Sellout value, budget, a monthly cash flow, the margin and the two sensitivities that matter, worked on a 120-unit tower.
A condo pro forma is not a rental pro forma with a sale at the end. Revenue arrives in a burst of closings after completion, the construction loan is repaid by those closings, and the margin between sellout value and total cost is the only cushion the deal has.
Worked in full in The Condominium Development Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
The top line of a condo pro forma is the gross sellout value: every unit, at its size, at a price per square foot supported by comparable sales for its type, floor and view. In the worked example from The Condominium Development Handbook, a fictional waterfront tower called The Ashcombe, 120 units add up to 147,400 saleable square feet and a gross sellout of $128,310,000, an average of $1,069,250 a unit and $870 per square foot.
| Unit type | Units | Size (SF) | Price per SF |
|---|---|---|---|
| One-bedroom | 40 | 850 | $800 |
| Two-bedroom | 60 | 1,250 | $850 |
| Three-bedroom | 16 | 1,700 | $900 |
| Penthouse | 4 | 2,800 | $1,150 |
Two deductions turn gross into net: sales commissions (5 percent in the example) and the seller's closing costs (1 percent). Lenders and investors size everything on the net, $1,005,095 per average unit here.
The budget is familiar: land with its closing costs ($9,690,000), hard costs ($71,902,439, or $400 per gross square foot), a contingency ($3,595,122), soft costs ($8,628,293), marketing and the sales center ($2,000,000), a development fee ($2,523,776), the loan fee and interest, and one line rental models never have: dues and property taxes on units the developer still owns after completion ($582,900 in the example). The total development cost is $103,975,268.
What makes a condo pro forma different is the calendar. The Ashcombe closes on its land in month 0, launches presales in month 4, closes its construction loan in month 12, completes in month 36 and sells its last unit in month 47. An annual model blurs exactly the months that matter: the 3-month burst of closings that repays the loan, and the interest that accrues until it does. Build it monthly.
Construction lenders want equity in first and out last. The example's equity commitment of $36,000,000 pays for land, predevelopment and the start of construction ($12,778,488 is spent before the loan closes); the loan, a commitment of $70,000,000 at 8.0 percent, funds the rest, with interest capitalized month by month. Buyers' deposits are not a source of funds: they sit in escrow, peaking at $14,114,100. After completion, every net closing dollar sweeps the loan, which is repaid in month 38, the month in which cash first reaches the equity. Total interest comes to $4,352,739.
The example earns a profit of $16,764,442: 16.1 percent on cost and 13.1 percent on gross sellout, an unlevered IRR of 14.2 percent and an equity IRR of 15.8 percent. Condo investors and lenders look at the margin first because a condo is a one-shot sale over a short period: a short duration flatters the IRR, while the margin is the cushion that absorbs a price cut or a cost overrun.
| Scenario | Profit | Profit on cost | Equity IRR |
|---|---|---|---|
| Base case | $16,764,442 | 16.1 percent | 15.8 percent |
| Prices 5 percent lower | $10,696,132 | 10.3 percent | 10.5 percent |
| Prices 10 percent lower | $4,627,823 | 4.4 percent | 4.7 percent |
| Hard cost 5 percent higher | $12,038,341 | 11.1 percent | 11.6 percent |
| Hard cost 10 percent higher | $7,381,492 | 6.5 percent | 7.1 percent |
Price acts on the whole sellout, so a price cut consumes the margin faster than the same percentage on hard cost. In the example, a price fall of 13.8 percent wipes out the profit entirely. Keep the loan commitment fixed when you stress cost: with hard costs 10 percent higher, the loan hits its commitment and the equity must find $5,989,258 more. A sensitivity that quietly enlarges the loan is not a stress test.
For a first look at a site, the free Condo Development Pro Forma (Excel) estimates interest with an average-balance rule instead of a monthly schedule. On the same inputs it shows 13.8 percent on cost, against 16.1 percent in the monthly model: close enough to screen a site, not to commit equity. The presale side of the deal is covered in condo presale requirements for a construction loan, and what happens to unsold units after completion in condo inventory loans.
There is no rule: a target margin is each investor's and lender's policy. What matters is how much of the margin survives realistic price and cost stresses; in the worked example a price fall of 13.8 percent wipes out the profit.
Because closings arrive in a burst after completion and sweep the loan within weeks, interest and IRR depend on months; an annual model misstates both.
Not in the base case. Deposits are buyers' money held in escrow; some states allow amounts above a threshold to fund construction under strict conditions, which is a separate scenario to model with counsel.
This guide is drawn from The Condominium Development Handbook, which follows The Ashcombe from its first presale to its last closing, its construction loan, its waterfall and the handover of its association.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks