How to Fund a Port Capital Plan: Federal Grants, Local Match, Pay-Go Cash, and Revenue Bonds

A worked $144,000,000 plan for a landlord port, with a $22,000,000 federal grant and the debt capacity left afterward.

A port capital plan is not a bond issue. It is a set of projects, each with its own users, revenue, and best source of money. Here is how one fictional authority matched five projects to grants, cash, and bonds, and what it left for the next decision.

Worked in full in The Port Authority Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Start from the plan, not from the bonds

A port authority's capital plan is where its strategy meets its balance sheet. The order of the questions matters: what to build, what each project earns, which money fits each project, and only then how much to borrow. The Port Authority Finance Handbook works the whole sequence on one fictional case, the Kessington Bay Port Authority, whose five-year plan totals $144,000,000.

The case plan and its funding

ProjectCostFunding in the case
Berth 4 rehabilitation and extension$64,000,000federal grant of $22,000,000, rest from governmental bonds
Container yard expansion (leased)$41,000,000docks and wharves bonds (AMT)
Cruise terminal upgrade$12,000,000governmental bonds
Shore power and electrification$18,000,000state grant and cash
Rail connector$9,000,000state grant and cash

Fictional case. Every figure is computed by the book's model.

Grants fund 23.6 percent of the plan, bond project funds 66.0 percent, and the authority's own cash, $15,000,000, the remaining 10.4 percent.

A funding hierarchy

Many ports follow the same order: grants first, where their conditions are acceptable; tenant contributions where a tenant benefits directly; cash for short-lived or mixed-use assets; governmental bonds for long-lived public facilities; exempt facility bonds for facilities leased to private operators; and taxable debt for anything left. The hierarchy keeps the most expensive money for last. It is a guide, not a rule: a grant with an onerous condition can cost more than it brings.

The grant and its local match

The Port Infrastructure Development Program of the Maritime Administration generally limits the federal share to 80 percent of project cost, with possible increases for small projects at small ports and certain rural projects. In the case, the authority asks for less: $22,000,000 toward a $64,000,000 berth, a federal share of 34.4 percent against a maximum of $51,200,000, because a larger committed local match can strengthen a competitive application. The local match of $42,000,000 has to be funded before the application is filed, and federal money brings procurement, labor, domestic preference, environmental review, and single audit requirements. Reimbursement arrives after the authority pays, so cash must bridge the gap. Program rules change with each notice of funding opportunity; the current notice governs.

Why the bonds are larger than the projects

Bond project funds of $95,000,000 require $113,113,712 of par, because the bonds also pay for two years of capitalized interest ($9,909,189), the debt service reserves ($6,847,158), and costs of issuance ($1,357,365). Each extra is a choice with a cost elsewhere: shorter capitalized interest moves debt service ahead of the new revenue, and a surety instead of a cash reserve trades a premium for a smaller issue.

What the plan does to coverage and to the next decision

Coverage falls from 3.10x in FY2029 to 1.43x in FY2030 when the new debt service begins, and the days cash low point is 445 days against a floor of 300. After the plan, at a policy coverage target of 1.40x, the authority has room for about $763,960 of additional annual debt service, roughly $12,818,490 of new bonds. A future channel deepening could cost the authority $63,000,000 before credits. Putting those two numbers side by side, every year, is how a board learns which long-range needs it can fund.

The revenue base behind the plan is described in how port authorities are funded, and the lease protection that keeps coverage above the covenant in a bad year in how minimum annual guarantees work in terminal leases. For the bondholder's view of the debt itself, see The Seaport Revenue Bond Handbook. The free Port Authority Model (Excel) has a capital plan sources and uses tab, a new bond with capitalized interest and reserve, and coverage, so you can test your own plan.

Questions practitioners ask

How do port authorities fund capital projects?

Usually with a mix of federal and state grants, tenant contributions, the authority's own cash, and revenue bonds. Governmental bonds typically fund public facilities, and exempt facility bonds for docks and wharves fund governmentally owned facilities leased to private operators.

What local match does a PIDP grant require?

The Port Infrastructure Development Program generally limits the federal share to 80 percent of project cost, so at least 20 percent comes from non-federal sources, with possible increases in the federal share for small projects at small ports and certain rural projects. The current notice of funding opportunity governs.

Why is a bond issue larger than the project it funds?

Because par must also cover capitalized interest during construction, the debt service reserve fund, and costs of issuance. In the book's case, project funds of about 95 million dollars require about 113 million dollars of bonds.

Read the full handbook

This guide is drawn from The Port Authority Finance Handbook, which follows a public port authority from its terminal schedule and leases through its budget, liquidity, and forecast to two series of revenue bonds, a federal grant, and the cost share of a channel deepening.