Free companion page
Free to print: Part 2: A Master Calendar Template for Any Order, from How to Read a Bank Consent Order.
This page is free and needs no sign-up. It reproduces material from How to Read a Bank Consent Order by Julian R. Sterling so you can print it or keep it open while you work.
To print it, use your browser's print button. Figures are as stated in the book; check the official source before relying on any of them.
Copy the table into a spreadsheet, add one row for every article with a duty, and fill the third column with a named role. Owners in the case are drawn from the Board, the Compliance Committee, the chief executive officer, the chief financial officer, the chief risk officer, the general counsel and the internal audit director.
| Article | Deadline rule | Owner |
|---|---|---|
| Committee formation | A fixed day after the effective date; confirmation goes to the supervisor in writing | The Board |
| Plan submission | A fixed day after the effective date; the plan goes for a statement of no supervisory objection | Chief executive officer |
| Plan adoption | Starts when the supervisor's letter arrives, not when the plan is sent | The Board |
| Recurring progress report | After each committee meeting, with a set lag; the report goes to the Board | Compliance Committee |
| Board transmittal | After the Board's next meeting, with comments added; the report goes to the supervisor | General counsel |
| Capital plan and ratios | A plan by one day; ratios reached by a later day and kept while the order stands | Chief financial officer |
| Restrictions with prior request | In force at once; each action needs a request made a set time before it | Chief risk officer and chief financial officer |
| Audit and validation | An audit program by a fixed day; validation reports follow once the work is done | Internal audit director |
Two habits make the template useful. First, write the trigger of every clock in the second column: the effective date, a letter, a meeting or a completed task. Most missed dates come from a wrong trigger, not from slow work. Second, add a column of your own for the date after any written extension, and never overwrite the original date, so the order's text and the extended date can both be seen. Chapter 10 explains what follows a missed date.