Tool 1: Inspection Readiness Check-List by Protocol
An inspection team usually works by protocol: a set of questions for one program, answered from records, interviews and a visit to the field. The check-list below covers six programs. The integrated inspection in the case used protocols on three of them (integrity management, operator qualification and control room management) and on records, which run through every section. Run it a few weeks before a planned inspection and again after any change in the program. A cross on any line means a record to find or a gap to close before the team arrives.
Integrity management
- A written integrity management program exists and describes the method used to identify high consequence areas.
- The program contains all of the elements the rule requires: HCA identification, a baseline assessment plan, threat identification with data integration and risk assessment, a direct assessment plan where used, remediation, continual evaluation, confirmatory direct assessment where used, preventive and mitigative measures, performance measures, recordkeeping, management of change, quality assurance, a communication plan, procedures to give the program to PHMSA and state authorities on request, procedures that limit environmental and safety risk during assessments, and a process for newly identified HCAs.
- The baseline plan lists the threats, the methods, a schedule and the risk factors behind the schedule.
- Every assessment used is one of the allowed methods: in-line inspection, pressure testing, spike hydrostatic testing, excavation and direct examination, guided wave ultrasonic testing, direct assessment for external corrosion, internal corrosion or stress corrosion cracking, or other technology with advance notice to PHMSA.
- Each HCA segment has a reassessment date, and the date is inside the maximum interval of 7 calendar years. Write down how the years are counted. The rule text does not say, and the case dates each reassessment in the same month seven years later, a conservative reading that is the case's own.
- If a longer interval is used, the stress-level table and the confirmatory direct assessment steps are documented. The case does not use the longer intervals.
- Anomalies are acted on promptly. The date of the discovery determination is recorded and falls no later than 180 days after the assessment unless that was impracticable, in which case PHMSA was told. Immediate repair conditions led to a pressure reduction or a shutdown until repair. One-year and monitored conditions are on a tracked list.
Operator qualification
- Covered tasks are identified in writing: activities on a pipeline facility that are operations or maintenance tasks, performed as a requirement of Part 192, that affect the operation or integrity of the pipeline.
- Each evaluation is a documented process: a written or oral examination, a work performance history review, observation on the job, during on-the-job training or in simulations, or another form of assessment.
- Qualified means evaluated and able to perform the assigned covered tasks and to recognize and react to abnormal operating conditions. The program says what an abnormal operating condition is for each task.
- An unqualified individual works only when directed and observed by a qualified one.
- The program evaluates anyone whose performance may have contributed to an incident or who may no longer be qualified.
- The reevaluation interval is written down for every task. The rule sets none, so the interval is the operator's choice and the team must be able to explain it.
- Significant changes to a program already verified are notified to PHMSA or the participating state agency.
- Records show who is qualified, for which tasks, the dates of current qualification and the methods. Current records are kept while the individual performs the task; prior records, and records of people no longer doing covered tasks, are kept for five years.
- Contractors: the check of a contractor individual's qualification is made before each job, not only when the contractor is hired.
Control room management
- First test the scope: a controller who monitors and controls all or part of a pipeline through SCADA brings the operator under the full set of written procedures. A distribution-only operator with fewer than 250,000 services, or a transmission operator without a compressor station, needs only the procedures for paragraphs (d), (i) and (j). Count services for the operator as a whole.
- Roles and responsibilities are written down.
- Adequate information: point-to-point verification is done, and the manual operation plan and backup SCADA are tested every year, at most 15 months apart.
- Fatigue mitigation: shift schedules allow eight hours of continuous sleep, controllers and supervisors are educated and trained, and a maximum hours-of-service limit is set and may be exceeded only in an emergency.
- Alarm management: safety-related alarms are reviewed; the monthly review of points taken off scan, inhibited, false or forced is done and documented; set-points, the alarm plan and controller workload are checked every year, at most 15 months apart.
- Training is reviewed every year, and team training is in place.
- Records show compliance and any deviation, with documentation that the deviation was necessary for safe operation. The rule names no retention period.
Distribution integrity
- The plan shows knowledge of the system and a plan to gather missing information.
- Threats are identified across the eight categories: corrosion (including atmospheric corrosion), natural forces, excavation damage, other outside force damage, material or welds, equipment failure, incorrect operations and other issues that could threaten integrity.
- Risks are evaluated and ranked.
- Measures to reduce risk include an effective leak management program, unless all leaks are repaired when found.
- Performance measures are tracked: hazardous leaks eliminated or repaired by cause and by material, excavation damages, excavation tickets and total leaks eliminated or repaired by cause.
- The whole pipeline is re-evaluated at least every five years, and four of the measures are reported each year in the distribution annual report and to the state authority where it has jurisdiction.
- Records that demonstrate compliance are kept for at least 10 years, including copies of superseded plans.
Damage prevention
- The operator takes part in the one-call system for each place where it has buried pipe, and tickets are answered inside the time the program sets.
- Locate marks are checked against the records of the pipe before and after an excavation. A mark that is off the pipe is a finding for the locating contractor and a lesson for the plan.
- Excavation damages are logged by cause, and each is reviewed with the damage prevention supervisor.
- For rules beyond the federal ones, read the state's current requirements with counsel.
Reporting
- The call to the National Response Center is made at the earliest practicable moment and no later than one hour after confirmed discovery. The notice is revised or confirmed within 48 hours.
- The written incident report is filed on the right form within 30 days of detection.
- The annual report is filed by 15 March for the preceding year.
- A safety-related condition is reported in writing within the deadline that counts from the determination and from the discovery. See the calendar in Tool 2.