Construction Scheduling for the Contractor's Team: the Baseline, Critical Path and Float, Cost-Loaded Schedules, Monthly Updates, Look-Aheads, Delay Recovery and the Window Analysis.
DRM-free PDF edition, $19.99: searchable, printable, instant download.Buy the PDFFree sample
These are the companion files of the book. Five workbooks follow the schedule of Halvercroft Constructors, the fictional general contractor of the case, on the Dunmarrow County Public Safety Building: the calendars, the baseline network and its passes, the cost curves, the monthly updates and the recovery of the steel slip. A toolkit holds the check-lists of Appendix B in editable form.
The archive holds the five workbooks, the toolkit and 00_START_HERE.md. No macros, no circular references, no external links, no password. The workbooks recalculate in Excel, LibreOffice or Google Sheets.
Chapter 5
The two case calendars and their holidays, the contract time, and every day of the job with its working day number. Sheets: Calendars, Working days. A Checks sheet puts the figures printed in the book beside the cells that compute them.
Download workbook 140 KBChapters 4, 6, 7 and 9
The baseline network and its links, with the forward and backward passes, total and free float and the critical path by live formula. Sheets: Activities, Links, Holidays. A Checks sheet puts the figures printed in the book beside the cells that compute them.
Download workbook 238 KBChapter 8
Activity values spread over their workdays, and the early, late and as-built cumulative curves. Sheets: Activity values, Spread, Curves, Holidays. A Checks sheet puts the figures printed in the book beside the cells that compute them.
Download workbook 352 KBChapters 10, 12 and 15
Ten monthly updates: value in place, forecast, slip, and the window changes that add up to the net slip. Sheets: Updates, Progress, Holidays. A Checks sheet puts the figures printed in the book beside the cells that compute them.
Download workbook 433 KBChapters 13 and 14
The recovery options after the steel slip: Saturdays worked, cost per workday recovered and the exposure. Sheets: Options, Saturdays, Holidays. A Checks sheet puts the figures printed in the book beside the cells that compute them.
Download workbook 516 KBAppendix B
Contract schedule requirements (what to extract before building); Baseline review before submission; The monthly update; The three-week look-ahead; A recovery plan.
Download the toolkit41 KBRead first
What each file holds, which workbook answers which chapter, and the two inputs to change first.
Download the read-me4 KB| The longest path | 63 activities finish on working day 243, 16 December 2026, with 8 working days of project float |
| Float that does not add up | Acceleration and resequencing recover 5 workdays each, 9 together, at $6,222 a workday |
| The windows close | Ten windows add up to 6 workdays, the net slip at the update of 1 November 2026 |
The files are provided as they are, without warranty of any kind. The model is illustrative: Halvercroft Constructors, Dunmarrow County and every party are fictional, and the durations, values, premiums and rates are the book’s assumptions, not market terms or the practice of any real contractor or owner. Forms and rules change: check the current texts, the contract as signed and your counsel.