An elemental cost plan for a 12 m clear distribution unit, how the rate moves with size and height, and the gap between construction cost and total development cost.

Build a warehouse up from its elements and an illustrative 20,000 m² unit at 12 m clear costs about 556 per m² of gross internal area to construct, roughly 52 per sq ft, including preliminaries and contingency. Add land, fees, finance and letting costs and the all-in development cost is 997 per m², so the construction figure alone covers only 55.8 per cent of what the developer actually spends.

Worked in full in Logistics and Industrial Real Estate by Julian R. Sterling, with every figure reproduced in a free workbook.See the book on Amazon →

"What does a warehouse cost to build?" gets answered with a single rate per square metre, usually from a cost consultant's index. The rate is useful only once you know what is inside it, how it moves with size and height, and what sits outside it. The figures below are illustrative rates, not market data: replace each with your own quantity surveyor's and the structure of the answer holds.

The building and the rates

A single-storey unit of 20,000 m² on a 4.0 hectare site, footprint 200 m by 100 m, clear internal height 12.0 m and eaves at 13.5. One dock door per 1,000 m², so 20 docks at 25,000 each, 1,000 m² of two-storey offices at 1,600 per m², and 12,000 m² of yard and parking at 70 per m².

Elemental construction cost, illustrative rates.
ElementBasisCostPer m² GIA
Substructure and ground slab95 per m²1,900,00095
Steel framerises with height1,400,00070
Roof60 per m²1,200,00060
Wall cladding8,100 m² of wall at 85688,50034
Dock doors and levellers20 at 25,000500,00025
Offices and amenities1,000 m² at 1,6001,600,00080
Mechanical, electrical, sprinklers75 per m²1,500,00075
Yard, parking, externals12,000 m² at 70840,00042
Subtotal9,628,500481
Preliminaries10%962,85048
Contingency5%529,56826
Construction cost11,120,918556

The calculation step by step

Construction per m² = (Σ elements × (1 + prelims)) × (1 + contingency) / GIA

9,628,500 × 1.10 = 10,591,350; × 1.05 = 11,120,918; / 20,000 = 556 per m². Divide by 10.7639 for 51.66 per sq ft. In Excel: =SUM(C2:C9)*(1+10%)*(1+5%)/20000.

Two lines are geometry, not rates. Wall cladding is perimeter times eaves height, 600 m by 13.5 m, so its cost per m² of floor falls as the building gets bigger: a box four times the size has only twice the perimeter. The frame, the cladding and the sprinklers all rise with height. That is why one "rate per m²" cannot be carried from a 5,000 m² unit to a 40,000 m² one.

From construction cost to development cost

All-in development cost on the same unit.
ItemBasisCostPer m² GIA
Constructionabove11,120,918556
Professional fees10% of construction1,112,09256
Land4.0 ha at 1,500,0006,000,000300
Land acquisition costs6.8%408,00020
Finance on land7% for 18 months672,84034
Finance on build7%, half drawn on average, 12 months428,15521
Letting fees15% of the 1,360,000 rent204,00010
Total development cost19,946,005997

At an illustrative rent of 68.00 per m², 1,360,000 a year, the yield on cost is 1,360,000 / 19,946,005 = 6.82 per cent. Capitalised at a 5.75 per cent exit yield the completed unit is worth 23,652,174, a profit of 3,706,169, or 18.6 per cent on cost. The 107 basis points between yield on cost and exit yield is the developer's margin, and it assumes the unit lets on completion; the article on how long a speculative warehouse can stay unlet prices what happens if it does not.

What if: size and clear height

Construction cost per m² GIA by unit size and clear height, same rates.
GIA, m²10.0 m clear12.0 m clear15.0 m clearCladding per m² at 12 m
5,00057859662269
10,00055857359449
20,00054455657434
40,00053454455924

Going from 12 to 15 m clear on the 20,000 m² unit adds 17 per m², 3.1 per cent, while clear height, and with it the storage volume under the haunch, rises by 25.0 per cent. Height is the cheapest volume a developer can build, which is why occupiers pay for it, though not, as the cube-parity argument shows, in proportion.

Small units carry a double penalty: more cladding per m² of floor, and usually a larger office share. Multi-let estates of 2,000 to 5,000 m² units cost visibly more per m² than a big box on the same rates, before any difference in specification.

Reading a cost consultant's rate

Before comparing a quoted rate with this build-up, ask four questions. Is it per m² of gross internal area or of footprint, which differ once there are mezzanine offices? Does it include externals and the yard, 42 per m² here, or only the building? Are preliminaries and contingency inside it, together about 75 per m² on this unit? And does it assume the same clear height and the same dock ratio? A rate that answers none of them cannot be compared with anything.

The common mistake

Quoting the construction rate as the cost of the warehouse. Here it is 556 per m² against 997 all-in: the full cost is 1.79 times construction. A developer who divides rent by construction cost alone sees a 12.23 per cent yield and a project that cannot fail; the true yield on cost is 6.82. Land is 32.1 per cent of the total on this site, and in a supply-constrained location it can exceed construction.

Takeaway

Build the rate from its elements, let geometry carry the size and height effects, then add land, fees, finance and letting before you compare cost with value: 556 per m² to build, 997 to deliver, 6.82 per cent on cost on this illustrative unit. The development sheet in the free workbook for this case takes the same structure through the letting decision and the land value it supports.

Questions readers ask

Why do smaller warehouses cost more per square metre to build?

Because wall area grows with the perimeter while floor area grows with its square. On the same illustrative rates, cladding costs 69 per m² of floor on a 5,000 m² unit and 24 on a 40,000 m² unit, which takes total construction from 596 to 544 per m² at 12 m clear. Small units also tend to carry a larger office share.

How much does extra clear height add to warehouse build cost?

Less than the volume it adds. On a 20,000 m² unit, raising clear height from 12 to 15 m adds about 17 per m², 3.1 per cent of construction cost, through a heavier frame, more cladding and sprinkler changes, while clear height, and with it the usable storage volume, rises by 25.0 per cent.

What is the difference between construction cost and total development cost?

Construction covers the building, externals, preliminaries and contingency. Total development cost adds land and its acquisition costs, professional fees, finance and letting fees. On this illustrative unit construction is 556 per m² and the total 997, so construction is 55.8 per cent of the spend and the yield on cost is 6.82 per cent, not 12.23.

Read the whole case

This article is one calculation from Logistics and Industrial Real Estate. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Also on this site

Reading guide: real estate investing, finance and fund management → · All 1340 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.