It starts 72 hours after the damage and ends when the property should be repaired with reasonable speed, not when it is: 196 days in the worked award, about $131,283 a day.
The period of restoration begins 72 hours after the direct physical loss for Business Income, immediately for Extra Expense, and ends when the property should be repaired, rebuilt or replaced with reasonable speed and similar quality. Worked on a fire-damaged food plant: the insured claimed 214 days, the insurer 168 and the appraisal award 196, each day worth about $131,283.
Worked in full in The Business Interruption Claim Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Under the ISO Business Income (and Extra Expense) Coverage Form CP 00 30 10 12, the "period of restoration" ends on the earlier of two dates: the date when the property at the described premises should be repaired, rebuilt or replaced with "reasonable speed" and similar quality, or the date when business is resumed at a new permanent location. The word "should" matters. The period is a reconstruction of how long a diligent rebuild would take, not the time the rebuild actually took. A slow contractor does not lengthen it. A fast one does not move the theoretical date either, but once operations actually resume, the sales made come off the loss under the Resumption of Operations condition.
For Business Income, the period starts 72 hours after the time of the direct physical loss or damage; for Extra Expense, immediately. The first three days are a deductible measured in time. In the worked case the fire broke out at 2:00 a.m. on March 9, 2025, so Business Income day 1 was March 12, 2025. The three waiting days carried a loss of $810,245 on the award's measures ($832,933 on the insured's, $782,498 on the insurer's), which the policy does not pay. An ISO endorsement, reported as CP 15 56, can reduce or remove the waiting period for an additional premium.
The expiration date of the policy does not cut the period short: a loss in the last week of the policy year is measured to the end of its restoration. But the period excludes any extra time required by an ordinance or law that regulates construction, use or repair, or that requires a response to pollutants. In the case, the pie line was in fact down 231 days, 17 of them caused by a sprinkler and fire code upgrade required by the township. The insured claimed 214 days because the form leaves that ordinance delay out, unless separate ordinance or law coverage applies.
The fictional company followed through The Business Interruption Claim Handbook, Carrow Valley Foods, Inc., lost its Lancaster plant to a fire in the oven room. Physical damage was undisputed; the length of the period was not.
| Position | Days | Ends | Evidence |
|---|---|---|---|
| Insured | 214 | October 11, 2025 | Oven maker's quoted lead time and the contractor's schedule |
| Insurer's forensic accountant | 168 | August 26, 2025 | A refurbished oven from the used equipment market and a parallel roof repair |
| Appraisal award | 196 | September 23, 2025 | A new oven with an expedited delivery slot and a partly parallel schedule |
The period also applies line by line. The award restarted snack bars on June 30, 2025, cookies on August 17, 2025 and pies on September 24, 2025; in fact the lines came back on July 8, 2025, August 24, 2025 and October 29, 2025. Each line stops accruing Business Income on its own restart date, and the loss after a restart moves into the customer recovery.
The free Business Interruption Loss Calculator takes the months of the repair period as an input, so you can test the loss on each party's period before the meeting.
Holding the award's other measures and changing only the period and the line restarts, Lancaster Business Income and Extra Expense before coinsurance come to:
| Period of restoration | Business Income and Extra Expense |
|---|---|
| 168 days | $30,345,300 |
| 196 days | $34,144,775 |
| 214 days | $36,384,301 |
That is about $131,283 per day between 168 and 214 days. In the reconciliation between the insurer's figure and the insured's, the period and the line restarts were worth $5,820,088, the largest of the eight items in a gap of $13,109,928 and more than the next three together (continuing utilities, expediting and makeup sales).
Money spent to shorten the rebuild is Extra Expense only to the extent it reduces the loss that would otherwise have been payable. The company paid $1,450,000 for contractor overtime and air freight of oven parts on July 10, 2025, which it said cut 21 days. On the award's measures, keeping the pie line down 21 days longer would have added $1,319,007 of loss, so the award allowed $1,319,007 of the $1,450,000. The insurer allowed nothing, treating the expediting as part of a rebuild with reasonable speed.
The trap: running Extra Expense to the actual restart date. Extra Expense incurred after the agreed end of the period is not covered: the co-packer ran until October 29, 2025 because the real rebuild took 231 days, and the co-packer premium claimed at $2,927,463 was allowed at $2,606,147.
Customers do not return on the restart date. The Extended Business Income additional coverage pays the loss after operations resume until the business could have reached its pre-loss level with reasonable speed, for at most 60 consecutive days, a number the Extended Period of Indemnity option replaces with the days in the Declarations. The company had 180 days. The award's Extended Business Income was $1,154,482; under the standard 60 days it would have been $970,463, so $184,019 depended on the endorsement.
When damage elsewhere leads a civil authority to prohibit access to the premises, the Civil Authority additional coverage runs its own clock: Business Income starts 72 hours after the first order and lasts up to four consecutive weeks, while Extra Expense starts at once. The described premises must be within one mile of the damaged property. In the case, a chemical release at a neighboring facility 0.6 mile from the company's warehouse closed the area for 9 days from August 17, 2025. Coverage began on August 20, 2025, so 6 days were paid: $499,500 against $749,250 for all 9 days, with $249,750 falling in the waiting period. Rerouting through a third-party cross-dock was Extra Expense from the first day: $216,000.
Every day is argued with documents: equipment lead time quotes in writing, the contractor's baseline schedule and its updates, permit and inspection dates, the used equipment search, and the reasons each step could not run in parallel. Record them as the rebuild happens; a schedule rebuilt a year later persuades nobody. Once the days are set, how to calculate a business interruption loss turns them into dollars and how business income coinsurance works decides what share is paid. For project finance, where the same idea is called the indemnity period, see how to size delay in start-up insurance; for the property proceeds, how to calculate the gain deferred under section 1033.
Under the standard form, 72 hours after the direct physical loss or damage for Business Income, and immediately for Extra Expense.
On the date the property should be repaired, rebuilt or replaced with reasonable speed and similar quality, or the date business resumes at a new permanent location, whichever is earlier. It is a theoretical date, not the actual end of the works.
No. The expiration date of the policy does not cut the period of restoration short.
Not under the standard form: extra time required by an ordinance or law regulating construction or repair is excluded from the period unless ordinance or law coverage is added.
As Extra Expense, to the extent it reduces the loss that would otherwise have been payable. In the worked case $1,319,007 of $1,450,000 was allowed, the loss that 21 more days of shutdown would have added.
This guide is one arc of The Business Interruption Claim Handbook. The book follows one manufacturer from a plant fire to a signed appraisal award: the insuring agreement and the physical loss trigger, the period of restoration and the waiting period, Extra Expense and expediting, Civil Authority, Extended Business Income and dependent properties, limits, coinsurance and the worksheet, the but-for projection, partial resumption and mitigation, continuing and saved expenses, the monthly loss schedule, makeup sales, the first 72 hours, statements of loss and advances, the insurer's forensic accountant and the reconciliation walk, appraisal and claims handling rules, accounting and tax, and the renewal after the claim, with formulas, checklists and templates.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Business Interruption Loss Calculator (Excel).
Illustrative figures computed by the book model; Carrow Valley Foods, Inc., Example Company and every person and amount are fictional and invented for illustration, not any company's data, a market statistic or a forecast. Sales projections, trends and saved expense ratios are conventions of practice, not regulation; the ISO form CP 00 30 10 12 and the other rules are described as read in November 2026, and your own policy wording governs. Education only, not legal, tax, accounting or insurance advice.