How to Build a Decommissioning Cost Estimate for a Utility-Scale Solar Farm
A solar decommissioning cost estimate prices every removal and restoration task as quantity times unit cost, adds contingency and project management, and then subtracts a salvage credit that the permitting authority may discount and cap. This guide walks through the method line by line and shows how the number moves at the first update.
What the estimate is used for
The same set of quantities feeds at least four different numbers, and confusing them is a frequent source of disputes. The county or locality uses the estimate to size financial assurance. The owner's accountants use the gross cost, without salvage, to measure the asset retirement obligation under ASC 410-20 in principle. Lenders and tax equity investors test it in due diligence, and acquirers price it into the purchase price and the representations.
Build the estimate once, on one set of quantities, and label each convention: gross or net, today's dollars or escalated, salvage at full value or after the haircut.
Start from the obligation, not the equipment list
The scope of the estimate is set by whatever creates the obligation: a county ordinance or conditional use permit, a state statute, the landowner lease, or a federal right-of-way grant. Those documents decide how deep foundations and piles come out, which buried cables may stay, whether roads are removed or left at the landowner's election, and what restoration standard applies. Some rules also fix who prepares the estimate: in Virginia, section 15.2-2241.2 in principle provides for a Virginia-licensed professional engineer with decommissioning experience, engaged by the applicant and approved by the locality, and lets the estimate account for net salvage value.
In the Harrowgate case, the Marlow County ordinance is a case assumption, not a real rule: removal of all above-ground equipment and of foundations and buried items to 4 feet below grade, restoration to the prior land use, an engineer's estimate updated every five years, and assurance equal to the net cost plus a 10% county administration allowance. Read the actual text that governs your site and confirm it with counsel and the county before you price anything.
The line items
Each line is a quantity, a unit and a unit cost. Quantities come from the as-built drawings and the equipment schedules; unit costs come from contractor quotes, cost databases or recent comparable work. The unit costs and scrap prices used for Brindle Flats, a 120 MWac / 156 MWdc single-axis tracker plant with 346,700 modules on 940 acres fenced, are teaching assumptions, not market quotes.
| Line item | Quantity | Unit cost | Amount |
|---|---|---|---|
| Mobilization and demobilization | 1 | $400,000 | $400,000 |
| Module removal and packing (per module) | 346,700 | $3.10 | $1,074,770 |
| Module transport and recycling (per module) | 346,700 | $14.00 | $4,853,800 |
| Tracker dismantling (per MWdc) | 156 | $9,500 | $1,482,000 |
| Pile extraction (per pile) | 62,400 | $18.00 | $1,123,200 |
| Inverter skid removal (per skid) | 40 | $9,000 | $360,000 |
| Cable and conduit removal to 4 feet (per MWac) | 120 | $6,000 | $720,000 |
| Fence removal (per mile) | 9.2 | $14,000 | $128,800 |
| Project substation dismantling | 1 | $380,000 | $380,000 |
| Road removal, decompaction and seeding (per acre) | 940 | $1,150 | $1,081,000 |
Module transport and recycling is the largest line, and it carries a regulatory question as well as a price. Under RCRA, some end-of-life modules are not hazardous waste while others contain enough metals, lead for example, to meet the definition; in principle the generator makes the hazardous waste determination by testing or by knowledge. EPA is working on a universal waste proposal for solar panels, but nothing is final. Price the route you can use today and confirm the classification with the agency.
Piles and trackers are the next judgment calls. Count piles from the as-built record, not the design set, and price tracker dismantling per MWdc so the line scales with the array. Road removal, decompaction and seeding are priced per fenced acre because restoration to the prior land use covers the whole footprint. On top of the subtotal of $11,603,570, the case adds a 10% contingency ($1,160,357) and 6% for engineering and project management ($696,214), for a gross cost of $13,460,141, or $112,168 per MWac.
The salvage schedule
Salvage belongs on its own schedule, as tonnage times a scrap price index, so that a reviewer can move prices without touching the removal costs. At commercial operation Brindle Flats carried ferrous scrap from piles and trackers of 15,600 tonnes at $260 ($4,056,000), aluminum cable at $342,000 and copper at $306,000, for total salvage of $4,704,000. The estimate gives no resale value to used modules: a buyer may exist at the time, but a credit that depends on a secondary market fifteen or thirty years out is hard to defend in front of a county.
