Opening value times the discount rate: the part of a value change that needs no judgment, and the identity that must tie to the cent.
The unwind of the discount is the increase in a discounted cash flow value caused by the passage of time alone: every future cash flow is one period closer, so it is discounted one period less. Over a year it equals the opening value times the discount rate. In our case, an equity value of $70.04m at 8.0% unwinds by $5.60m.
The case comes from the Infrastructure Valuation course by Julian R. Sterling, author of The Project Finance Handbook.Get the DRM-free PDF, $19.99 →
If no assumption changes, the value one year later is the opening value, plus the unwind, less the cash distributed during the year:
Closing value = Opening value x (1 + discount rate) - distribution
It is not an approximation. It follows from the definition of a present value with year-end cash flows, and a model must reproduce it exactly.
Saltbrush Solar, fictional, is a 150 MW solar plant with 22 years of life left. Its equity is valued at 31 December 2030 by discounting the distributions to its shareholder at 8.0%.
| Line | US$ m |
|---|---|
| Value at 31 December 2030 | 70.04 |
| Unwind of the discount (8.0%) | 5.60 |
| Distribution received in 2031 | -3.91 |
| Value at 31 December 2031, same assumptions | 71.73 |
| Effect of a merchant price curve 5% lower | -2.48 |
| Effect of a discount rate of 7.75% | 1.59 |
| Value at 31 December 2031 | 70.83 |
The first three lines are mechanical. Discounting the remaining distributions, from 2032, at the same rate gives $71.73m directly: the two routes agree. The last lines are judgment: a new price curve, then a new rate, applied in that order.
A bridge that mixes time and assumptions cannot be reviewed. If the mechanical part does not tie, something changed in the model without anyone deciding it. Once it ties, every remaining movement has an owner: the market adviser for the curve, the valuation committee for the rate.
It is not cash, and it is not outperformance. It is the return the investor required, earned by waiting. In this case the fund required 8.0% and earned 6.72% over the year, because the cut in merchant prices cost more than the lower discount rate gave back. A lower rate also has a price: from then on, the unwind runs at 7.75%.
Every figure is computed by script from the course's running case, Saltbrush Solar, a fictional solar plant, and checked on 19 November 2026. Prices, yields, costs and discount rates are assumptions of the case, not market data. For education, not investment or valuation advice.
26 short video lessons on the valuation of an operating infrastructure asset: operating cash flow, debt service, tax and distributions, the discount rate, contracted and merchant cash flows, multiples and comparables, sensitivities and the valuation bridge. You value a solar plant in Excel, with step files, exercises and a certificate exam ($149).
Multiply the opening value by the discount rate for the period. With several rates or cash flows during the period, it is the closing value with unchanged assumptions, plus the cash paid out, less the opening value.
No. It is the increase in value from the passage of time. Cash comes from the distributions, which reduce the value when they are paid.
In a fixed order kept from one period to the next, each change on top of the previous one, because the effects interact.
This article is one calculation from The Project Finance Handbook. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.
See the course →Free companion files
Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada
Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99