Tool 5: Enrollment and program diligence checklist
Use it before a campaign, before signing a program, and before an investor visit. The items come from the case.
- [ ] Customer consent and data-access authorizations are on file for every device.
- [ ] The device telemetry online rate is measured before the season starts, not after the first event.
- [ ] Installer contract terms are read, including clawbacks if a customer leaves early.
- [ ] Battery backup-reserve settings are agreed with each customer. In the case, customers keep 20 percent of storage as backup.
- [ ] The baseline method is written in the contract, with its adjustment. In the case, the adjusted baseline was a clause the data science lead fought for.
- [ ] Event limits are known: hours, number and notice.
- [ ] Settlement timing is known, and so is the data the utility will deliver to support it. In the case, settlement comes 60 days after the season ends.
- [ ] Double-payment and priority clauses are read against every other revenue line you plan.
- [ ] Program cap and headroom are tracked. In the case, the cap is 60 MW nominated and the headroom is 2.4 MW.
- [ ] Cybersecurity requirements are listed and costed.
- [ ] Churn is reported by cohort, so a bad installer or offer shows up in months, not years. In the case, expected churn is 5 percent a year for batteries and 15 percent a year for thermostats.
A last test for each item: who owns it, and when was it last checked. An item with no owner is not done.