3. The grid connection request checklist
A grid connection starts with a load request to the utility. This checklist is general practice; utilities publish their own forms and the form always wins.
- Site address, parcel and the host's written consent to the application.
- Requested load in kW, the number and rating of chargers, and any power management cap you intend to rely on.
- Phasing: the load you need at opening and the load you may need later.
- A site plan showing the proposed equipment, the point of connection, trenching routes and any existing utility easements.
- A single-line diagram of the electrical design, from the utility connection through switchgear to the chargers.
- A construction and energization schedule, with the dates by which you need the transformer and service in place.
- Contacts: your grid and interconnection manager, the electrical engineer of record, and the host's asset manager.
- Make-ready eligibility: whether the utility has a program that funds part of the work, what it covers, and what the application deadline is.
- The utility's reply: the load letter, its date, the capacity it confirms and the conditions attached.
In the case, Tallowmere Power issued its load letter on 22 April 2024 and confirmed capacity for 1,500 kW. Its make-ready program funded the transformer and service line, $240,000, which stayed utility property. Chapter 5 follows the whole request.