Because scrap prices swing, counties often discount or cap the credit. Marlow County allows 75% of estimated salvage, capped at 50% of gross cost. That gives a credit of $3,528,000, a net cost of $9,932,141, an administration allowance of $993,214 and a notional assurance amount of $10,925,355, since the first posting falls at the Year 10 update. Our article on decommissioning bonds and financial assurance covers how that amount is secured.
The book goes further: the full Harrowgate case, every table and a live Excel model are in The Energy Project Decommissioning Handbook. Try your own numbers with the free Decommissioning Cost Estimate Model.
Worked example: the Year 10 update
Marlow County requires the first posting of assurance for solar at the Year 10 update, so the update is the number that ties up capital. Dunmore Engineering rebuilt the estimate and explained the change in a bridge, one driver at a time.
- Start from the Estimate at COD at $10,925,355.
- Cost inflation (index 1.30): every unit cost is escalated, +$4,441,846 to $15,367,201. This is the step that a mechanical update would stop at, and it would overstate the requirement.
- As-built pile count: the record shows 64,100 piles against 62,400 in the design, -$11,231 to $15,355,970. The quantity rose, yet the step reduces the amount, because the extra piles also add steel to the salvage schedule.
- Recycling re-quote: the recycling fee per module, $18.20 after indexing, was re-quoted at $12.00, -$2,742,812 to $12,613,158.
- Scrap prices: steel moved from $260 to $300 per tonne, copper from $6,800 to $8,900 and aluminum cable from $900 to $1,050, -$649,325 to $11,963,833.
- Result: gross $15,050,862, salvage $5,566,200 (37.0% of gross), credit $4,174,650, net $10,876,212 and required assurance $11,963,833, a total change of +$1,038,478 since commercial operation.
Indexing alone is not an update: fresh quotes on the dominant lines and current tonnage change the answer more than any escalation rate.
Stress the salvage before the county does
Run the update again with scrap prices down 40 percent and the recycling fee up 30 percent. At Brindle Flats the required assurance rises to $15,393,280, up +$3,429,447, and the 50% cap does not bind. Knowing that range early lets the owner choose an instrument with headroom.
Updating and documenting the estimate
An estimate is only as good as its file. Keep the source of each quantity, the date and basis of each unit cost, the scrap index and date, and the escalation index used. Several regimes set the update cycle in principle. Texas, under HB 3228 of 2025 for solar power facility agreements entered into on or after September 1, 2025, requires a first updated cost and salvage estimate by the 10th anniversary of the commercial operations date and then at least every five years. Confirm the current statute text with counsel before relying on it.
The trap: updating by index alone and carrying design quantities forward. The county then holds a number that nobody can trace to the site, and the first serious review reopens the whole estimate.
To build your own estimate with the salvage credit, the assurance amount and the five-year update already laid out, download the free Decommissioning Cost Estimate Model (Excel). The full Brindle Flats case, from commercial operation to the Year 10 bridge, is in The Energy Project Decommissioning Handbook.
Frequently asked questions
Is the decommissioning estimate the same as the asset retirement obligation?
No. In principle ASC 410-20 measures the obligation at fair value from expected cash flows, discounted at a credit-adjusted risk-free rate, and does not net salvage, which is recognized when realized. The assurance estimate is usually in today's dollars and may net a discounted salvage credit.
Should used modules count as salvage?
Only with care: a resale credit depends on a secondary market nobody can quote today. Pricing modules as a recycling cost leaves any resale upside to the owner.
Who should prepare the estimate?
An engineer with decommissioning experience, and where the rule requires it a licensed professional engineer approved by the locality. The owner engages the engineer; the county reviews the result.
How often should the estimate be updated?
On the cycle the governing rule sets, and after any event that changes quantities or prices materially, such as an expansion or a new recycling route.
Sources
- Code of Virginia, section 15.2-2241.2 (decommissioning of solar facilities)
- Texas Utilities Code, Chapter 302 (solar power facility agreements), as amended by HB 3228 (2025)
- FASB Accounting Standards Codification, ASC 410-20, Asset Retirement Obligations
- US EPA, Resource Conservation and Recovery Act: hazardous waste determination (SW-846 Method 1311) and universal waste regulations, 40 CFR Part 273
- The Energy Project Decommissioning Handbook, Chapters 5, 7 and 8 (the Brindle Flats estimate, salvage and Year 10 bridge)
Figures checked on November 25, 2026. The Harrowgate case is fictional.