivable (ending) | 750,000 | Separate asset (gross) |
| 2026 remediation charge before recovery | 560,000 | Operating expense |
| Less: probable insurance recovery | -750,000 | Offsets remediation expense |
| Net 2026 environmental expense (credit) | -190,000 | Net credit on income statement |
Contrast that with a nonrecognized subsequent event: on 20 February 2027 (after year-end, before the 18 March 2027 issuance date), a fire at Corvane’s Ashby Crossing warehouse destroys $700,000 of inventory. The property policy covers cost above a $100,000 deductible, leaving a $600,000 expected recovery and a $100,000 net loss. Because the fire did not exist at 31 December 2026, Corvane adjusts nothing in 2026; it discloses the fire, carrying amount, deductible and estimated net loss in the 2026 notes, and records both the loss and probable recovery in 2027.
Run every claim through one dated claims inventory at close: accrue probable and estimable losses, disclose reasonably possible ranges, apply the two-step assertion test to unasserted claims, defer gain contingencies until realized, and present probable insurance recoveries gross on the balance sheet.
Figures checked on 23 November 2026. Standards paraphrased as read in November 2026; Corvane Hydraulics, Inc. and all case figures are fictional teaching assumptions. Not accounting, legal or tax advice.
A loss contingency is accrued only when two conditions are met together: it is probable that a liability had been incurred at the balance sheet date, and the amount of the loss can be reasonably estimated. Reasonably possible losses are disclosed without accrual, and remote losses are neither accrued nor disclosed.
Unasserted claims require a two-step test. First, assess whether assertion of the claim is probable. If assertion is not probable, no accrual or disclosure is required. Only if assertion is probable do you evaluate whether an unfavorable outcome is probable or reasonably possible.
No. Under US GAAP, the loss contingency liability and any probable insurance recovery receivable must be presented gross on the balance sheet as separate liability and asset lines, unless a legal right of setoff exists. On the income statement, the recovery may offset the related loss expense.
A gain contingency is not recognized until it is realized or realizable, a much higher threshold than probable. In the worked case, an $800,000 claim against a supplier is not recognized at year-end 2025 and is recorded only when settled for $500,000 and collected in October 2026.
This article is one close schedule from The Contingencies and Provisions Handbook, covering ASC 450, ASC 460 and ASC 410 side by side with IAS 37: litigation accruals, warranties, guarantees, asset retirement obligations, environmental remediation, restructuring and subsequent events, with a free companion Excel workbook.
Google Play · DRM-free PDF, $19.99 · Paperback, $32.99, shipped worldwide · Free Excel model