Interval-by-interval CfD math worked across all 12 months of a 50 MW wind contract, plus DST alignment, negative-price floors, and Excel calculator.
Every monthly Virtual PPA invoice is built from 672 to 744 hourly ISO intervals, not a simple monthly average price. Here is the exact hourly-to-monthly VPPA settlement formula worked across all 12 months of a 50.0 MW wind contract, including negative-price floors, curtailment caps, and the 15-minute CSV invoice audit.
Worked in full in The PPA Pricing Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
In a properly drafted VPPA, monthly financial settlement is calculated strictly at each hourly (or 5-minute/15-minute) ISO settlement interval and summed across the calendar month:
Monthly_CfD_Buyer = Sum[h]( MAX(0, Meter_MWh_h) x (Adj_LMP_h - Strike_Price) )
Adj_LMP_h = MAX(0, LMP_h) so the buyer never pays more than the fixed strike price during negative-price intervals.Critical billing rule: Never let a developer multiply total monthly MWh by the simple unweighted average monthly LMP. Always verify interval-by-interval SUMPRODUCT matching against public ISO Day-Ahead Hub LMP downloads.
From The PPA Pricing Handbook, Table 1 shows Alderbrook's exact Year 1 monthly settlement ledger across 175,200 MWh P50 generation (reproduced live in the free VPPA Settlement Calculator (Excel)):
| Month | P50 MWh | Hub Capture ($/MWh) | Hub VPPA CfD ($) |
|---|---|---|---|
| January | 16,800 | $49.00 | +$16,800 |
| February | 15,600 | $46.75 | -$19,500 |
| March | 17,400 | $42.00 | -$104,400 |
| April (Peak Outflow) | 16,800 | $39.00 | -$151,200 |
| May | 15,000 | $42.00 | -$90,000 |
| June (Break-Even) | 12,600 | $48.00 | $0 |
| July | 10,200 | $59.50 | +$117,300 |
| August (Peak Inflow) | 10,800 | $61.50 | +$145,800 |
| September | 13,200 | $47.50 | -$6,600 |
| October | 15,600 | $43.50 | -$70,200 |
| November | 15,000 | $45.00 | -$45,000 |
| December | 16,200 | $47.80 | -$3,240 |
| Full Year 1 Total | 175,200 | $46.80 | -$210,240 |
Notice the $297,000 intra-year seasonal cash swing between April (-$151,200 outflow during high spring wind and low shoulder prices) and August (+$145,800 inflow during hot summer peak prices), while bundled RECs add $1,138,800/year ($6.50/REC) for +$928,560 net annual value.
MAX(0, Meter_MWh)).Explore how a Virtual PPA works, review PPA basis risk explained, and download the unlocked free VPPA Settlement Calculator (Excel) to run your own monthly settlement audit.
This guide is drawn from The PPA Pricing Handbook, following Alderbrook Materials Corporation through a complete 12-year, 50.0 MW wind VPPA pricing and governance case.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: VPPA Settlement Calculator (Excel).
Sum the hourly product of contracted metered MWh (floored at zero) times the difference between the floor-adjusted floating ISO LMP and the fixed PPA strike price across all hours in the month.
Wind and solar generation is correlated with hourly prices (wind blows more during cheap overnight hours). Using an unweighted monthly average price ignores diurnal shape and produces a materially wrong invoice.
Without protection, the buyer owes Strike minus the negative LMP (paying more than the strike price). A $0.00/MWh negative-price settlement floor caps payment at the strike price, and a capped zero-settlement economic curtailment clause sets settlement to $0.00 up to an annual MWh cap.
ISOs issue initial settlements within 7 to 14 days and final resettlements 45 to 180 days later. Well-drafted VPPAs bill on initial ISO data and roll minor resettlement deltas onto a later invoice as a clearly labeled true-up within a 12-month lookback window.