Articles

SMR Economics: Cost Curves, Learning Rates, and the LCOE Waterfall

Exact FOAK-to-NOAK LCOE breakdown ($170.93 down to $79.68/MWh), 15% Wright's Law learning curves, and +25% / +2-year overrun stress.

First-of-a-kind SMRs cost $170.93/MWh on unsubsidized commercial bank debt, yet drop to $102.10/MWh with DOE FFB financing and a 40% IRC 48E ITC, and fall to $79.68/MWh by Unit 4 along a 15% Wright's Law learning curve.

Worked in full in The Small Modular Reactor Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

The Five-Step SMR LCOE Waterfall (FOAK to NOAK)

In The Small Modular Reactor Finance Handbook, every capital and operating assumption is worked on Redwood Creek SMR Station (300 MWe, 92.0 percent capacity factor, 2,417,760 MWh/yr, 40-year life, $33.20/MWh all-in OpEx). Starting from an overnight capital cost of $8,500/kW ($2.55 billion) plus $300,000,000 in Owner's Costs ($2.85 billion pre-IDC), the LCOE waterfall isolates each financial lever:

SMR Economics Stage (40-Yr Life)Net Capital Base (WACC)Delivered LCOEStep Saving
1. Unsubsidized FOAK (Commercial Debt)$3,256,384,289 (10.00%)$170.93/MWhBaseline
2. Unsubsidized FOAK (DOE FFB Debt)$3,102,614,369 (7.50%)$135.09/MWh-$35.84/MWh
3. Subsidized FOAK (FFB + 40% 48E ITC)$2,098,214,369 (7.50%)$102.10/MWh-$32.98/MWh
4. Upside FOAK (FFB + 50% 48E Dom. Cont.)$1,847,114,369 (7.50%)$93.86/MWh-$8.24/MWh
5. Subsidized NOAK Unit 4 (15% Learning)$1,498,386,749 (7.00%)$79.68/MWh-$22.42/MWh (vs. Stage 3)

Wright's Law Learning Curve and the Overrun Warning

With a 15.0 percent learning rate per cumulative doubling on frozen designs, overnight capital cost drops from $8,500/kW on Unit 1 to $7,225/kW on Unit 2, $6,141.25/kW on Unit 4 (-27.75 percent, saving $707,625,000 per reactor), and $5,220.06/kW by Unit 8 (-38.59 percent). However, schedule discipline is non-negotiable: a +25.0 percent CapEx overrun (+$712,500,000) paired with a 2-year delay (8-year build) adds $110,411,841 in extra FFB IDC, lifts subsidized LCOE to $129.13/MWh, and compresses 40-year pre-tax levered Equity IRR by 565 bps from 9.56 percent down to 3.91 percent.

Review SMR architecture fundamentals in what a small modular reactor is and how SMR designs differ financially, structure the sovereign capital stack in financing new nuclear with DOE LPO Title 17, IRC 48E/45Y, and UK RAB, and test your own LCOE and IRR live in the free SMR Project Finance and LCOE Model (Excel).

Questions practitioners ask

What is the realistic LCOE of a First-of-a-Kind (FOAK) SMR?

On a 300 MWe light-water SMR costing $8,500/kW overnight ($9,500/kW pre-IDC), unsubsidized FOAK LCOE runs $170.93/MWh on commercial debt or $135.09/MWh on DOE FFB debt, falling to $102.10/MWh with a 40% IRC 48E ITC and $79.68/MWh by NOAK Unit 4.

Why do hyperscalers pay over $105/MWh for SMR power when solar is cheaper?

Un-firmed solar only generates 22 to 28 percent of hours; converting intermittent renewables into 99.9 percent hourly 24/7 firm carbon-free baseload requires massive overbuild, multi-day storage, and radial transmission that push delivered 24/7 firm renewable cost into the $90 to $130/MWh range.

How much does a 2-year construction delay hurt SMR economics?

On Redwood Creek Unit 1, stretching a 6-year build to 8 years alongside a 25% CapEx overrun adds $110,411,841 in pure delay IDC and slashes 40-year pre-tax levered Equity IRR by 565 bps to 3.91 percent.

Read the full handbook

This guide is drawn from The Small Modular Reactor Finance Handbook, following Small Modular Reactor projects from Wright's Law cost curves and NRC licensing through 24/7 CFE PPAs, post-OBBBA tax credits, DOE Title 17 FFB loans, and UK RAB financing.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: SMR Project Finance and LCOE Model (Excel).