S&OP Capacity Check Example: Rough-Cut Capacity Planning (RCCP) Worked

Step-by-step Bill of Resources capacity math, diagnosing a 112.4% CNC machining overload, and pricing pre-build vs. overtime vs. lost margin.

A supply plan that has never been tested against physical machine hours is a wish list. Rough-Cut Capacity Planning (RCCP) combines a verified Bill of Resources with empirical Utilization and Efficiency factors to catch bottleneck overloads months ahead of peak season and price the lowest-cost executive trade-off.

Worked in full in The Sales and Operations Planning Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

The Three Core RCCP Capacity Check Formulas

During Step 3 (Supply Review) of every monthly S&OP cycle, Operations tests whether the aggregate monthly supply plan fits inside the net productive hours of critical bottleneck work centers before releasing orders to MRP:

Available Effective Capacity = Units x Shifts x Hours/Shift x Workdays x Utilization x Efficiency

Required Capacity (Work Center i) = Sum_j ( Planned Production_j x BoR_(i,j) )

Load Ratio (%) = ( Required Capacity / Available Effective Capacity ) x 100

Always derive Utilization and Efficiency from trailing shop-floor ERP clocks rather than optimistic machine nameplate ratings. In The Sales and Operations Planning Handbook, Creekside Thermal Controls runs 20 workdays, 2 shifts per day, 8 hours per shift, at verified 90.0 percent Utilization and 95.0 percent Efficiency (an 85.5 percent combined effective factor, yielding 273.6 effective hours per machine/station per month).

Worked Example: Creekside's August Peak Capacity Check

In August, seasonal commercial HVAC demand calls for 12,000 Standard Valves (0.20 CNC hrs, 0.00 Elec hrs, 0.08 Test hrs), 6,000 Smart Actuators (0.35 CNC, 0.40 Elec, 0.10 Test), and 1,500 Hydronic Manifolds (1.10 CNC, 0.30 Elec, 0.30 Test):

Bottleneck Work CenterAvail Eff HrsRequired Hrs (Aug)Load Ratio & Status
CNC Machining (20 machines)5,472.0 hrs6,150.0 hrs112.4% OVERLOAD (-678.0 hrs)
Electronic Assembly (12 stations)3,283.2 hrs2,850.0 hrs86.8% SAFE (+433.2 hrs)
Hydrostatic Test & QA (8 stands)2,188.8 hrs2,010.0 hrs91.8% TIGHT (+178.8 hrs)

Verify CNC Machining Required Hours: (12,000 x 0.20) + (6,000 x 0.35) + (1,500 x 1.10) = 2,400 + 2,100 + 1,650 = 6,150.0 hours against 5,472.0 available regular hours, exposing an exact 678.0-hour deficit.

Pricing the Three Executive Trade-Offs (Options A, B, and C)

Operations never escalates an unpriced red bar to Executive S&OP. Ahead of Pre-S&OP, Manufacturing and Finance price three mutually exclusive solutions:

When demand exceeds all feasible supply levers, allocate scarce machine hours using Gross Margin per Bottleneck Hour: Smart Actuators ($190 / 0.35 = $542.86/CNC hr, Rank 1), Standard Valves ($95 / 0.20 = $475.00/CNC hr, Rank 2), and Hydronic Manifolds ($400 / 1.10 = $363.64/CNC hr, Rank 3).

Run this exact RCCP check on your own plant using the free Monthly S&OP Plan Calculator, and see how it integrates with the 5-step S&OP process and 20-day monthly calendar and reconciling the S&OP demand plan to the GAAP financial forecast.

Questions practitioners ask

How do you calculate Rough-Cut Capacity Planning (RCCP) load?

Multiply each product family's planned monthly production by its Bill of Resources hours per unit for a critical work center, sum across all families to get Required Hours, and divide by Available Effective Capacity (Units x Shifts x Hours/Shift x Workdays x Utilization x Efficiency).

What is a safe RCCP capacity utilization target?

Most manufacturing plants target 85 to 90 percent load as optimal and flag 90 to 95 percent as a tight watch zone. Load above 95 percent leaves insufficient buffer for breakdowns and changeovers and should trigger a formal Pre-S&OP resolution scenario.

When is pre-building inventory cheaper than running overtime?

Pre-building wins whenever the short-term inventory carrying cost (Unit Cost x Carrying Rate x Hold Months / 12) is lower than the overtime premium per unit (BoR Hours x Overtime Rate/hr). At Creekside, pre-building 2,500 Standard Valves saved $35,875 compared to running all 678.0 deficit hours on weekend overtime.

How do you allocate capacity when demand exceeds maximum plant output?

Rank unconstrained product families by Gross Margin (or Contribution Margin) per Bottleneck Hour rather than unit margin alone, while honoring firm MTO contractual obligations and strategic account commitments.

Read the full handbook

This guide is drawn from The Sales and Operations Planning Handbook, following Creekside Thermal Controls through a complete 12-month S&OP transformation.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Monthly S&OP Plan Calculator (Excel).

Illustrative figures computed by the book model; Creekside Thermal Controls, Inc. is fictional. Education only, not legal, accounting, or external audit advice.