Your capacity tag is your metered load in the grid's five summer peak hours, scaled by the utility and billed every day of the next delivery year.
A capacity tag, or peak load contribution (PLC), is a site's share of the grid's summer peak. In PJM the utility averages the site's metered load in the five coincident peak hours (the 5CP), scales it, and the obligation is billed every day of the next delivery year. In the worked case one megawatt of obligation costs $122,039 a year.
Worked in full in The Commercial Energy Procurement Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Every load-serving entity in PJM must carry capacity for its customers' share of the system peak. PJM buys that capacity years ahead through the Reliability Pricing Model and its Base Residual Auction, for delivery years that run from June 1 to May 31. The distribution utility then pushes the obligation down to each customer account. That number, in megawatts, is the capacity tag, also called the peak load contribution. Your supplier pays capacity on it every day of the delivery year and either folds the cost into a fixed price or bills it as a pass-through line.
The capacity line therefore behaves very differently from the energy line. Energy is a price you take from the market. Capacity is a quantity you largely set yourself, multiplied by a price that PJM has often already cleared for the next two delivery years.
PJM defines the 5CPs as the five highest daily RTO peak loads of the summer, June 1 through September 30, counting one peak per day, and publishes them for the utilities. Each utility reads the customer's metered load in those five hours, averages it and scales it to the zone's weather-normalized peak: that is the PLC. The load-serving entity's obligation is the PLC multiplied by further zonal and pool scaling factors. The tag set in one summer applies to the delivery year that starts the next June 1, and the exact factors differ by zone, so the utility's own method is the one that counts.
For summer 2025 the five peak hours were June 23, June 24, July 29 and July 28, 2025, each at hour ending 18:00 Eastern prevailing time, and June 25, 2025 at hour ending 15:00. The highest reached 160,649 MW. Nobody knows on the day which afternoons will make the list, which is why any plan to lower a tag responds on many more days than five.
Kestrel Molded Products is a fictional US injection molder with three sites in one utility zone of a PJM retail choice state: the Mansfield plant, the Erie Road plant and the Lakeside distribution center. Every company, site, load and amount in the case is invented for illustration, and market prices are assumptions, not forecasts. Its largest site, the Mansfield plant, uses 36,000 MWh a year with an annual peak of 6,000 kW.
| Summer 2025 peak hour | Mansfield metered load |
|---|---|
| June 23, hour ending 18:00 | 5.62 MW |
| June 24, hour ending 18:00 | 5.71 MW |
| July 29, hour ending 18:00 | 5.48 MW |
| June 25, hour ending 15:00 | 5.55 MW |
| July 28, hour ending 18:00 | 5.30 MW |
| Average of the five hours | 5.53 MW |
The case uses illustrative scaling factors, not published ones. Weather normalization of 0.985 turns the 5.53 MW average into a PLC of 5.45 MW; combined zonal and pool scaling of 1.080 turns the PLC into a capacity obligation of 5.89 MW. That obligation is billed from June 1, 2026 to May 31, 2027. Across the three sites Kestrel carries 10.70 MW.
The capacity cost is the obligation times the clearing price per MW-day times the number of days. PJM's RTO clearing price moved from $28.92 per MW-day for 2024/2025 to $269.92 for 2025/2026 and $329.17 for 2026/2027, at the price cap. The 2027/2028 auction cleared at $333.44 per MW-day, the temporary cap, with a floor of $179.55 applying to the 2026/2027 and 2027/2028 auctions. The 2028/2029 auction, announced on July 14, 2026, came in at the cap of $325 per MW-day for the entire PJM footprint.
| Mansfield capacity line | Arithmetic | Cost |
|---|---|---|
| July 2026 bill | 5.89 MW x $329.17 x 31 days | $60,103 |
| Delivery year 2026/2027 | 5.89 MW x $329.17 x 365 days | $707,666 |
| Delivery year 2027/2028, no action | 5.89 MW x $333.44 x 366 days | $718,810 |
On the July 2026 bill the capacity line is $18.16 per MWh, 17.4 percent of a $344,795 bill: the second largest line after energy. The 2027/2028 delivery year includes February 29, 2028, hence 366 days. Because every delivery year touching 2027 and 2028 has already cleared, capacity for a 2027 to 2028 contract bought in late 2026 carries no price risk, only tag risk: the only thing that can still change the line is Kestrel's own load in the peak hours. Price risk comes back from June 2029.
