How Do Solar and Battery Completion Tests Work in Project Finance?
Solar and battery completion tests measure the plant's capacity and efficiency against the EPC and supply guarantees, so that the independent engineer can certify completion and any shortfall is paid as liquidated damages before the construction loan converts.
Why completion tests matter to lenders
A completion test is a contractual measurement, run under an agreed procedure, that shows whether the plant delivers the performance the contractor or supplier guaranteed. For lenders it is the bridge between construction risk and operating risk. The construction loan converts to a term loan only when completion is certified, and the term loan is sized on what the plant can actually produce. A shortfall that is not caught at testing ends up in the operating cash flows for the life of the debt.
The independent engineer reviews the test procedures before testing, witnesses the tests or reviews the data, checks the calculations, and issues an opinion. It does not run the plant and it does not guarantee results; it states whether, within its scope, the test was performed as agreed and what the results show.
The PV capacity test
A PV capacity test compares the power a solar plant actually produces, corrected to reference conditions, with the power a model says it should produce under those same conditions. In US EPC contracts a common basis is ASTM E2848, in principle: measured power is regressed against irradiance, temperature and wind and evaluated at reporting conditions, then compared with modeled expected power. IEC TS 61724-2 describes a related capacity evaluation method. The contract fixes the details: test duration, data filtering, the model used for expected power, measurement uncertainty and the pass threshold. Confirm them against the current edition of the standard and the contract itself.
Worked example 1: the Halden Mesa PV test.
- The plant is 250 MWac / 325 MWdc on single-axis trackers. Tessaro Constructors guarantees 97.0% of expected capacity. The guarantee sits below 100 percent to absorb test measurement tolerance, while the energy model behind the P50 assumes the plant delivers 100 percent of its modeled capacity.
- The test, on an ASTM E2848 basis, measures 96.1% of expected capacity.
- Ashgrove Technical Advisors reviews the data filtering and the regression and confirms the result within its scope. The shortfall below the guarantee is 2,250 kWac.
- Buy-down damages apply at $1,200 per kWac, for a payment of $2.70 million.
- Ashgrove then carries the measured ratio of 96.1% into energy in the lenders' base case at conversion, which lowers the IE-case debt from $313.51 million to $300.84 million.
The two numbers measure different things. The buy-down damages only compensate the shortfall below the guarantee; the base case loses everything between the measured result and the full modeled capacity the P50 assumed. That is why $2.70 million of damages sits far below the $12.67 million of debt the shortfall removes. Where the damages go is a negotiated design choice; on Halden Mesa the credit agreement applies them to prepay the loan rather than letting them flow to equity.
The book goes further: the full Halden Mesa case, every table and a live Excel model are in The Independent Engineer Handbook. Try your own numbers with the free IE Cost-to-Complete Model.
Battery capacity and round-trip efficiency
A battery capacity test measures the energy a storage system can discharge at its rated power from a defined state of charge, under the conditions set by the supply agreement. Round-trip efficiency is the ratio of energy discharged to energy charged over a full cycle, measured at an agreed point. Both are guarantees under the battery supply agreement, which on Halden Mesa sits outside the EPC contract. Safety and design compliance, for example with UL 9540, UL 9540A and NFPA 855 in principle, is reviewed separately from these performance tests.
Worked example 2: the Halden Mesa battery tests.
- The battery is 100 MW / 400 MWh (4 hours), contracted to Northgate Power Cooperative under a tolling agreement at $12.00 per kW-month.
- The capacity test measures 392 MWh against 400 MWh guaranteed. The shortfall is 8,000 kWh.
- Capacity damages apply at $180 per kWh, giving $1.44 million.
- Round-trip efficiency measures 86.4% against a guaranteed 85.0%. The test passes, and no damages are due.
- Together with the PV buy-down, performance damages total $4.14 million. At conversion they join the delay damages of $4.50 million, and the two together prepay $8.64 million of the loan.
A passed efficiency test does not offset a failed capacity test. Each guarantee stands alone unless the contract says otherwise, and the IE reports each one separately.
| Test | Guaranteed | Measured | Damages |
|---|---|---|---|
| PV capacity | 97.0% | 96.1% | $2.70 million |
| Battery capacity | 400 MWh | 392 MWh | $1.44 million |
| Round-trip efficiency | 85.0% | 86.4% | None (passes) |
Substantial completion and final completion
Substantial completion is the point at which the plant is complete enough to operate commercially and has passed the required tests, even if minor punch list items remain; final completion is the point at which the punch list is closed and every remaining contractual obligation is met. In principle, delay damages stop running at substantial completion, and the contract decides how much retainage is released then.
On Halden Mesa, guaranteed substantial completion was the end of Month 16, and the plant was 45 days late. Delay damages at $400 per MWac per day came to $4.50 million, well below the cap of $28.53 million (10% of the EPC price), and were paid into the project accounts. The full cost of the delay was $10.67 million, leaving $6.17 million uncovered. At substantial completion $11.90 million of retainage was released, while $2.70 million stayed held until final completion against a punch list estimate of $1.80 million. Final completion came before conversion, so that holdback was drawn into the loan before the term loan was sized.
What the IE checks before signing
A completion certificate is the IE's confirmation to the lenders that the conditions for completion under the credit agreement have been met, as far as they fall within its scope. In practice the IE checks:
- that the test procedures were agreed in advance and followed;
- that metering, calibration and data quality meet the procedure;
- that the calculation of results and damages is arithmetically right;
- that the punch list is complete and the amount held against it is enough;
- that permits, interconnection approvals and the operating documentation are in place.
Earlier steps of the mandate are covered in what an independent engineer does in project finance and in construction draw certification and cost to complete. To test how a delay or a shortfall moves your funding position, use the free IE Cost-to-Complete Model (Excel). The full test sequence and conversion arithmetic for Halden Mesa are in The Independent Engineer Handbook.
The trap: accepting a pass on a capacity test that was run on a cherry-picked window. A few days of clean data, mild temperatures and filtered-out outliers can flatter the result. The IE should check that the filtering rules were set before the test and applied as written, not chosen after the data came in.
None of this is engineering, legal or investment advice; read the actual contracts and confirm the test method with the parties.
Frequently asked questions
Is ASTM E2848 mandatory for PV capacity tests?
No. It is a common basis in US EPC contracts, but the contract decides the method. Some contracts refer to IEC TS 61724-2 or to a bespoke procedure.
Who pays performance liquidated damages?
The party that gave the guarantee: the EPC contractor for PV capacity, the battery supplier for battery capacity and efficiency, each under its own contract.
Can a failed test be rerun?
Whether a retest is allowed, and within what period, is a negotiated term of each contract. Where it is allowed, the contractor usually fixes the cause first; if the retest still fails, buy-down damages apply.
Does the IE witness every test in person?
Not always. The scope may provide for site attendance, remote data review or both. The IE states in its certificate how it observed the test.
Sources
- ASTM E2848, Standard Test Method for Reporting Photovoltaic Non-Concentrator System Performance (E2848-13, reapproved 2023)
- IEC TS 61724-2, capacity evaluation method for PV systems
- UL 9540 and UL 9540A, energy storage systems and thermal runaway fire test method
- NFPA 855, installation of stationary energy storage systems
- FERC Order No. 2023 on generator interconnection procedures (July 2023)
Figures checked on November 25, 2026. The Halden Mesa case is fictional.