Decommissioning Bonds and Financial Assurance for Wind and Solar Projects
Financial assurance is the security a county, a landowner or a federal agency holds so that removal and restoration are paid for if the owner does not do the work. This guide covers where the requirement comes from, how the amount is set, what each instrument really costs and when the beneficiary can draw.
What financial assurance secures
A wind or solar project ends with a bill: cranes, demolition crews, haul and disposal, recycling fees, decompaction and seeding. The party that granted the permit or the lease wants that bill paid even if the owner is insolvent, sold, or simply gone by then. Financial assurance answers that risk. It does not reduce the owner's obligation to decommission; it gives the beneficiary a source of funds if the owner fails to perform. The owner remains liable for any shortfall, which BLM's rule states expressly for federal land and which many ordinances and leases also provide.
Where the requirement comes from
Requirements stack. A single project can owe assurance to a county under its ordinance or permit, to landowners under a statute or the lease, and to a federal agency on public land. A few examples, stated in principle:
- Texas: Utilities Code Chapters 301 (wind) and 302 (solar), amended in 2025 by HB 3228, and the new Chapter 303 added by HB 3809 for battery storage, require financial assurance in landowner agreements entered into on or after September 1, 2025, covering removal, recycling or disposal and restoration, reduced by estimated salvage value. Wind estimates are updated at least every five years; solar has a first update by the 10th anniversary of commercial operations, then at least every five years.
- Virginia: section 15.2-2241.2 of the Code lets a locality require a decommissioning agreement with assurance for a solar facility. It names certified funds, cash escrow, bond, letter of credit or parent guarantee, and caps the amount at the projected cost plus a reasonable allowance for the locality's administrative costs on default, plus an annual inflation factor.
- Illinois: under the Renewable Energy Facilities Agricultural Impact Mitigation Act (505 ILCS 147), owners of commercial wind and solar facilities sign an Agricultural Impact Mitigation Agreement with the Department of Agriculture covering deconstruction and phased financial assurance.
- Federal land: 43 CFR 2805.20, as amended by the 2024 Renewable Energy Rule, requires a performance and reclamation bond before BLM issues a Notice to Proceed. Outside designated leasing areas the minimums are USD 10,000 per acre to be disturbed for solar, and USD 10,000 per turbine under 1 MW or USD 20,000 per turbine of 1 MW or more for wind. The amount rests on a reclamation cost estimate, which may consider salvage, and BLM may require an increase or decrease on review.
Many counties add their own conditions. Confirm the current text with counsel, the county or the agency.
The amount formula
Most rules converge on the same arithmetic: gross cost (line items, contingency, engineering and project management) less a salvage credit, plus an allowance for the beneficiary's own costs. The fictional Marlow County ordinance in the Harrowgate case sets a 10% contingency, 6% for engineering and project management, a salvage credit of 75% of estimated salvage capped at 50% of gross cost, and a 10% administration allowance on the net. The haircut protects the county against a scrap price drop between the estimate and the work; the cap stops a high-steel project from posting almost nothing.
At Tallow Creek Wind, 30 turbines of 2.3 MW in Operating Year 18, the gross cost is $8,988,608 and estimated salvage $2,693,700 (30.0% of gross). The credit is $2,020,275, the net $6,968,333, the administration allowance $696,833 and the required assurance $7,665,166, or $255,506 per turbine. The owner's own view of the net cost, with full salvage and no allowance, is $6,294,908. Both numbers are legitimate; they answer different questions. How the underlying estimate is built is covered in our article on building a solar decommissioning cost estimate.
The book goes further: the full Harrowgate case, every table and a live Excel model are in The Energy Project Decommissioning Handbook. Try your own numbers with the free Decommissioning Cost Estimate Model.
The instruments
| Instrument | Provider | Main cost | What it ties up |
|---|---|---|---|
| Surety bond | Surety company | Annual premium | Indemnity from owner or parent, sometimes collateral |
| Standby letter of credit | Bank | Annual fee | Credit capacity under the owner's facilities |
| Cash escrow or trust | Owner | Return given up on the cash | The full amount in cash |
| Parent guarantee | Parent company | Little direct cost | The parent's balance sheet, if the beneficiary accepts it |
The beneficiary chooses which forms it accepts. A parent guarantee works only when the county or landowner is willing to take the guarantor's credit, which in practice means a strong, rated parent. In the case, Harrowgate's parent is unrated, and Marlow County does not accept a parent guarantee.
