Free companion page

Companion page: The Geothermal Handbook

Free to print: Tool 1: Lease and Permit Check-List, from The Geothermal Handbook.

This page is free and needs no sign-up. It reproduces material from The Geothermal Handbook by Julian R. Sterling so you can print it or keep it open while you work.

To print it, use your browser's print button. Figures are as stated in the book; check the official source before relying on any of them.

Tool 1: Lease and Permit Check-List

Purpose: to keep the sequence of approvals visible from the lease sale to commercial operation. Use it as a living list, with a date and an owner beside each line. The permitting and land manager owns it, and the project analyst keeps the dates in the project file. Chapters 3 and 5 explain each step.

Copy the list below and add a status column of your own.

How to use it: review the list at the start of every month and before every board meeting. A line is closed only when the document is in the file, not when someone says it was filed. Check the order too, because some steps cannot start before an earlier one is complete. A gradient hole cannot be drilled before the notice of intent to explore, and a rig cannot move before the drilling permit of that well. Keep the list in one place that the whole team can read. Add the name of the BLM field office staff member or state office that handles each step, by role, so a late response is chased early.

  1. Nominate or identify the lands and read the sale notice for the parcels you want.
  2. Set the bonus bid ceiling from the exploration plan, not from the last sale.
  3. Pay the bonus and first rental on the leases won, and record the effective date.
  4. Calendar the primary term and every annual rental date.
  5. File a notice of intent to explore before gradient holes or other exploration work.
  6. Confirm the NEPA level of review for each step: categorical exclusion, environmental assessment or environmental impact statement.
  7. Check wildlife constraints on the parcels, for example sage-grouse habitat in the Great Basin, and the timing limits that follow.
  8. Complete the survey of cultural resources and record the consultation with tribal interests.
  9. Secure state water rights from the state engineer for drilling water and, if the plant needs it, for cooling.
  10. Obtain a geothermal drilling permit for each well before the rig moves.
  11. Agree the seismic monitoring plan and the traffic light protocol with the BLM before any stimulation.
  12. File the utilization plan for the plant and its well field.
  13. Obtain the facility construction permit and the site license for the plant before any construction or testing.
  14. Apply for the right-of-way for the transmission line and the pipelines that cross federal land.
  15. Obtain state and county permits for the plant, the line and the roads.
  16. Track the interconnection request and the interconnection agreement.
  17. Obtain the commercial use permit before commercial operation.
  18. Set up the royalty and rental reporting so the first payment after production is on time.

In the case, the leases took effect on 1 February 2022 and gradient holes were drilled under a notice of intent to explore in the summer of 2022. Lease 1 holds the Phase 2 pilot, and the plant, wells and pipelines sit on lease 2 and lease 3. The 24-mile transmission line crosses BLM land under a right-of-way.