How to calculate net scrap cost at the operation of failure, burdened rework cost, hidden-factory FTEs, and Rolled Throughput Yield (RTY) under ASC 330 and IAS 2.
Valuing scrap strictly at raw material cost understates true manufacturing loss by 40 to 60 percent, while leaving rework unclocked hides full-time employees inside Labor Efficiency Variance. Here are the exact stage-of-completion scrap, burdened rework, and Rolled Throughput Yield (RTY) formulas.
Worked in full in The Cost of Quality Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Every manufacturing operation a part passes through adds direct labor and absorbed overhead. Scrapping a valve housing after finish CNC machining destroys far more cash than rejecting a raw casting at the receiving dock. Always cost scrap at its accumulated standard cost up to the exact operation of failure, less net realizable salvage recovery:
Units Started = Good Units Shipped + Scrapped Units
Scrap Rate = (Scrapped Units / Units Started) x 100
Net Scrap Cost = Scrapped Units x (Cumulative Standard Cost at Failure - Net Salvage per Unit)
In The Cost of Quality Handbook, Kestrel Precision Components, Inc. shipped 240,000 good units in Fiscal 2025 by starting 250,000 units and scrapping 10,000 units (4.00 percent scrap rate). At an average 80 percent stage of completion ($112.00 cumulative cost out of $140.00 full standard cost) minus $4.00/unit metal salvage ($108.00 net/unit), Kestrel's true net scrap loss totaled $1,080,000 ($1,120,000 gross minus $40,000 salvage) - double the old material-only report.
Under FASB ASC 330-10-30 and IFRS IAS 2.16(a), normal irreducible setup scrap is capitalized into inventory, while abnormal scrap exceeding efficient production must be expensed immediately as a period cost.
Rework is never free just because operators are already on payroll. Capture rework on dedicated barcode-scanned RWK- work orders using the fully burdened hourly labor rate (base wage + taxes + benefits + variable shop overhead) plus replacement parts:
Unit Rework Cost = (Rework Hours per Unit x Burdened Rate) + Replacement Parts per Unit
Total Rework Cost = Reworked Units x Unit Rework Cost
Hidden Factory FTEs = (Reworked Units x Rework Hours per Unit) / 2,000
At Kestrel's baseline, 16,000 reworked units (6.40 percent of started) averaging 0.75 hours at $48.00/hour burdened ($36.00 labor) plus $9.00 replacement parts equaled $45.00 per unit, totaling $720,000 per year. More startling, 16,000 x 0.75 = 12,000 rework hours - trapping 6.0 full-time equivalents inside the hidden factory!
| Scrap & Rework Metric | FY2025 Baseline | FY2026 Q4 After | Improvement |
|---|---|---|---|
| Scrapped Units (Scrap Rate) | 10,000 (4.00%) | 4,000 (1.64%) | -6,000 units (-60.0%) |
| Net Scrap Loss (@ $108.00/unit) | $1,080,000 | $432,000 | -$648,000 |
| Reworked Units (Rework Rate) | 16,000 (6.40%) | 7,000 (2.87%) | -9,000 units (-56.3%) |
| Total Rework Cost (@ $45.00/unit) | $720,000 | $315,000 | -$405,000 |
| Hidden Factory Rework Hours (FTEs) | 12,000 hrs (6.0 FTEs) | 5,250 hrs (2.63 FTEs) | 6,750 hrs (3.38 FTEs) freed |
Kestrel previously celebrated a 96.0 percent final-test yield while ignoring upstream machining and assembly defects. Multiplying First-Pass Yield (FPY) across all three sequential production stages exposes true Rolled Throughput Yield (RTY):
Baseline RTY = 94.0% (CNC) x 95.0% (Assembly) x 96.0% (Final Test) = 85.73 percent
After-State RTY = 98.0% (CNC) x 98.5% (Assembly) x 99.0% (Final Test) = 95.56 percent (+9.84 pts)
At baseline, over 14 out of every 100 units on the flagship actuator line experienced a first-pass rejection or minor in-station touch-up across the three stages (spanning both the 10,000 formal scrapped units and 16,000 formal rework orders valued in the general ledger as well as unlogged station-level retries). Installing automated in-process CNC bore probes with 75 percent pre-control stop alarms, DC torque-angle nutrunners, and tapered seal-insertion sleeves lifted RTY by 9.84 percentage points, cutting combined scrap and rework by $1,053,000 per year and freeing 6,750 productive hours.
Calculate your own plant's true scrap cost, rework cost, and hidden-factory FTEs with the free Cost of Quality (PAF) Calculator, and explore Cost of Quality formula and PAF categories and Cost of Poor Quality (COPQ) examples and EBIT leverage.
Multiply scrapped units at each operation step by their accumulated standard manufacturing cost (raw material plus direct labor and absorbed overhead up to the point of failure), then subtract net metal/component salvage recovery.
No. Under both FASB ASC 330-10-30 (U.S. GAAP) and IAS 2.16(a) (IFRS), abnormal amounts of wasted materials, labor, and overhead must be expensed immediately as period costs rather than capitalized into inventory.
Compare floor-stock consumable usage (O-rings, fasteners) against standard BOM requirements, audit automated test-bench serial-number retry logs, deploy 6-second barcode RWK- work orders, and cross-check unfavorable Labor Efficiency Variance.
Final-stage yield ignores every unit scrapped or reworked upstream. RTY multiplies First-Pass Yield across all sequential stages (e.g., 94.0% x 95.0% x 96.0% = 85.73%), revealing the true size of the hidden factory.
This guide is drawn from The Cost of Quality Handbook, following Kestrel Precision Components through a complete 12-month Cost of Quality transformation.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks