Six-package $4,000/kW hard CapEx breakdown, two-tier 10% base and weather-vessel contingency, Jones Act feeder barges, WELCAR/DSU insurance, and overrun vs. delay stress tests.
Gigawatt-scale offshore wind farms rarely close under a single turnkey EPC contract. Instead, sponsors split $4,000/kW of base hard CapEx across six marine and onshore packages, ring-fence 10 percent construction contingency, and manage Jones Act feeder barges under WELCAR and MWS insurance.
Worked in full in The Offshore Wind Project Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
In The Offshore Wind Project Finance Handbook, Beacon Shoal Offshore Wind (900 MW) budgets $3,600,000,000 ($4,000/kW) of Base Hard CapEx across six amended FIDIC Yellow Book and BIMCO marine packages:
| CapEx Package | Dollar Budget | Unit Cost ($/kW) | Primary Risk Driver |
|---|---|---|---|
| 1. WTG Supply (60 x 15 MW) | $1,350,000,000 | $1,500/kW | Steel/copper indexation, EUR FX, serial defects |
| 2. Monopile Foundations | $585,000,000 | $650/kW | Heavy S355 steel, seabed geotech, scour rock |
| 3. OSS & Subsea Cables | $630,000,000 | $700/kW | N-1 transformers, cable burial (>70% of claims) |
| 4. Marine Install & Vessels | $495,000,000 | $550/kW | WTIV scarcity, Jones Act feeder barges |
| 5. Onshore Grid & Port | $270,000,000 | $300/kW | FERC Order 2023 upgrades, 25 t/m2 quay |
| 6. Dev, BOEM Lease & Owner | $270,000,000 | $300/kW | $120M BOEM bonus (non-ITC), NEPA EIS/COP |
Onshore solar deals routinely close with 3 to 5 percent contingency. Multi-contracted offshore wind demands roughly double that cushion because contractor Delay Liquidated Damages (typically capped at 10 percent of each smaller sub-contract) cannot cover $350,000/day WTIV standby if an array cable or monopile slips. Beacon Shoal ring-fences $360,000,000 (10.0 percent) in two explicit buckets:
Adding capitalized IDC ($311,740,465 across a 25%/45%/30% S-curve), 2.0 percent upfront debt fees ($48,827,515), and the 6-month DSRA ($123,041,120) brings Total Project Uses to $4,443,609,100 ($4,937/kW).
Which hurts equity returns more: a 15 percent hard CapEx overrun or a 12-month COD delay? The deterministic model in The Offshore Wind Project Finance Handbook gives an unambiguous answer:
Test your own CapEx packages and delay shocks in the free Offshore Wind Project Finance Model (Excel), or read how offshore wind project finance works and offshore wind offtake and Index ORECs.
This guide is drawn from The Offshore Wind Project Finance Handbook, following Beacon Shoal Offshore Wind, LLC (900 MW) from seabed lease and Index OREC through sculpted debt, tax credits, and stress tests.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Offshore Wind Project Finance Model (Excel).
No single contractor will wrap $3.6 billion of marine risk across turbines, seabed foundations, subsea cables, and jack-up vessels at an economic price. Splitting procurement into 5 to 7 packages saves 15 to 25 percent in wrap premiums, managed via an Owner's Interface Team and 10 percent contingency.
Under 46 U.S.C. 55102 and the FY2021 NDAA OCSLA extension, once a monopile attaches to the OCS seabed it becomes a U.S. coastwise point. U.S.-flagged feeder barges transport turbine components from a U.S. marshalling port to a stationary foreign jack-up WTIV, which lifts and installs them without transporting cargo.
No. DSU insurance indemnifies lost gross profit or debt service strictly when a delay results from an insured physical loss under the WELCAR Construction All Risks policy (after a 45-to-90-day waiting period). Pure marine weather delays must be funded by vessel contingency.
WELCAR and DSU underwriters require an independent MWS to approve every critical marine lift, tow, piling, and cable-lay procedure via a written Certificate of Approval. Proceeding without MWS sign-off can void project insurance coverage.