Articles · Construction Surety
How underwriters strip GAAP working capital down to bonding capacity, price a tiered $86.4M bridge bond at 0.62 percent, and cost the four default options when a job fades.
Contract surety underwriters size a contractor's aggregate bond program from adjusted working capital, not headline GAAP equity. Stripping $6,200,000 of disallowed current assets reduces $12,200,000 of working capital to $6,000,000, supporting a $60,000,000 program and a $35,000,000 single-job limit. On an $86,400,000 bridge contract, a tiered rate schedule yields a $539,190 premium (0.62 percent), which vanishes if a single default triggers a $6,040,000 net loss.
Worked in full in The Surety Bond Professional by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback
A surety bond is a three-party credit agreement: the surety guarantees to the project owner (the obligee) that the contractor (the principal) will bid in good faith, finish the contract, and pay subcontractors and suppliers. Unlike casualty insurance, which prices for expected losses across a pool, surety underwriting prices for zero expected loss and backs every program with a General Agreement of Indemnity (GAI) signed by the contractor, affiliated asset entities, and individual owners.
On federal construction contracts, the Miller Act (40 U.S.C. Section 3131) and Federal Acquisition Regulation (FAR) Part 28 require separate performance and payment bonds from corporate sureties listed on U.S. Treasury Circular 570. Circular 570 caps a surety's single-bond underwriting limitation at 10 percent of its capital and surplus unless the excess is protected by coinsurance or reinsurance. In The Surety Bond Professional, Brackwater Surety holds $410,000,000 in policyholders' surplus, giving it a $41,000,000 federal underwriting limit and a $25,000,000 per-account reinsurance retention.
At year-end 2022, Vessmore Paving and Bridge Co. reports $38,250,000 in current assets and $26,050,000 in current liabilities: $12,200,000 of GAAP working capital and $24,100,000 of equity on $140,000,000 of revenue. Before setting a bond program, Brackwater's underwriter removes current assets that cannot reliably fund payroll and suppliers during a cash squeeze:
| Adjustment item | Underwriting rationale | Amount |
|---|---|---|
| GAAP working capital | $38,250,000 current assets - $26,050,000 current liabilities | $12,200,000 |
| Less: Receivables > 90 days past due | Collectibility risk on aged billings | -$1,400,000 |
| Less: Prepaid expenses | Cannot be converted into cash for job costs | -$600,000 |
| Less: Due from shareholders | Related-party receivable | -$900,000 |
| Less: Underbillings (costs in excess of billings) | Excluded in full under case policy (fade risk) | -$2,200,000 |
| Less: Materials inventory | Job-specific or illiquid in distress | -$1,100,000 |
| Adjusted working capital | Total deductions of $6,200,000 | $6,000,000 |
Applying Brackwater's teaching rule of thumb of 10 times adjusted working capital gives Vessmore an initial $60,000,000 aggregate program and a $35,000,000 single-job limit (calibrated against its largest completed job of $28,000,000). Adjusted equity falls by the same $6,200,000, from $24,100,000 to $17,900,000.
Six months later, Vessmore wants to bid an $86,400,000 river bridge while already carrying $31,200,000 in bonded backlog ($117,600,000 combined). To qualify, management lifts adjusted working capital from $6,900,000 at 30 June 2023 to $12,000,000 by injecting a $2,600,000 subordinated shareholder loan and terming out $2,500,000 of its bank revolver into a five-year loan. At 10 times $12,000,000, Brackwater raises the program to $120,000,000 aggregate and $90,000,000 single job, subject to quarterly work-in-progress (WIP) schedules and a cap on shareholder distributions.
The Surety Bond Professional follows Vessmore across three years with ten toolkit worksheets: prequalification grid, surety adjustments, WIP fade analysis, bonding capacity, premium calculator, and default option costing.
