Library Construction Bonds: Total Project Cost, GO Bond Debt Service, and the Homeowner Cost

A $49,730,500 central library financed with $36,000,000 of bonds, a campaign, a grant, and reserves.

A library bond measure is decided on total project cost, not construction cost, and the bonds are only one of four sources. This worked case builds the full financing plan, the debt service levy, and the cost to a homeowner.

Worked in full in The Public Library Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Total project cost first

A library building is decided financially by its total project cost, not its construction cost. In the fictional case worked in The Public Library Finance Handbook, a new 64,000 square foot central library has a hard cost of $34,880,000 at $545 per square foot, but a total project cost of $49,730,500, about $777 per square foot, once site work, soft costs, furniture and technology, the opening day collection, contingency, and temporary space are added.

Sources and uses

SourceAmount
General obligation bonds, net of $396,000 issuance costs$35,604,000
Capital campaign, net of a 7 percent pledge allowance$7,440,000
State construction grant (fictional program)$2,000,000
Library capital reserve$4,686,500
Total, equal to total project cost$49,730,500

Debt service and the separate bond levy

General obligation bonds are usually approved by voters and repaid by a separate debt service levy outside the operating rate limit. Level debt service on $36,000,000 at an assumed 4.10 percent over 20 years is $2,672,452 a year, using the annuity formula par x rate / (1 - (1 + rate) ^ -years). Divided by net taxable value and the collection rate, that requires about 0.296 mills, or $79 a year ($6.54 a month) for the median home. The case's fictional debt limit of one percent of taxable value is $89,500,000, and the issue uses 40.2 percent of it.

Tax-exempt rules that last for the life of the bonds

Tax-exempt bonds bring continuing obligations that bond counsel sets out at closing: arbitrage limits on investing proceeds, with spending exceptions for construction issues; limits on private business use of the building, which matter for cafes, concessions, and frequent private rentals; record retention; and, for publicly offered bonds, annual continuing disclosure filings on EMMA under SEC Rule 15c2-12.

Pledges are not cash, and buildings cost money to run

Campaign pledges arrive over years. In the case, the last installment, $1,488,000, arrives after the contractors must be paid, so the plan needs a bridge in FY2030, here an interfund loan from the capital reserve. And the larger building adds $512,570 a year to the operating budget, mostly for six added staff. That is why a bond measure and an operating levy are often considered together: the combined cost for the case's median home is $105 a year.

Readers who want the investor's side of municipal credit can turn to The Municipal Bond Analyst. For the operating side, read how public libraries are funded and how a library levy works, and estimate your own debt service levy with the free Library Budget Model (Excel).

Questions practitioners ask

How are public library buildings usually financed?

Most often with voter-approved general obligation bonds repaid by a separate debt service levy, combined with a foundation capital campaign, state construction grants where available, and the library's own capital reserve.

What does a library bond cost a homeowner?

Divide the annual debt service by net taxable value in thousands and by the collection rate to get the debt service rate in mills, then apply it to the home's taxable value. In the book's fictional case, $36 million of 20-year bonds costs the median home about $79 a year.

Why is total project cost so much higher than construction cost?

Because a building project also pays for site work, design and project management, permits and testing, furniture and technology, the opening day collection, contingency, and temporary space. In the case, total project cost is about $777 per square foot against a hard cost of $545.

Read the full handbook

This guide is drawn from The Public Library Finance Handbook, which follows a library district from its levy and budget through reserves, cash flow, a referendum, its foundation, E-Rate, and the financing of a new central library.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Library Budget Model (Excel).