Peak exposure on proximo terms, preliminary notices and lien deadlines by state, payment bonds, waivers, a failed framer, and the reserve.
A dealer that sells on account is a lender to the construction industry. This guide sizes the exposure, explains in principle how lien rights protect it, and measures what they recover when a contractor fails.
Worked in full in The Lumber and Building Materials Dealer Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
A pro dealer that sells on account advances materials to builders and contractors who pay weeks later. In the fictional case of The Lumber and Building Materials Dealer Finance Handbook, 90% of sales are on account and external receivables average $5,896,504, more than two years of recurring EBITDA. The credit function is one of the dealer's main risk functions, and its main tools are limits set on the right exposure and lien rights kept alive on every job.
On proximo terms due the tenth, a builder that buys steadily carries about forty days of purchases just before it pays, and more if it pays late. The case's largest builder buys about $686,880 a month, pays about fifteen days late, and averages $1,061,371, but peaks at about $1,259,280. A limit set at the average would put the account on hold every month just before payment, and the counter would override it. A limit set on the peak can be enforced.
State statutes give those who furnish materials to improve real property a lien right if they are not paid, and on public work payment bonds protect suppliers instead. The rights are strict: missing a notice deadline can lose them. Three examples, read in November 2026 and quoted only to show how much the rules differ, not as guidance for any job:
On federal projects, the Miller Act gives a supplier to a subcontractor a claim on the payment bond if it gives written notice to the prime contractor within 90 days of its last delivery and sues within one year (40 U.S.C. 3133). Counsel should handle every lien and bond claim.
In the case, a framing contractor fails owing $286,000 on five jobs. Notices had been given on three, with $171,000 of balances. Assuming 85% recovery where lien rights are intact and 5% where they are not, the dealer recovers $151,100 and loses $134,900, of which $109,250 is on the two jobs without notices. With notices on every job, the loss would have been about $42,900.
| Item | Amount |
|---|---|
| Balance owed | $286,000 |
| With lien rights intact | $171,000 |
| Recovered | $151,100 |
| Loss | $134,900 |
| Payments in the 90 days before filing, net of new value | $90,000 |
Fictional case figures; recovery rates are assumptions.
Bankruptcy adds two more questions. Payments received in the 90 days before a filing may be recoverable by the trustee as preferences, subject to defenses such as ordinary course and subsequent new value (11 U.S.C. 547). And goods received by the debtor in the 20 days before the case can support an administrative claim (11 U.S.C. 503(b)(9)), whose value depends on the estate.
An aging-based reserve applies a rate to each bucket. In the case, rates from 0.5% on current balances to 40.0% over ninety days give a reserve of $231,143, 3.9% of external receivables. Bad debts are cyclical: 1.20% of external credit sales in the bust state against 0.40% in the base year.
Related: how lumber dealer economics work and how a building materials dealer is financed. The free Lumber Dealer Model (Excel) includes the aging, reserve, and borrowing base.
On the peak balance under the customer's terms and payment pattern, not on the average balance.
Yes, widely, and they change. California, Florida, and Texas each set different triggers and deadlines. Follow current state-specific procedures and ask counsel.
No. It describes rules in principle with fictional figures. Real liens, bonds, and bankruptcy claims need qualified counsel.
This guide is drawn from The Lumber and Building Materials Dealer Finance Handbook, which follows a fictional family-owned pro dealer from the price of a board foot through margins, inventory, deliveries, the truss shop, contractor credit and liens, the borrowing base, the cycle, debt, valuation, an expansion, and an acquisition.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Lumber Dealer Model (Excel).