Vessmore wins the Callow River bridge at $86,400,000 (estimated cost $79,488,000, 8.0 percent gross margin). The owner requires a 5 percent bid bond ($4,320,000, issued at no separate charge) and 100 percent performance and payment bonds ($86,400,000 penal sum each). Performance and payment bonds are priced together on a declining tiered schedule per $1,000 of contract price:
| Contract price tier | Tier amount | Rate per $1,000 | Tier premium |
|---|---|---|---|
| First $500,000 | $500,000 | $25.00 | $12,500 |
| Next $2,000,000 | $2,000,000 | $15.00 | $30,000 |
| Next $2,500,000 | $2,500,000 | $10.00 | $25,000 |
| Next $2,500,000 | $2,500,000 | $7.50 | $18,750 |
| Balance above $7,500,000 | $78,900,000 | $6.50 | $512,850 |
| Gross bond premium | $86,400,000 | 0.69% | $599,100 |
| Less: 10% account credit | -10.0% | -$59,910 | |
| Net bond premium charged | $86,400,000 | 0.62% | $539,190 |
Then the job fades. Drilled shafts in karst limestone, late steel girders, and overtime push the bridge margin from 8.0 percent at bid to 2.1 percent at 35.0 percent complete, and down to minus 4.0 percent at 59.0 percent complete (with a $3,560,000 full-loss recognition and $4,850,000 of overbillings). After the owner terminates Vessmore on 1 April 2025, $30,480,000 of contract balance remains (including $3,080,000 of retainage) and $6,380,000 of payment bond claims are allowed across 23 subcontractors and suppliers.
Brackwater's claims manager prices all four performance-bond options side by side: financing Vessmore ($14,500,000), taking over with completion contractor Grindell ($13,860,000 net of a $1,900,000 differing-site-condition claim), tendering Grindell to the owner ($15,790,000), or paying the owner's $15,000,000 demand plus payment claims ($21,780,000). Takeover wins by $640,000. At substantial completion, the actual performance bond loss is $6,760,000 ($36,850,000 completion contract + $1,420,000 consultants + $870,000 liquidated damages - $30,480,000 contract balance - $1,900,000 change order), plus $6,380,000 of payment claims = $13,140,000 gross loss. Recoveries of $7,100,000 ($3,000,000 letter of credit, $2,850,000 auctioned equipment, $1,250,000 individual indemnitor settlement) cut the final net loss to $6,040,000, more than eleven times the $539,190 premium.
The trap: Reading overbillings without checking margin fade. At 31 December 2024, Vessmore had billed $55,900,000 against $51,050,000 of earned revenue, a $4,850,000 overbilling that looked like strong cash collection on the surface. In reality, job fade had already pushed estimated cost to $92,560,000 against an $89,000,000 contract, meaning Vessmore was spending future cash to plug current losses (job borrow) while unpaid suppliers began calling the surety.
Figures verified November 23, 2026. Brackwater Surety, Vessmore Paving and Bridge Co., and all financial figures, multiples, and rates are fictional teaching assumptions from The Surety Bond Professional, not industry norms or legal, accounting, or insurance advice.
Underwriters start from GAAP working capital and disallow illiquid or uncertain current assets such as receivables over 90 days past due, prepaid expenses, shareholder loans, inventory, and often underbillings. A common teaching benchmark sets the aggregate bond program at roughly 10 times adjusted working capital (for example, $6,000,000 adjusted working capital supporting a $60,000,000 aggregate program and a $35,000,000 single-job limit).
Contract surety bonds are priced on a sliding tiered rate per $1,000 of contract price, so larger contracts pay a lower effective percentage. In the worked $86,400,000 bridge case, tiered rates from $25.00 down to $6.50 per $1,000 produce a $599,100 gross premium, or $539,190 (0.62 percent of the contract price) after a 10 percent account credit.
Insurance prices for expected losses across a pool of policyholders. A surety bond is a three-party credit extension backed by a General Agreement of Indemnity: the surety expects zero net loss and holds contractual rights to demand collateral, take over contract balances, and recover losses from corporate and personal indemnitors.
For federal construction bonds required under the Miller Act (40 U.S.C. Section 3131) and FAR Part 28, corporate sureties must appear on Treasury Circular 570. Each surety's single-bond underwriting limitation is generally 10 percent of its capital and surplus unless the excess is protected by approved coinsurance or reinsurance.
Sixteen chapters and three appendices covering the Miller Act, FAR Part 28, Treasury Circular 570, contractor financial statements, WIP schedules, bonding capacity, pricing, indemnity, default options, takeover agreements, payment bond claims, and thirty interview questions.
DRM-free PDF, $19.99 · Paperback, $32.99 · Apple Books · Google Play