Data_Center_Construction_Model_Blank.xlsx: the book's inputs, cell by cell (Harrowgate, BC1)
Type each value into the named sheet and cell. Shares are decimals (0.05 = 5%). Amounts in US$ million unless the label says otherwise.

Inputs!C5	48	Critical IT capacity (MW)
Inputs!C6	24	Capacity per tranche (MW)
Inputs!C7	140	Rent ($ per kW per month)
Inputs!C8	30	Grace period (days)
Inputs!C10	32	Site work and civil
Inputs!C11	78	Building shell and core
Inputs!C12	64	Electrical installation
Inputs!C13	54	Mechanical installation
Inputs!C14	26	Fire protection, security, controls and low voltage
Inputs!C15	44	General conditions, insurance and construction manager fee
Inputs!C16	150	Owner-furnished electrical equipment
Inputs!C17	46	Owner-furnished mechanical equipment
Inputs!C18	20	Design and engineering
Inputs!C19	7	Commissioning
Inputs!C20	14	Owner's costs (owner's team, permits, builder's risk, utility contribution)
Inputs!C21	25	Owner's contingency
Inputs!C22	0.05	Retainage on GMP progress payments
Inputs!C24	24	Schedule length (months, March 2025 = month 1)
Inputs!C25	14	Data date (month)
Inputs!C26	0.5850467289719626	Physical percent complete at the data date
Inputs!C27	322	Actual cost to date ($m)
Inputs!C29	12	Supplier slip on tranche 1 lineups (weeks)
Inputs!C30	0.35	Extended general conditions and owner's team ($m per week)
Inputs!C31	4	A: tranche 2 pushed (weeks)
Inputs!C32	2.4	B: supplier premium ($m)
Inputs!C33	3.1	B: field acceleration ($m)
Inputs!C34	4	B: remaining tranche 1 delay (weeks)
Inputs!C35	0.8	C: re-engineering, relabeling, factory witness test ($m)
Inputs!C36	2	C: tranche 1 delay (weeks)
Inputs!C38	2.6	Rock in the generator yard excavation (unforeseen site condition)
Inputs!C39	1.8	Utility's revised estimate for the substation contribution
Inputs!C40	1.5	Switchgear reallocation, option C (re-engineering and two weeks of extended general conditions)
Inputs!C41	1.9	Copper escalation on busway and cable under the electrical subcontract's escalation clause
Inputs!C42	2.2	Fuel system changes after the fire marshal's plan review
Inputs!C43	0.6	Integrated systems test rerun on one generator block
Inputs!C44	6	Open risks carried ($m)
Inputs!C46	2.4	Worker-hours to October 2026 (million)
Inputs!C47	9	Recordable injuries
Inputs!C49	56	Medium-voltage switchgear lineups: lead time (weeks)
Inputs!C50	9	Medium-voltage switchgear lineups: ordered (month, January 2024 = 1)
Inputs!C51	29	Medium-voltage switchgear lineups: needed for tranche 1 (month)
Inputs!C52	64	Diesel generators, 3.0 MW: lead time (weeks)
Inputs!C53	9	Diesel generators, 3.0 MW: ordered (month, January 2024 = 1)
Inputs!C54	30	Diesel generators, 3.0 MW: needed for tranche 1 (month)
Inputs!C55	60	Unit substation transformers: lead time (weeks)
Inputs!C56	10	Unit substation transformers: ordered (month, January 2024 = 1)
Inputs!C57	29	Unit substation transformers: needed for tranche 1 (month)
Inputs!C58	36	UPS systems: lead time (weeks)
Inputs!C59	12	UPS systems: ordered (month, January 2024 = 1)
Inputs!C60	30	UPS systems: needed for tranche 1 (month)
Inputs!C61	40	Air-cooled chillers: lead time (weeks)
Inputs!C62	11	Air-cooled chillers: ordered (month, January 2024 = 1)
Inputs!C63	28	Air-cooled chillers: needed for tranche 1 (month)
Inputs!C64	30	Fan walls and computer room air handlers: lead time (weeks)
Inputs!C65	14	Fan walls and computer room air handlers: ordered (month, January 2024 = 1)
Inputs!C66	30	Fan walls and computer room air handlers: needed for tranche 1 (month)
Inputs!C67	24	Busway and power distribution units: lead time (weeks)
Inputs!C68	17	Busway and power distribution units: ordered (month, January 2024 = 1)
Inputs!C69	31	Busway and power distribution units: needed for tranche 1 (month)
Inputs!C70	16	Tranche 2 switchgear float before any swap (weeks)