Worked example: what each form costs on Brindle Flats
- The required assurance at the Year 10 update is $11,963,833.
- Letter of credit: a fee of 1.75% a year gives $209,367 a year.
- Surety bond: a premium of 0.85% plus collateral of 10% ($1,196,383), whose carrying cost is the gap between an 8% cost of capital and the 4% the collateral earns, for $149,548 a year in total.
- Cash escrow: the same gap applied to the full amount gives $478,553 a year.
- Over the 25 years remaining, discounted at 8% on a flat amount, the present values are $2,234,946 for the letter of credit, $1,596,391 for the bond and $5,108,446 for escrow.
The bond wins in the case, but the ranking is sensitive to the premium, the collateral percentage and the owner's cost of capital. A letter of credit also consumes credit capacity, a cost the fee does not show. Run the comparison with your own quotes; the fees, premium and rates here are teaching assumptions, not market quotes.
Keeping the amount current
An instrument sized once and left alone drifts away from the requirement. Tallow Creek posted a surety bond of $6,350,000 at its Year 15 update; the Year 18 update shows a gap of $1,315,166 against the new required amount. The fix is a bond rider or an additional instrument, agreed with the county before the deadline, and a covenant in the owner's calendar that ties each estimate update to an assurance review. Updates can also reduce the amount, and a good agreement lets the owner request the reduction.
Draw conditions and release
The beneficiary draws on default under stated conditions, so the drafting decides how useful the security is. Typical triggers are abandonment as defined in the ordinance (for example a stated period without generation), failure to start or complete removal within the time allowed after notice, and failure to renew or replace an expiring instrument. That last trigger matters most for letters of credit and bonds with fixed terms: the beneficiary should be able to draw if a replacement is not delivered before expiry. Release normally follows final inspection and landowner sign-off, sometimes in stages as work is completed. Confirm the draw and release mechanics with counsel for each beneficiary.
The trap: reading the posted amount as the cost of decommissioning. The assurance number includes a haircut on salvage and an administration allowance, and it can be well above what the work will cost the owner. Price the asset on the owner's net cost, and the assurance on its carrying cost.
To compute the assurance amount from your own estimate, with the salvage credit and the five-year update, download the free Decommissioning Cost Estimate Model (Excel). The full instrument comparison and the Tallow Creek bond gap are in The Energy Project Decommissioning Handbook.
Frequently asked questions
Does salvage value reduce the required assurance?
Often, but not always in full. Several statutes and ordinances allow estimated salvage to reduce the amount, and many apply a discount, a cap, or both, because scrap prices move.
Can the owner choose the instrument?
Within the forms the beneficiary accepts. The rule or agreement lists the acceptable forms; the owner then compares their real cost, including collateral and credit capacity.
Can the assurance amount go down?
Yes, where the rule ties the amount to an updated estimate. BLM, for example, may require an increase or a decrease after review, and many local agreements work the same way on each update.
When is the bond released?
After the beneficiary confirms that removal and restoration meet the standard, usually through a final inspection and, on private land, landowner sign-off.
Sources
- Texas Utilities Code, Chapters 301 and 302 as amended by HB 3228 (2025), and Chapter 303 as added by HB 3809 (2025)
- Code of Virginia, section 15.2-2241.2
- Renewable Energy Facilities Agricultural Impact Mitigation Act, 505 ILCS 147 (Illinois)
- 43 CFR 2805.20, as amended by the Renewable Energy Rule, 89 FR 35634 (May 1, 2024)
- The Energy Project Decommissioning Handbook, Chapters 2, 7 and 9 (sources of obligations, salvage credits, instruments and the Tallow Creek bond gap)
Figures checked on November 25, 2026. The Harrowgate case is fictional.
The Energy Project Decommissioning Handbook
16 chapters, 4 appendices, a decommissioning plan template, four checklists and unlocked Excel workbooks for a wind farm, a solar plant and a battery at end of life.
View the book and companion files PDF edition Paperback