How Availability Payment P3s Work: Structure, Indexation, and Credit Math

A practitioner walkthrough of DBFOM availability payment mechanics, fixed vs. CPI-indexed tranches, Value for Money (PSC), GASB 94, and DSCR sizing.

An availability payment Public-Private Partnership (P3) transfers construction cost, schedule, and 30-year lifecycle maintenance risk to private capital without forcing lenders to gamble on traffic counts, patient admissions, or courtroom dockets. Here is the complete capital structure, indexation split, Value for Money math, and DSCR profile worked on a $250 million civic courthouse P3.

Worked in full in The P3 Availability Payment Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

What Makes an Availability Payment P3 Different?

Traditional Design-Bid-Build procurement routinely delivers public buildings late and over budget, followed by decades of deferred mechanical maintenance when county or state budgets tighten. Demand-risk toll concessions solve lifecycle discipline on tolled highways, but you cannot charge user tolls at a county courthouse, a safety-net hospital, or a K-12 public school.

Under a Design-Build-Finance-Operate-Maintain (DBFOM) availability payment P3, a private special purpose vehicle (ProjectCo) designs, constructs, finances, and maintains the facility across a multi-decade concession. ProjectCo earns $0 during construction and collects zero user fees. Once the Independent Engineer certifies Substantial Completion, the public sponsor pays a periodic Availability Payment (AP) conditioned strictly on the facility remaining open, safe, and compliant with technical output standards.

Worked Case: Meridian Civic Justice Center P3 ($250,000,000)

In The P3 Availability Payment Handbook, every formula, invoice, and stress test is worked on one fictional U.S. county courthouse P3, the Meridian Civic Justice Center (Public Sponsor: Alder County; SPV: Meridian Civic Partners LLC), spanning 33 years (3-year construction + 30-year operations):

Capital & Credit ParameterMeridian Civic P3 Value
Total Project Uses (DB $198,000,000 + Soft/IDC/Reserves)$250,000,000
Public COD Milestone Payment / Senior Debt / Sponsor Equity$25,000,000 / $200,000,000 / $25,000,000
Senior Debt Terms (28-yr tenor, 2-yr tail)5.50 percent fixed ($14,162,880/yr DS)
Year 1 Gross Availability Payment (70.0 percent Fixed / 30.0 percent CPI)$24,000,000 ($2,000,000/mo)
Base Case Min / Avg Senior DSCR (LLCR / PLCR)1.23x / 1.25x (1.24x / 1.28x)
Pre-Tax Sponsor Equity IRR (MOIC)12.0 percent (5.65x)

Splitting Fixed Capital vs. CPI-Indexed Tranches

Smart public sponsors never index 100 percent of an Availability Payment to inflation. In Meridian Civic, Year 1 Gross AP ($24,000,000) is split cleanly into two tranches:

Value for Money (PSC vs. P3) and GASB 94 Transparency

Because private debt and equity carry higher nominal yields than tax-exempt General Obligation bonds, an availability payment P3 must clear a rigorous Value for Money (VfM) test against a risk-adjusted Public Sector Comparator (PSC). At a 5.50 percent evaluation discount rate (evaluated at COD), Alder County's traditional DBB PSC (including 20.0 percent historical public construction overrun risk and 30-year deferred-maintenance-adjusted lifecycle costs) totals $428,584,763, compared to $406,243,670 for the P3 ($25,000,000 milestone + $381,243,670 PV of Net AP) - delivering $22,341,093 (5.2 percent) in net Value for Money savings. Under GASB Statement No. 94, Alder County records the courthouse as a Capital Asset and the capital payment stream as a Financed Purchase Liability on its Statement of Net Position, ensuring full public transparency.

Next, dive into performance deductions and payment mechanisms, evaluate public credit via appropriation risk in availability payment deals, or download the unlocked free P3 Availability Payment Model (Excel).

Questions practitioners ask

How does an availability payment P3 differ from a toll road concession?

In a toll concession, private lenders bear traffic and revenue volume risk. In an availability payment P3, the public sponsor retains 100 percent of utilization risk and pays a pre-agreed periodic fee conditioned solely on the facility being open, safe, and maintained to technical standards.

What is a typical DSCR for an availability payment P3?

Because demand risk is eliminated and revenue comes from an investment-grade public sponsor, availability payment P3s typically support 85 to 90 percent debt-to-private-capital leverage with minimum Senior DSCR between 1.20x and 1.30x (1.23x in the Meridian Civic case), distribution lock-up at 1.15x, and event of default at 1.05x.

Are availability payment P3s off-balance-sheet under GASB 94?

No. GASB Statement No. 94 requires public sponsors to recognize the underlying facility as a Capital Asset and the design-build-finance portion of the Availability Payment as a long-term Financed Purchase Liability, while expensing the O&M component as incurred.

Read the full handbook

This guide is drawn from The P3 Availability Payment Handbook, following the $250,000,000 Meridian Civic Justice Center P3 across 33 years of construction, operations, credit stress tests, and handback.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: P3 Availability Payment Model (Excel).

Illustrative figures computed by the book model; Meridian Civic Justice Center, Alder County, and Meridian Civic Partners LLC are fictional. Education only, not legal, municipal advisory, accounting, tax, or investment advice.