Never compare a lump-sum municipal BAN against Tax-Exempt Commercial Paper without crediting project-fund reinvestment earnings, and always quantify the exact present-value cost of a +100 bps or +200 bps take-out rate shock before choosing a capital bridge.
Bond Anticipation Notes (BANs) and Tax-Exempt Commercial Paper (TECP) both bridge capital construction before permanent long-term bond take-out, but they carry opposite carry and fee profiles. On a $45,000,000 capital project drawn 60% on average, positive-carry reinvestment of $729,000 can make a fixed-rate BAN slightly cheaper than LOC-backed TECP, while a +100 bps take-out shock costs $4,027,663 in present value.
On Alderbrook's $45,000,000 Water Treatment upgrade (60% average Year 1 draw = $27,000,000 drawn, $18,000,000 undrawn), the fixed-rate BAN (4.75% coupon, 3.45% yield, 4.021% All-In TIC) carries a gross 1-year financing cost of $1,822,300. Crediting 4.05% temporary-period reinvestment earnings on the undrawn $18,000,000 ($729,000) lowers net BAN cost to $1,093,300. By comparison, a $45,000,000 TECP program at 3.15% CP interest ($850,500) plus 8 bps dealer fee ($21,600), 45 bps bank LOC fee on the full $45,000,000 commitment ($202,500), and $45,000 IPA/surveillance fees totals $1,119,600 (4.15% effective rate on drawn funds).
| Scenario ($45,000,000 Capital Bridge) | Rate / Terms | Annual / 1-Yr Cost | PV / Stress Impact |
|---|---|---|---|
| Fixed-Rate BAN (Net After 4.05% Reinv.) | 4.021% All-In TIC | $1,093,300 | Wins in positive carry |
| TECP Program (60% Avg. Draw + 45 bps LOC) | 4.15% eff. on drawn | $1,119,600 | Wins if reinv. drops < 3.9% |
| 20-Yr Take-Out Base vs. +100 bps Shock | 4.25% vs. 5.25% | +$302,960/yr | $4,027,663 PV cost |
| 20-Yr Take-Out +200 bps Shock | 6.25% | +$618,410/yr | $8,221,362 PV cost |
Model your own capital bridge and rollover stress: Get the complete 9-tab workbook (including BAN take-out shocks, TECP breakevens, and VRDN bank-bond term-out stress) inside The Municipal Short-Term Note Handbook, or start with the free TRAN & Note Starter Model.
The Trap: Waiting until 30 days before BAN maturity exposes the issuer to a forced 12-month rollover costing $2,502,500 (at 5.25% plus $140,000 COI). Similarly, on a $45,000,000 SBPA-backed VRDN (3.65% normal all-in cost = $1,642,500/yr), a failed remarketing triggering a 3-year bank-bond term-out at 7.50% spikes annual debt service to $17,304,193 (+$15,661,693/yr). Always begin permanent take-out execution 180 days before BAN maturity.
TECP beats a fixed-rate BAN whenever short-term reinvestment rates fall below TECP's marginal drawn cost (negative arbitrage, especially combined with slow construction draws), when slow draws jeopardize BAN 18-month/2-year spending exceptions, or across multi-year rolling capital programs that avoid repeated BAN issuance fees.
Under Treasury Regulation Section 1.148-2(e)(2), capital project BANs qualify for a 3-year temporary period provided the issuer meets the 5% 6-month Time Test, 85% 3-year Expenditure Test, and Due Diligence Test.
Sources: Treas. Reg. Sections 1.148-2(e)(2) and 1.148-7(d)-(e); GASB Statement No. 88. Figures verified November 24, 2026.