Seven steps from the offer letter's headline to a risk-adjusted present value compared with operating costs.
An offer letter's total is not a value. These seven steps turn a package into a present value you can compare across sites and defend to a board.
Worked in full in The Economic Development Incentives Handbook by Julian R. Sterling, with the case reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Put each benefit in the year the company actually receives it: land and infrastructure before construction, sales tax savings with purchases, grant tranches after milestones are certified, credit refunds after returns are filed, abatements as taxes come due. In the fictional case of The Economic Development Incentives Handbook, Site A's package totals $42.35 million over 2027 to 2038, with $24.29 million (57.3 percent) arriving by the end of 2030.
Use one discount rate for every site. At 8.0 percent, Site A is worth $32.97 million and Site B $33.59 million. At 6 percent they are $34.84 million and $35.30 million; at 10 percent, $31.34 million and $32.05 million. Front-loaded packages hold value better as the rate rises.
Site B's investment credit has a face value of $13.86 million. Sold at $0.88 per dollar, it is worth $9.68 million in present value. If it could only be used against the company's own liability of $350,000 a year, it would be worth $2.17 million, and $10.36 million would expire unused.
| Site A tool | Nominal | Present value |
|---|---|---|
| Refundable jobs credit | $11.14 million | $6.44 million |
| Deal-closing grant | $4.50 million | $3.58 million |
| Forgivable loan | $6.00 million | $6.00 million |
| Sales tax exemption on equipment | $7.80 million | $7.00 million |
| Property tax abatement | $5.46 million | $3.39 million |
| Other tools (training, infrastructure, electric rate) | see the book's case tables | |
| Total | $42.35 million | $32.97 million |
As-of-right benefits belong in the location's cost, not in its package. Site B exempts equipment by statute; Site A's exemption is discretionary. Counting only Site A's exemption as an incentive would credit it with $7.00 million of advantage that does not exist.
Site B costs $19.48 million more to operate in present value. Before incentives it is more expensive by $12.48 million; its package is worth $0.61 million more than Site A's; after incentives Site A is cheaper by $11.87 million.
Run shortfall and closure scenarios across all tools, assign probabilities, and compute a weighted value. With the case's weights, Site A's package is worth $31.67 million and Site B's $31.77 million. The value per committed job is $73,277 at Site A before risk; after an illustrative 25 percent tax rate, $54,958.
Using 3.0 percent, the state's cost is $25.89 million in present value. Counting benefits only within the agreement window, its benefit-cost ratio is 0.81; over twenty operating years, 1.76, breaking even if less than 43.3 percent of such projects would have come anyway.
For the tools, see how economic development incentives work; for the risks, see clawback provisions. The free Incentive Package Value Model (Excel) runs every step for your own project.
Education only. Not legal, tax, accounting, or investment advice; every figure is from a fictional case.
List each benefit by year as it will actually be received, value credits on the route available (refund, sale, or own use), discount at one rate, separate as-of-right benefits, compare with operating cost differences, and adjust for the risk of shortfalls and clawbacks.
Usually the company's normal rate for project cash flows, with specific incentive risks modeled in scenarios rather than added to the rate. Test the ranking of packages at a lower and a higher rate.
Often, directly or through lower deductions. Since the 2017 amendment of Internal Revenue Code section 118, contributions by governmental entities are generally not excluded as contributions to capital, subject to transition rules. Confirm the treatment of each benefit with a tax adviser.
This guide is drawn from The Economic Development Incentives Handbook, following Project Granite, the fictional Calloway Drivetrain Systems plant from the offer letters to the compliance reports.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Incentive Package Value Model (Excel).
Illustrative figures computed by the book’s model; Project Granite and Calloway Drivetrain Systems are fictional. Education only, not legal, tax, accounting, or investment advice.