Worked DMAIC scrap economics, IRC Section 11 tax shields, 3-year After-Tax NPV, and 70 percent realization stress testing.

Simple percentage ROI hides taxes, capital outlays, depreciation shields, and savings decay. To earn fast CFO sign-off on Six Sigma DMAIC projects, pair variable-cost COPQ math with Simple Payback, 3-Year After-Tax NPV under IRC Section 11, and a mandatory 70.0 percent conservative realization stress test.

Worked in full in The Lean Project ROI Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Why Simple Six Sigma ROI Fails CFO Capital Reviews

Many Six Sigma Black Belt charters calculate ROI as Annual Savings / Project Cost and boast "378 percent ROI!" CFOs distrust that ratio because it ignores corporate income taxes (21.0 percent federal statutory rate under IRC Section 11 plus state tax), ignores the ASC 360 split between depreciated CapEx and immediately deductible OpEx, ignores the time value of money, and assumes 100 percent of savings last forever without decay.

Worked Six Sigma DMAIC Case: Crestline Project 2 (Scrap & Rework)

In The Lean Project ROI Handbook, Crestline Precision Manufacturing ran a Six Sigma DMAIC project targeting valve-body machining scrap across 60,000 annual units. Cutting scrap from 4.8 percent (2,880 units) to 1.6 percent (960 units) eliminated 1,920 scrapped units per year.

Crucially, Controller David Chen stripped out $93.75/unit of allocated ERP fixed overhead ($180,000 phantom claim) and valued scrapped castings strictly at their $82 truly variable replacement cost:

Direct project outlay totaled $58,000 ($36,000 CapEx for in-line gauging depreciated over 5 years at $7,200/year plus $22,000 upfront DOE/tooling OpEx). At a 10.0 percent hurdle rate and 25.0 percent combined corporate tax rate (21.0 percent federal + 4.0 percent state):

After-Tax Initial Outlay (t=0) = $36,000 + $22,000 x (1 - 0.25) = $52,500

Annual After-Tax Cash Flow = $219,200 x (1 - 0.25) + ($7,200 x 0.25) = $166,200/year

3-Year After-Tax NPV = ($166,200 x 2.486852) - $52,500 = $360,815 (Simple Payback: 3.2 months)

Portfolio-Level Economics & the 70.0 Percent Stress Test

At the portfolio level, CFOs also deduct 100 percent of annual Continuous Improvement program overhead ($204,000/year at Crestline for MBB/analyst staff, 0.25 FTE Finance validation, and tools) from gross Hard P&L savings ($804,000), leaving $600,000/year in Net EBITDA Lift (3.94x gross coverage; 2.94x net program ROI) against $216,000 total direct outlay ($135,000 CapEx + $81,000 OpEx):

Portfolio Metric (3-Yr @ 10.0%, 25.0% Tax)Base Case (100% Realization)Conservative Stress (70.0%)
Gross Hard P&L Savings / yr$804,000$562,800
Net Hard P&L Benefit (after $204k CI OH)$600,000$358,800
Simple Payback (Direct Outlay $216,000)4.3 months7.2 months
3-Year Pre-Tax NPV$1,276,111$676,282
3-Year After-Tax NPV (P&L Only)$940,120$490,248

Adding Project 3's Year 1 $1,200,000 working capital cash release (PV $1,090,909) pushes total Portfolio After-Tax NPV to $2,031,029. Meanwhile, operating break-even realization sits at just 25.4 percent ($204,000 / $804,000).

Explore the underlying baseline rules in how to calculate Kaizen savings, master hard savings vs. soft savings, and run your own Six Sigma NPV and 70 percent stress test in the free Lean Project Savings Calculator.

Questions practitioners ask

How do you calculate Six Sigma project NPV after taxes?

Compute After-Tax Initial Outlay as CapEx + OpEx x (1 - Tax Rate), compute Annual After-Tax Cash Flow as Annual Hard Savings x (1 - Tax Rate) + Annual Depreciation x Tax Rate, discount those annual cash flows over a conservative 3-year horizon at the corporate hurdle rate, and subtract the After-Tax Initial Outlay.

Why should Six Sigma scrap savings exclude fixed overhead?

Under FASB ASC Topic 330, fixed manufacturing overhead (plant depreciation, supervision, property taxes) is allocated to standard product cost for inventory valuation, but those fixed bills do not decline when scrap drops. Only truly variable materials, consumables, and paid rework overtime save real cash.

What realization haircut should Finance use to stress-test Six Sigma portfolios?

Applying a 70.0 percent conservative realization stress test (30 percent decay haircut) while keeping 100 percent of fixed CI program overhead intact proves whether a portfolio still clears the corporate hurdle rate under real-world drift.

Read the full handbook

This guide is drawn from The Lean Project ROI Handbook, following Crestline Precision Manufacturing, Inc. through a complete five-project Continuous Improvement Finance transformation.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Lean Project Savings Calculator (Excel).

Illustrative figures computed by the book model; Crestline Precision Manufacturing, Inc. is fictional. Education only, not legal, tax, accounting, or external audit advice.