Why pure private debt fails (0.56x DSCR) while a Blended P3 clears 1.55x Senior DSCR, plus SBA 504 Green retrofit math (14.7 percent CoC).
A ground-up twin-sheet community arena fails 100 percent private commercial bank underwriting at 0.56x DSCR, but clears 1.55x Senior Bond DSCR under a blended municipal P3. Here is how to structure tax-exempt bonds, Rev. Proc. 2017-13 contracts, and SBA 504 green acquisitions.
Worked in full in The Ice Rink and Arena Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
As worked in The Ice Rink and Arena Finance Handbook, financing Northstar Ice Pavilion ($22,000,000 TDC) with a 65.0 percent LTC private commercial bank loan ($14,300,000 at 7.25 percent over 20 years) and full commercial property taxes ($195,000 instead of a $48,000 municipal PILOT) drops CFADS to $753,000 against $1,356,285 of debt service, creating a -$603,285 annual deficit (0.56x DSCR). Switching to a Blended P3 transforms the exact same building into an investment-grade asset:
| Financing Tranche / Coverage Metric | Blended P3 Stack | 100% Private Bank |
|---|---|---|
| Municipal Capital Grant & Land | $8,000,000 (36.4 percent) | $0 |
| Senior Debt (Tax-Exempt Bonds vs. Bank) | $8,500,000 @ 4.75 percent (25 yr) | $14,300,000 @ 7.25 percent (20 yr) |
| C-PACE Energy Efficiency Loan | $2,000,000 @ 6.25 percent (20 yr) | $0 |
| Private Sponsor Equity | $3,500,000 (15.9 percent) | $7,700,000 (35.0 percent) |
| Stabilized CFADS (After $120K Reserve) | $900,000 | $753,000 |
| Senior / Combined CFADS DSCR | 1.55x Sr / 1.19x Comb | 0.56x (Unbankable) |
Review twin-sheet revenue economics in ice rink economics and twin-sheet operating leverage, model energy savings in ice rink energy costs, AIM Act refrigerants, and retrofits, and stress-test your capital stack in the free Ice Rink Operating and Debt Model (Excel).
At modern construction costs ($22M+ for a twin-sheet complex), 65 percent commercial bank debt at 7.25 percent and full commercial property taxes create a 0.56x DSCR deficit. Municipal land, tourism grants, PILOT tax abatements, and 4.75 percent 25-year tax-exempt bonds lift Senior CFADS DSCR to 1.55x.
No. Under IRC Section 141 and IRS Revenue Procedure 2017-13, net-profit sharing creates impermissible Private Business Use that can disqualify tax-exempt bonds. Operators must be paid fixed fees, per-unit fees, or qualitative productivity KPI bonuses.
Because an ice rink is classified as a special-purpose property, SBA 504 requires a 15 percent minimum equity injection for an existing operator (20 percent for a startup under 2 years old), paired with a 50 percent bank first mortgage and a 35 percent CDC debenture (capped at $5.5 million when achieving a 10 percent or greater energy reduction).
This guide is drawn from The Ice Rink and Arena Finance Handbook, following community ice rinks and small arenas from hourly ice economics and refrigeration physics through municipal P3s, tax-exempt bonds, and SBA 504 acquisitions.