Free to print: The closing checklist on Calloway Ridge, from How to Read a Construction Loan Agreement.
This page is free and needs no sign-up. It reproduces material from How to Read a Construction Loan Agreement by Julian R. Sterling so you can print it or keep it open while you work.
To print it, use your browser's print button. Figures are as stated in the book; check the official source before relying on any of them.
The table below gathers the commercially important closing items for the case. It is a reading aid, not a complete list.
| Item | Who delivers | Why it matters |
|---|---|---|
| Construction contract | Borrower, Halverson Builders | Price and scope behind the budget |
| Contractor's consent | Halverson Builders | Lender can keep the builder after a default |
| Budget review | Brookline Construction Consultants | Basis for every later draw |
| Guaranties | Sponsor side | Cost, completion and carry support |
| Title policy and survey | Borrower | Priority of the mortgage |
| Mezzanine documents | Tolland Credit Partners | Order between the two lenders |
| Equity reconciliation | Merriden Development | Unlocks the first loan draw |
The last line is the one that changes timing. Most items are delivered at closing. The equity reconciliation is delivered over the months that follow, as the sponsor spends its $34.0 million, and it is the condition that opens the door to the first draw.
Key Takeaway: On Calloway Ridge, the sponsor's $34.0 million must be spent in full before Ashgrove Bank funds its first draw. Equity counts only when it has paid for budget costs, proved by invoices and evidence of payment. Bank lenders also read equity through regulatory capital and concentration guidance, which is why the equity clauses can be harder to move than the credit risk alone suggests.