Free to print: Tool 5: Programme review checklist ; 20. How do the Hudson and Emden formulas differ?, from The Construction Claims Professional.
This page is free and needs no sign-up. It reproduces material from The Construction Claims Professional by Julian R. Sterling so you can print it or keep it open while you work.
To print it, use your browser's print button. Figures are as stated in the book; check the official source before relying on any of them.
Purpose: to test whether a programme can carry an analysis before anyone builds one on it (Chapter 5).
Use a simple sheet with one row per update and one column per check, marked pass, fail or query. An update that fails more than one check is not used as a window boundary without a note saying why.
Both take a percentage of the contract amount and spread it over the contract period. Hudson uses the percentage built into the tender; Emden uses the contractor's actual overhead percentage. In the case, Hudson used the tender percentage of 4.5 percent: 4.5 percent x $412,000,000 / 915 days = $20,262.30 a day, and at 161 days $3,262,230. Emden used the actual 6.0 percent, giving $27,016.39 a day, and at 161 days $4,349,639. Chapter 12 compares them.