How Does an Independent Engineer Certify a Construction Draw and the Cost to Complete?

The independent engineer certifies a construction draw by checking that the work claimed is in place, applying retainage, and confirming that undrawn equity and loan still cover the cost to complete the project.

Each month the independent engineer compares the contractor's claim with what it sees on site, certifies only verified progress, applies retainage, and runs the funds sufficiency test. On the fictional Halden Mesa project, Draw 10 passed with funds available of $171.10 million against Ashgrove's cost to complete of $169.09 million: a margin of only $2.01 million, against $5.70 million in the borrower's own view.

What a draw certificate is

A draw certificate is the IE's written statement to the lenders that the costs in a drawdown request correspond to work performed, that the project remains in balance, and that nothing the IE has seen stands in the way of funding. The credit agreement sets the exact wording and the conditions to each draw; the IE certifies only the technical items within its scope. The administrative agent checks the other conditions and releases funds.

The IE never certifies more than it has evidence for. Evidence means site observation, photographs, quantity surveys, delivery records and invoices, checked against the EPC payment schedule and the construction budget.

Step one: verify the work claimed

Progress verification is the comparison between the percentage of completion claimed for each payment milestone and the percentage the IE can confirm. For a solar plant the usual measures are piles driven, trackers and modules installed, cable terminated and inverters energized. When the IE cannot confirm a line, it reduces the certified amount and says why.

Worked example 1: Draw 5 on Halden Mesa.

  1. Tessaro Constructors claims $28.51 million for the month, including balance-of-plant progress.
  2. Ashgrove Technical Advisors walks the site and finds that part of the claimed balance-of-plant work is not yet in place.
  3. Ashgrove certifies $26.91 million and withholds $1.60 million, with a short explanation in the certificate.
  4. Retainage of 5% applies to the EPC invoices: $0.92 million is held back this month, bringing retainage held to $3.06 million.
  5. Cash paid for Draw 5 is $25.99 million, funded entirely by equity ($25.99 million), because equity is spent first.
  6. In Draw 6, once the work is verified, the withheld amount is released: Draw 6 certifies $35.15 million against $33.55 million claimed.

The adjustment is not a penalty. It is a timing correction that keeps lender money from running ahead of the works.

The book goes further: the full Halden Mesa case, every table and a live Excel model are in The Independent Engineer Handbook. Try your own numbers with the free IE Cost-to-Complete Model.

Step two: apply retainage

Retainage is the share of each EPC payment that the owner holds back until completion as security for defects, incomplete work and the punch list. On Halden Mesa the rate is 5%, and it applies to EPC change orders as well as to the original price: CO2 alone adds $0.34 million, and $14.60 million is held by completion. At substantial completion $11.90 million is released, while $2.70 million stays held to final completion, sized at 150 percent of the punch list estimate of $1.80 million. The 150 percent multiple is a contract design choice, not a rule; the IE checks that the punch list behind it is complete and priced sensibly.

Retainage matters to lenders because it is money that has been certified but not yet paid. It sits in the cost to complete until it is released, and forgetting it understates what the project still owes.

Step three: the funds sufficiency test

The funds sufficiency test, also called the in-balance test, is the check that the funds still available to the project are at least equal to the cost to complete it. Funds available means undrawn equity plus undrawn loan commitment, and sometimes other committed sources the credit agreement allows. Cost to complete means everything left to pay until completion: remaining EPC payments, retainage, the battery supply agreement, network upgrades, owner's costs and the interest during construction (IDC) still to accrue. If the test fails, the credit agreement normally requires the borrower to inject equity or obtain other funds before the next draw.

Worked example 2: the Draw 10 test after a change order.

  1. In Draw 10 the lenders approve change order CO2 of $6.80 million for module substitution and expediting after a supplier shortfall. It falls on the owner under a designated-supplier clause of the EPC contract, which Ashgrove had flagged as an owner risk in its contract review at close. Contingency left falls to $5.70 million.
  2. Ashgrove records paid to date of $289.90 million.
  3. After the substitution, Ashgrove's schedule analysis forecasts substantial completion about 45 days late. Its cost to complete of $169.09 million, built line by line, therefore includes a delay allowance of $3.69 million for extended owner's costs and IDC above budget.
  4. Funds available, undrawn equity plus undrawn loan, are $171.10 million. Equity is already spent, so this is undrawn loan only. The sponsor's letter of credit of $12.00 million under its equity contribution agreement is reserved by the credit agreement for the paydown at conversion and does not count as funds available for the in-balance test.
  5. The IE margin is $2.01 million. The test passes, but thinly.