The trap: the tag changes on June 1, not when you read the bill. A tag set from summer 2025 starts on June 1, 2026. If the supplier or the utility keeps billing the old tag, the error runs all year. In the case, an invoice audit recovered $28,650 at the Erie Road plant because its capacity tag was not updated on June 1, 2026.
Kestrel curtailed 1.50 MW at the Mansfield plant during the summer 2026 peaks by shutting two presses and pre-cooling the building. Since the peak hours are only confirmed after the summer, it responded on 12 alert days of 4 hours each, 48 hours in all, to be sure of catching the five.
| Mansfield | No action | With peak shaving |
|---|---|---|
| Average 5CP load | 5.53 MW | 4.03 MW |
| Peak load contribution | 5.45 MW | 3.97 MW |
| Capacity obligation | 5.89 MW | 4.29 MW |
| Capacity cost 2027/2028 | $718,810 | $523,547 |
The obligation falls by 1.60 MW, more than the 1.50 MW curtailed, because the scaling factors multiply the cut. At $333.44 per MW-day over 366 days each MW of obligation is worth $122,039, so the saving is $195,263. The curtailment costs 48 hours at $1,600 an hour of overtime to make up lost production, $76,800, which leaves a net benefit of $118,463 for the delivery year. The plan pays as long as each curtailment hour costs less than $4,068.
The transmission tag works on the same principle with a single hour. PJM network service peak loads use each zone's coincident peak hour over the year from November 1 to October 31. Mansfield's load in that hour was 5.60 MW, billed at an illustrative $58,000 per MW-year: $324,800 a year. If the same 1.50 MW also lands in the zonal peak hour, the tag saves $87,000, but catching one hour out of a year is uncertain, so the case books it as upside, not budget. ERCOT has no capacity market at all: transmission costs follow each customer's load in the four summer monthly system peak intervals (4CP), a method the Texas commission is reviewing.
The free Electricity Contract Comparison Calculator comes prefilled with Example Facility, a fictional single site in a PJM retail choice zone for calendar 2027: 8,000 MWh, a peak of 1.60 MW and a load factor of 57.1 percent. Its capacity obligation is 1.35 MW at $333.44 per MW-day for the year, $164,303, and its transmission tag is 1.40 MW at $52,000 per MW-year, $72,800. The two tags together cost $237,103 a year before a single megawatt-hour of energy is priced. A fixed all-in quote of $98.55 per MWh hides them inside one number; a fixed energy quote of $66.01 per MWh with pass-through shows them as separate lines you can manage. Enter your own tags to see how much of your supply cost they carry.
The tag calculation for all three Kestrel sites, the curtailment plan and the transmission tag are worked tab by tab in The Commercial Energy Procurement Handbook.
In PJM the two terms are used for the same idea: a customer's share of the summer system peak, set from its load in the 5CP hours. Strictly, the PLC is the scaled 5CP average (5.45 MW at the Mansfield plant) and the obligation billed is the PLC times further scaling factors (5.89 MW).
On June 1, the start of the PJM delivery year. A tag set from the summer 2025 peaks is billed from June 1, 2026 to May 31, 2027. Check the first bill after June 1: a tag left un-updated is a common billing error.
Multiply one MW by the clearing price per MW-day and the days in the delivery year. At $333.44 per MW-day over 366 days, one MW costs $122,039 for 2027/2028.
Yes, by reducing load in the summer peak hours, which are only known afterward. In the case, curtailing 1.50 MW on 48 alert hours cuts the obligation by 1.60 MW and nets $118,463 after the cost of overtime.
This guide is one arc of The Commercial Energy Procurement Handbook. The book follows one manufacturer from retail choice and the anatomy of the bill to load profiles, capacity and transmission tags, demand charges and ratchets, fixed, pass-through, index and block products, layered hedging, bandwidth, credit and change-in-law clauses, the supplier RFP, broker fees, the hedging policy and the energy budget, natural gas, demand response, renewable energy certificates and virtual PPAs, and invoice audit.
Paperback PDF edition, $19.99 Book page and companion workbooks
Free download: Electricity Contract Comparison Calculator (Excel).
Illustrative figures computed by the book model; Kestrel Molded Products, its sites, the Example Facility and every supplier and amount are fictional and invented, not market data, and market prices are assumptions, not forecasts. PJM capacity prices and peak hours are PJM's published figures. Market rules and tariffs described as read in November 2026: they change, and each utility zone and contract differs. Education only, not legal, tax, accounting or financial advice.