Time-based versus energy-based availability, exclusions, liquidated damages, and how to model them
The availability guarantee in a wind turbine service agreement is a promise worth real money, but only if you read the exclusions, the damages rate, and the cap, and only if your energy model does not double count it.
Worked in full in The Onshore Wind Project Finance Handbook by Julian R. Sterling, with every figure reproduced in Excel workbooks.Get the DRM-free PDF, $19.99 →
When a turbine manufacturer maintains a wind farm under a long-term full-service agreement, it usually guarantees that the turbines will be available to run for at least a stated share of the time. If availability falls short, the manufacturer pays liquidated damages; if it beats a higher threshold, it may earn a bonus. The guarantee converts part of the equipment risk into a contractual payment, and it is one of the most negotiated clauses in onshore wind. For the wider financing picture, see how onshore wind project finance works.
The traditional measure counts hours:
Availability = (Period hours - Unavailable hours) / (Period hours - Excluded hours)
The negotiation is about the excluded hours. Typical exclusions are grid outages, balance of plant failures outside the manufacturer's scope, force majeure, curtailment ordered by the grid operator or required by permits, owner-requested stops, scheduled maintenance within an allowance, and weather outside the turbine's design envelope. Every exclusion makes the guarantee easier to meet and widens the gap between the guaranteed number and the downtime that actually reaches the revenue meter.
The more lender-friendly measure weights each hour of downtime by the energy the turbine would have produced:
Availability = Actual energy / (Actual energy + Energy lost to turbine unavailability)
A turbine stopped through a windy week costs far more than one stopped on a calm afternoon. Energy-based availability reflects that, and it rewards a service provider that plans maintenance for low-wind periods. It needs an agreed method for estimating lost energy, usually from nacelle anemometers or neighboring turbines.
The availability loss in an energy model is not one minus the guarantee. In The Onshore Wind Project Finance Handbook, the fictional Prairie Hollow Wind, LLC carries an availability loss of 3.5 percent in its energy estimate. That number starts from the guaranteed turbine availability, adds back excluded downtime that still costs energy, and adds balance of plant and grid downtime. A model that simply copies the guarantee assumes no excluded event ever happens.
Damages are usually calculated as lost energy below the threshold times a contract price per MWh, capped at a share of the annual service fee. The price matters more than most readers expect. In the example's first year, each MWh earns $45.00 of PPA revenue and a production credit of $30.00. A damages rate set at the PPA price alone compensates for roughly three fifths of the real loss during the credit years.
| Year-1 item (example) | Value |
|---|---|
| Full-service agreement fee | $36,000 per MW, or $7.13 million |
| Total operating costs before royalties | $12.00 million |
| Energy revenue (P50) | $31.99 million |
| Production credits (P50) | $21.33 million |
The service agreement is more than half of the operating budget, so its fee, its escalation, and its guarantee shape the whole cost side of the project.
Raising the availability loss from 3.5 percent to 6.0 percent for the whole life of the example project, with no compensation from the manufacturer, lowers the pre-tax equity IRR from 9.87 percent to 8.56 percent and the minimum P50 coverage ratio to 1.37x. A serial defect that takes many turbines down in a single year can hurt coverage more than that uniform stress suggests.
The free Onshore Wind Project Finance Model (Excel) lets you test the availability assumption against debt capacity and returns. The credit side of the same question is in the wind PTC versus ITC choice.
This guide is drawn from The Onshore Wind Project Finance Handbook, following Prairie Hollow Wind, LLC (198 MW) from leased farmland and wind measurement through turbine contracts, the PPA, the production tax credit, sculpted debt, and stress tests.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Onshore Wind Project Finance Model (Excel).
Time-based availability counts hours of downtime; energy-based availability weights each hour by the energy that could have been produced, so downtime in windy hours counts more.
No. Exclusions such as grid outages and balance of plant failures still cost energy, so the modeled loss should be higher than the shortfall implied by the guarantee.
Only if the contract price used for damages includes the credit value. Many contracts use the energy price alone.