Tool 2: RUS loan application check-list
Program facts, as read on the USDA Rural Development page for the Electric Infrastructure Loan and Loan Guarantee Program (last modified 19 March 2026):
- Most retail and power supply providers serving qualified rural areas may apply, cooperatives included.
- Loans finance distribution, sub-transmission and headquarters facilities, maintenance, upgrades, expansion, replacement, energy efficiency and renewable energy systems. Loan guarantees also cover generation and transmission.
- Up to 100 percent of a construction work plan may be financed.
- Loan guarantees funded by the Federal Financing Bank and Treasury rate loans carry a rate fixed at each advance at the daily Treasury rate plus one eighth of one percent.
- Hardship loans are fixed at 5 percent for up to 35 years, at the agency's discretion, for economically distressed areas or areas recovering from events such as natural disasters.
- Repayment generally may not exceed the useful life of the facilities financed, with a maximum of 35 years.
- Applications are accepted all year, from 1 October to 30 September.
- A general field representative confirms whether a service area qualifies as rural.
- The program rests on the Rural Electrification Act of 1936, as amended.
The check-list below is general practice; the lender's own instructions control.
- Confirm with the general field representative that the service area qualifies as rural.
- Approve the construction work plan by board resolution and record the date. In the case the board approved a $96,000,000 plan on 18 August 2026.
- Separate the items by category: substations $28,000,000, line rebuilds $44,000,000, meter replacement $14,000,000 and new services $10,000,000.
- Decide the amount to request and the share to fund from general funds. In the case the request is $76,800,000, 80 percent, and $19,200,000 comes from general funds.
- Build the long-range financial forecast and test every year against the ratios of Tool 1.
- Gather audited statements, the wholesale power contract, the bylaws, the rate schedule and the most recent board minutes on rates.
- Check existing loan documents for limits on new debt and liens.
- File the application and keep a log of every question from the lender. In the case the cooperative filed on 15 September 2026.
- Plan the advances: one on 1 January of each year in the case.