Condition, the renewal gap, accessible seating, renovate or replace, bonds, coverage, and private use
Before a county builds a new expo hall or rebuilds a grandstand, it should know the condition of what it owns, compare options fairly, and count coverage the way investors will. Here is the method, worked on a fictional fairground.
Worked in full in The County Fairground and Expo Center Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Many fairgrounds were built in a few bursts after the Second World War, and their barns, grandstands, and exhibition buildings are wearing out together. A capital plan starts with an inventory: each asset's current replacement value, its renewal backlog, and its condition index, the backlog divided by the value. The case grounds in The County Fairground and Expo Center Finance Handbook have a replacement value of $38,500,000 and a backlog of $10,600,000, an index of 27.5 percent. The 1971 Exhibition Hall alone stands at 45.2 percent.
At about 2 percent of replacement value a year, the grounds need $770,000 of renewal annually. The fund spends $450,000. The gap of $320,000 a year would push the backlog to $13,800,000 in ten years. Replacing the worst building does not close the gap for the rest of the grounds.
Under the 2010 federal accessibility standards, an assembly area with 501 to 5,000 seats needs 6 wheelchair spaces plus 1 for each 150 seats above 500, with a companion seat beside each. A 4,800-seat grandstand therefore needs 35 wheelchair spaces. Accessibility work belongs in the first tier of the capital plan, with life safety.
The case compares renovating the old hall for $6,100,000 with building a 40,000 square foot expo hall. On equivalent annual cost at a real rate of 2.0 percent, renovation costs $254,408 a year net of the building's contribution, against $363,725 for the new hall at full cost. But the state grant and foundation gifts exist only for the new hall. Counted in the option they fund, they bring the new hall's net annual cost to the county down to $210,191.
| Line | Amount |
|---|---|
| Total project cost | $18,892,354 |
| State grant | $1,500,000 |
| Foundation gifts, net of 10 percent expected shortfall | $2,700,000 |
| Fund cash contribution | $1,400,000 |
| Bonds, par | $13,510,000 |
| Level annual debt service (4.30 percent, 25 years) | $892,439 |
Fictional case computed by the book's model.
Coverage is pledged revenue divided by debt service. In the case, pledged revenue is the fund's operating revenue less operating expenses, plus the pledged lodging tax. It excludes the county's general fund transfer, which is appropriated each year, and state aid. Counted that way, FY2031 coverage is 1.64x; adding the unpledged support would show 2.09x, which overstates the bonds' independence. After the annual renewal transfer, coverage is 1.14x, and in a wet fair year it drops to 0.82x.
Many events in a new hall simply move from the building it replaces. The case hall earns $843,570 in FY2031, but the old hall would have earned $200,394. After the staff, utilities, insurance, and maintenance it adds, and after the part-time staff and cleaning of each event day, the hall improves the fund's operating result by about $184,714 a year, the figure to compare with its cost.
Each rental day in the new hall brings in about $4,952.03 with the margin on event services, but it also needs 30 part-time hours and its cleaning and waste hauling, $956.06 in FY2031. Net of that, a day contributes about $3,995.98. Covering the hall's debt service from its own bookings would take about 326 rental days, more than the 325 days the hall is available in a year. A feasibility study that prices the day at its rent alone makes the building look close to self-supporting; one that counts the people who run the floor shows why the county pledged a lodging tax.
Coverage that meets the bond ordinance can still hide a problem if the fund pays its debt service by skipping maintenance. The case tracks coverage after the $450,000 annual renewal transfer as well: 0.96x in FY2028, 0.95x in FY2029, and 1.14x by FY2031, below the 1.25x policy in every year. The fund manages both commitments only because it carries cash from the year before the bonds. A commission that reads only the ordinance figure would believe the hall is self-supporting; the honest figure says the lodging tax and the opening cash are carrying it through construction.
A project budget can balance on paper and still run short in the middle of construction. Bond proceeds arrive at closing and are drawn as work proceeds, the state grant pays on reimbursement weeks or months after invoices are paid, and foundation pledges arrive over several years. The case budget already assumes that 10 percent of pledges will never be collected, but it does not assume they will arrive late. A monthly draw schedule, separate from the operating cash plan, shows which source pays each month's invoices, and a reimbursement resolution adopted before early design spending keeps those costs eligible for tax-exempt proceeds.
Even when the bonds are general obligations, analysts look hard at a self-supporting fairground pledge, because a pledge that stops covering becomes a claim on the county. They ask about the lodging tax over a full economic cycle and the concentration of hotel rooms; the fund's operating result before support over several years and its dependence on July weather; the hall's market, anchor events, and comparable venues; and the reserve policy, the capital plan, and the quality of reporting. A forecast with scenarios, a coverage table counted the right way and after renewal, and a risk-based reserve answer most of those questions before they are asked.
For tax-exempt bonds, use by the general public is not private business use, and short arrangements are generally excluded: 100 days or less in some cases, or 50 days or less for negotiated arrangements at fair market value, renewal options included. A multi-year exclusive agreement with a show producer, a food service contract that shares profits, or a naming rights deal can count against the 10 percent limit, so bond counsel should review each one. Read how a fairground budget works and fair week revenue, explained, or model your own project with the free Fairground Budget Model (Excel).
With a mix of state grants, foundation gifts, cash reserves, county capital appropriations, and, for large projects, bonds repaid from a pledged revenue such as a lodging tax allocation and the fairground's own net revenue.
As pledged revenue divided by debt service, using the bond documents' definitions: operating revenue less operating expenses before depreciation, plus any pledged tax, excluding unpledged transfers, capital grants, and gifts.
Usually not when they are short and on the same basis as the general public, but multi-year exclusive agreements, profit-sharing management contracts, and naming rights can. Bond counsel decides.
This guide is drawn from The County Fairground and Expo Center Finance Handbook, which follows a county fairground from its fair board and tax status through the gate, the carnival, the grandstand, and the year-round bookings, to its budget, cash, reserves, county support, and the bond financing of a new expo hall.