Facility condition, the renewal gap, grants, impact fees, bonds, and the cost to the homeowner
Before a park district asks voters to replace a pool, it should know the condition of what it owns, every source of funds it can use, and what the bonds will cost the median homeowner. Here is the method, worked on a fictional district.
Worked in full in The Parks and Recreation District Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
A capital plan begins with an inventory: what each asset would cost to replace and what repairs are overdue. The facility condition index divides the backlog by replacement value. In The Parks and Recreation District Finance Handbook, the fictional district's facilities have a replacement value of $148,000,000, a backlog of $21,500,000, and an index of 14.5 percent. Its annual capital transfer of $2,000,000 falls $960,000 short of a renewal target of 2 percent of replacement value, so the backlog grows every year the gap stays open.
Pay-as-you-go transfers suit recurring renewal such as playgrounds, roofs, and equipment. Outdoor recreation grants, including state-administered grants from the federal Land and Water Conservation Fund, generally cover no more than half of a project and are paid on reimbursement; land developed with such a grant must stay in public outdoor recreation use unless the federal government approves a conversion. Impact fees or fees in lieu of land dedication fund capacity for new residents and, since the Supreme Court's April 2024 decision in Sheetz v. County of El Dorado, legislatively set fees are no longer exempt from the nexus and proportionality tests; on remand, a California appellate court upheld a fee set for a whole class of projects on the strength of its study (July 2025), and the Supreme Court declined to review that ruling in June 2026. Gifts and naming rights should be counted net of pledges that may not be collected.
| Line | Amount |
|---|---|
| Total project cost of a new aquatic center | $18,781,947 |
| State grant (reimbursement) | $600,000 |
| Impact fees | $1,150,000 |
| Campaign pledges, net | $1,350,000 |
| Capital reserve cash used | $2,395,597 |
| General obligation bonds, par | $13,475,000 |
| Level annual debt service, 20 years at 4.10 percent | $1,000,314 |
| Debt service rate per $100 of EAV | $0.0419 |
| Cost to the median home per year | $52.53 |
Fictional case. Every figure is computed by the book's model.
The bonds are sized last, after every other source, with costs of issuance and rounding to $5,000 denominations. Each source belongs to the capital projects fund and is counted once; none of them is operating revenue.
Options with different costs and lives are compared by equivalent annual cost: capital converted to a level annual amount over its life, plus the annual operating subsidy. In the case, renovating the old pool costs $1,171,811 a year on that basis and replacing it $1,144,285, so replacement is cheaper by about $27,526 a year, a narrow margin that depends on the attendance estimate for the new facility.
If the bond rate were one point higher, debt service would rise to $1,090,456 and the median home's cost to $57.26. The district's debt limit leaves ample capacity, so the real constraint is the voters. Tax-exempt bonds carry federal conditions for their whole life, including limits on private business use, arbitrage rules, and continuing disclosure. Bank qualification applies only to issuers expecting no more than $10,000,000 of tax-exempt debt in a calendar year. The operating side of the budget is covered in how a park district budget works, and program fees in recreation cost recovery.
The free Park District Budget Model (Excel) includes a capital and debt tab: condition index, renewal gap, bond sizing, level debt service, the debt levy, and the homeowner cost.
With a mix of capital transfers from operations, grants, impact fees or fees in lieu, gifts, reserve cash, and, for large projects, voter-approved general obligation bonds repaid from a separate debt service levy.
A local match, generally at least half of the project cost, reimbursement after the work is paid for, and a permanent commitment that the site remain in public outdoor recreation use unless a conversion is approved by the federal government.
Divide annual debt service by the district's assessed value and the collection rate to get the debt service rate, then apply that rate to the taxable value of a home of a stated value. In the book's fictional case, the median home pays about $52.53 a year.
This guide is drawn from The Parks and Recreation District Finance Handbook, which follows a park district from its levy and tax cap through fees, cost recovery, seasonal payroll, maintenance, aquatics, and golf, to its budget, cash, reserves, forecast, and the bond financing of a new aquatic center.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Park District Budget Model (Excel).