Free to print: Tool 1: Lease and Permit Check-List, from The Geothermal Handbook.
This page is free and needs no sign-up. It reproduces material from The Geothermal Handbook by Julian R. Sterling so you can print it or keep it open while you work.
To print it, use your browser's print button. Figures are as stated in the book; check the official source before relying on any of them.
Purpose: to keep the sequence of approvals visible from the lease sale to commercial operation. Use it as a living list, with a date and an owner beside each line. The permitting and land manager owns it, and the project analyst keeps the dates in the project file. Chapters 3 and 5 explain each step.
Copy the list below and add a status column of your own.
How to use it: review the list at the start of every month and before every board meeting. A line is closed only when the document is in the file, not when someone says it was filed. Check the order too, because some steps cannot start before an earlier one is complete. A gradient hole cannot be drilled before the notice of intent to explore, and a rig cannot move before the drilling permit of that well. Keep the list in one place that the whole team can read. Add the name of the BLM field office staff member or state office that handles each step, by role, so a late response is chased early.
In the case, the leases took effect on 1 February 2022 and gradient holes were drilled under a notice of intent to explore in the summer of 2022. Lease 1 holds the Phase 2 pilot, and the plant, wells and pipelines sit on lease 2 and lease 3. The 24-mile transmission line crosses BLM land under a right-of-way.