How many months can a funding round slip before a venture loan's minimum cash covenant breaks?

A minimum cash covenant ends the runway before the bank balance does. The test is the month the covenant fails, not the month the account reaches zero.

With $16.0m of cash and a $5.0m minimum cash covenant, the company fails the covenant in month 9, although cash lasts to month 11. A round planned for month 6 can slip only 2 months before the lender can declare a default; staying compliant through month 12 needs $6.05m more cash.

The assumptions

Illustrative venture-backed software company, invented figures
ItemValue
Opening cash$16.0m after the loan is drawn
Venture loan$10.0m at 12% fixed, interest only for 6 months, then equal principal over 24 months ($0.417m a month)
Operating burn$1.0m in month 1, growing 2% a month
CovenantCash of at least $5.0m, tested at each month-end while the loan is outstanding
Equity roundPlanned to close at the end of month 6, with cash arriving the same day

Interest is charged monthly on the opening balance, 10.0 × 12% ÷ 12 = $0.100m in the first month. Interest and principal count as outflows, so burn here is operating burn before debt service.

Step 1: the cash path month by month

Casht = Casht−1 − burnt − interestt − principalt, with burnt = 1.0 × 1.02t−1

Month 1: 16.000 − 1.000 − 0.100 − 0 = 14.900

Month 7: principal starts, and cash falls by 1.126 + 0.100 + 0.417 = 1.643 to 7.449

Excel, cash in B6 and loan balance in C6: =B5-1*1.02^(A6-1)-C5*0.12/12-IF(A6>6,10/24,0)

Cash and covenant headroom by month, $m
MonthOperating burnInterestPrincipalClosing cashHeadroom over $5.0m
11.0000.1000.00014.9009.900
21.0200.1000.00013.7808.780
31.0400.1000.00012.6407.640
41.0610.1000.00011.4786.478
51.0820.1000.00010.2965.296
61.1040.1000.0009.0924.092
71.1260.1000.4177.4492.449
81.1490.0960.4175.7880.788
91.1720.0920.4174.108−0.892
101.1950.0880.4172.409−2.591
111.2190.0830.4170.690−4.310
121.2430.0790.417-1.050−6.050

Step 2: three measures of runway

Simple runway: 16.0 ÷ (1.000 + 0.100) = 14.5 months, which ignores growing burn and principal

Cash runs out: closing cash is 0.690 in month 11 and −1.050 in month 12, so the last month with cash is 11

Covenant: headroom is 0.788 in month 8 and −0.892 in month 9, so the last compliant month is 8

The company has eight usable months, not the 14.5 of the simple measure or the eleven of the bank balance. A round that closes after month 8 arrives with the covenant already broken.

Step 3: how far the round can slip

Planned close: end of month 6. Last compliant month: 8. Slip allowed: 8 − 6 = 2 months

The company would have been judged to have 11 − 6 = 5 months of slack on bank cash alone

To stay compliant to month 12 the extra cash needed is 5.0 − (−1.050) = $6.05m

A lender can normally waive or reset a covenant in exchange for a fee or a paydown. Without a waiver the loan can be accelerated, and $8.75m would be repayable in month 9 against $4.11m of cash.

What if: the covenant or the burn is different

Covenant breach and slip allowed by case
CaseFirst month covenant failsFirst month cash is negativeMonths the month-6 round can slip
Base case9122
Covenant of $3.0m10123
Covenant of $7.5m7120
Burn flat at $1.0m a month9132
Burn growing 4% a month9112
Opening cash $18.0m10133

Raising the covenant from $5.0m to $7.5m takes the slip from 2 to 0 months, lowering it to $3.0m gives 3, and $2.0m more opening cash adds 1. Burn growth moves the zero-cash month (13 flat, 11 at 4% a month) but not the covenant month, because the covenant bites while burn is still close to its starting level. The model has no revenue growth, no fee on the loan and no cure period, which many loan agreements allow.

The common mistakes

Takeaway

Questions readers ask

How many months can a funding round slip before a venture loan covenant breaks?

2 months in this case. A round planned for month 6 must close by month 8, the last month in which cash stays above the $5.0m minimum.

Why does a minimum cash covenant shorten runway?

Because the lender tests cash at the covenant level, not at zero. Cash is $4.11m in month 9, below the $5.0m minimum, while it would not run out until month 12.

What happens if the covenant is breached before the round closes?

The lender can accelerate the loan or ask for a waiver, usually for a fee or a paydown. In month 9 the balance is $8.75m against $4.11m of cash.

The workbooks behind this article

The free companion files for The Venture Debt Lender rebuild a fictional venture debt fund’s two loans, with schedules, runway, warrants, returns with and without warrants, covenant breach, workout recovery and fund economics. The start-up in this article is invented and is not in them. No account and no email address.

Open the companion files →

Not on Amazon: 36 paperbacks by Julian R. Sterling on how to read the documents, printed on demand and shipped worldwide. Browse the bookshop →

Also on this site

Reading guide: credit, private credit and distressed debt → · All 1908 articles →