The borrower's budget-minus-spend view (budget plus approved changes, IDC at budget, no delay) gives a cost to complete of $165.40 million and a margin of $5.70 million, which is simply the contingency left after CO2. The IE view is the more conservative one, because it prices the delay the schedule already shows. For teaching purposes the case assumes that Ashgrove's Draw 10 forecast matched the outcome: final uses came in at $458.99 million against a budget of $461.00 million, and the loan headroom at completion was $2.01 million. That match is an assumption of the case, not proof of the method. A thin pass is a signal to watch the schedule closely, because each further week of delay adds IDC and owner's costs.

Item at Draw 10Borrower viewAshgrove view
Paid to date$289.90 million$289.90 million
Cost to complete$165.40 million$169.09 million
Funds available$171.10 million$171.10 million
Margin$5.70 million$2.01 million

Change orders and contingency

A change order is an agreed change to the EPC scope, price or schedule, and in a financing it usually needs lender consent above a threshold, with an IE opinion on cost and schedule impact. Halden Mesa recorded two in its lender reporting. CO1 (a budget change recorded as a change order) of $9.50 million in Draw 6 is not an EPC change order at all: it is an increase on the network upgrades line, paid to the utility after a restudy, and it carries no retainage. Interconnection costs can move after restudies, a risk that FERC Order No. 2023 made more visible in principle. CO2 followed in Draw 10 as a true EPC change order. Both were charged to contingency, as were later the extended owner's costs and the IDC overrun caused by the delay; contingency ended with $19.99 million used (90.9%) and $2.01 million left.

The IE tests each change order on three questions: is the cost reasonable, is it genuinely outside the original scope, and what does it do to the schedule and the cost to complete.

Delay and interest during construction

Interest during construction is the interest that accrues on the drawn loan balance before conversion and is itself funded by the loan, so any delay increases it. Halden Mesa reached substantial completion 45 days late. The delay period accrued $2.63 million of IDC and $1.20 million of extended owner's costs. Total IDC came to $11.74 million against a budget of $9.25 million: the overrun of $2.49 million comes from the delay and was charged to contingency. It is the delay-period interest of $2.63 million less a small cushion left in the budget on the guaranteed schedule. The budget already assumed equity first, so the funding order saved nothing against it. Tessaro's delay damages of $4.50 million were paid into the project accounts and, with the performance damages, applied to prepay the loan at conversion. When you model cost to complete, put IDC on the actual draw curve and a realistic completion date, not on a straight line.

The trap: taking the contractor's cost to complete at face value. The EPC estimate covers the EPC contract only. It leaves out owner's costs, network upgrades, the battery supply, retainage still to pay and the IDC that delay will add. The IE builds its own figure from every remaining use of funds.

You can rebuild this test on your own project with the free IE Cost-to-Complete Model (Excel). For the wider mandate, see what an independent engineer does in project finance; for the end of construction, see solar and battery completion tests. Every Halden Mesa draw, from close to conversion, is worked through in The Independent Engineer Handbook.

Frequently asked questions

Can the IE refuse to certify a draw?

The IE can decline to certify items it cannot verify and can report that the project is out of balance. Whether funds are then withheld is a lender decision under the credit agreement.

Is retainage part of the cost to complete?

Yes. Retainage is certified but unpaid, so it remains a future payment and belongs in the cost to complete until released.

What happens if the funds sufficiency test fails?

In principle the borrower must restore balance, with additional equity or other committed funds, before further loan advances; the exact remedy is a negotiated term of the credit agreement. Check the actual drafting with counsel.

How often does the IE certify draws?

Usually monthly, matching the EPC payment cycle. Halden Mesa had a draw at financial close and then 16 monthly draws, plus a delay period. For simplicity the case model books all development and owner's costs ($16.50 million) at close, with the financing fees of $6.00 million.

Sources

  1. FERC Order No. 2023 on generator interconnection procedures (July 2023)
  2. The Independent Engineer Handbook, Chapters 9 to 12 (the Halden Mesa draws, funds sufficiency test and change orders)

Figures checked on November 25, 2026. The Halden Mesa case is fictional.