The Construction Scheduler

Construction Scheduling for the Contractor's Team: the Baseline, Critical Path and Float, Cost-Loaded Schedules, Monthly Updates, Look-Aheads, Delay Recovery and the Window Analysis.

DRM-free PDF edition, $19.99: searchable, printable, instant download.Buy the PDFFree sample

These are the companion files of the book. Five workbooks follow the schedule of Halvercroft Constructors, the fictional general contractor of the case, on the Dunmarrow County Public Safety Building: the calendars, the baseline network and its passes, the cost curves, the monthly updates and the recovery of the steel slip. A toolkit holds the check-lists of Appendix B in editable form.

The five workbooks, the toolkit and the read-me, in one archive196 KB

The archive holds the five workbooks, the toolkit and 00_START_HERE.md. No macros, no circular references, no external links, no password. The workbooks recalculate in Excel, LibreOffice or Google Sheets.

The files

Three numbers to reproduce first

The longest path63 activities finish on working day 243, 16 December 2026, with 8 working days of project float
Float that does not add upAcceleration and resequencing recover 5 workdays each, 9 together, at $6,222 a workday
The windows closeTen windows add up to 6 workdays, the net slip at the update of 1 November 2026

The files are provided as they are, without warranty of any kind. The model is illustrative: Halvercroft Constructors, Dunmarrow County and every party are fictional, and the durations, values, premiums and rates are the book’s assumptions, not market terms or the practice of any real contractor or owner. Forms and rules change: check the current texts, the contract as signed and your counsel.