Entitlement Risk and Land Value: What an Approval Is Really Worth

Residual land value before and after approval, stage probabilities, the decision tree and the expected value of a pursuit, with a worked example.

Entitled land sells for a multiple of raw land, and the difference is often presented as the developer's profit. It is not. The gap is shared with the landowner, the city and the builder, and it is earned only some of the time. This guide shows how to measure the gap and how to price the risk of chasing it.

Worked in full in The Zoning and Entitlements Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Two values for the same land

Land is worth what the best buyer can do with it under the rules that apply. In the handbook case, Fenwick Yard is worth $4,939,704 as an industrial site under its current zoning. With an approval for 312 apartments, a builder working backward from the finished project can pay $16,122,719, or $51,675 per approved unit. The approval multiplies the land value by 3.26x.

The entitled figure is a residual: the stabilized value of the project, less the builder's required profit, less every cost other than land. Because land is what is left, it is the most sensitive number in the budget. In the case, a rise in the cap rate from 5.25 percent to 5.50 percent takes the land from $16,122,719 to $11,531,911.

The gap is not the profit

The developer in the case does not own the land. It holds an option at $33,000 per approved unit, so the landowner receives $10,296,000 at the full count, about 2.08 times the as-is value. After the option price, closing and disposition costs and a pursuit budget of $2,033,200, the developer's profit in the full approval case is $3,316,625. If the council approves only 276 units with more parking, the land is worth $11,961,734 and the profit falls to $444,679.

Putting a probability on each stage

An approval is not one event. The case assigns each stage a probability of being passed once it is reached. These are judgments made for illustration, not statistics.

StageProbability of passingProbability of reaching it
Feasibility and pre-application95 percent100.0 percent
Application and environmental review90 percent95.0 percent
Planning commission85 percent85.5 percent
Council vote and development agreement80 percent72.7 percent
Challenge period, site plan and subdivision92 percent58.1 percent

No single figure looks worrying. Multiplied together they give a 53.5 percent probability of a final approval. Of those approvals, the model expects 60 percent at the full count, so the chance of the outcome shown in the success pro forma is 32.1 percent.

The expected value of the pursuit

Weight each ending by its probability: the loss at each stage where the pursuit could fail, and the profit in the full and reduced approvals. In the case the result is $372,877. The worst case, a failure at the last stage, is -$2,333,200.

That is a positive expected value and a thin one, roughly a ninth of the profit in the success case. It also assumes that an approval arrives on time: in the case, a six-month delay cuts the full-approval profit to $426,756, and the expected value would be zero if 40 percent of full approvals came that late. It is fragile in other ways too. Holding everything else constant, it falls to zero if the probability of the council vote drops from 80 percent to 66 percent, or if the option price rises from $33,000 to $35,308 per unit. At the seller's asking price of $36,000, the expected value is -$111,834.

What this means for pricing land

Limits

Expected value suits a developer running many pursuits that can absorb the loss of any one. A firm for which the worst case is large relative to its capital should size the pursuit, or share it with a capital partner, before looking at the average. And the probabilities are only as good as the reasoning written down beside them.

Questions practitioners ask

How much does entitlement increase land value?

It depends on the site and the approval. In the fictional handbook case, a 4.20-acre industrial site worth $4,939,704 as-is has a residual land value of $16,122,719 once approved for 312 apartments, a multiple of 3.26x. The figures are illustrative, not market data.

What is entitlement risk?

The risk that the approvals a project needs are denied, granted for a smaller project, delayed or overturned after the developer has spent money on studies, design, hearings and deposits. It is best measured stage by stage with a decision tree.

How do you value an entitlement pursuit?

Estimate a probability of passing each stage, the loss if the pursuit fails at that stage and the profit in each success case, then compute the probability-weighted expected value. Test it against changes in the key vote probability and in the land price.

Read the full handbook

This guide is drawn from The Zoning and Entitlements Handbook, which follows Fenwick Yard from the first zoning memo and the option to the hearings, the final approval and the sale of the entitled site.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Entitlement Risk Budget (Excel).

Illustrative figures computed by the book model; Fenwick Yard is fictional. Education only, not legal, tax, engineering, or investment advice.