Articles · US Corporate & Construction Tax

Section 460 Small Contractor Exemption, Post-OBBBA Residential CCM, and the 10% Deferral Election

Large and mid-market contractors have three powerful statutory levers to defer federal tax under IRC Section 460 without triggering penalties. Here is how each rule works in 2026.

1. The Small Contractor Exemption Under IRC Section 460(e)(1)(B)

A construction contractor escapes mandatory PCM and may use the Completed Contract Method (CCM) or another exempt method on any construction contract estimated to complete within two years from commencement if its 3-year average annual gross receipts do not exceed the inflation-adjusted IRC Section 448(c) threshold: $30,000,000 for 2024 (Rev. Proc. 2023-34), $31,000,000 for 2025 (Rev. Proc. 2024-40), and $32,000,000 for 2026 (Rev. Proc. 2025-32). For example, Redwood Regional Builders LLC reports 2023 to 2025 gross receipts averaging $24,800,000, leaving $7,200,000 of headroom under the 2026 cap. If a 2026 revenue surge to $46,000,000 pushes its rolling average to $32,666,667, the transition to PCM operates on a cut-off basis for new 2027 contracts only.

2. Post-OBBBA (P.L. 119-21) Residential Construction Exemption

Public Law 119-21 (Sec. 70430, enacted July 4, 2025) replaced the narrow four-unit "home construction contract" exemption with a broad "residential construction contract" exemption under IRC Section 460(e)(1)(A) for contracts entered into in taxable years beginning after July 4, 2025, repealing the legacy 70/30 hybrid rule and aligning Section 56(a)(3) AMT. On RCI's 48-unit Oakridge Multifamily project ($18,000,000 price, 88.00% dwelling-unit costs, entered February 2026), CCM defers $1,800,000 of 2026 gross profit until 2027 completion, saving $264,600 in 2026 cash tax compared to the repealed 70/30 rule.

3. The 10% Deferral Election Under IRC Section 460(b)(5)

Even large commercial contractors subject to PCM can elect under IRC Section 460(b)(5) to defer all revenue and costs on any long-term contract that is less than 10% complete at year-end. On RCI's Contract B ($12,000,000 Municipal Water Plant), 2025 costs of $768,000 represent 8.00% of estimated total costs ($9,600,000), deferring $192,000 of gross profit and $40,320 of federal tax into 2026. Note that under Treas. Reg. Section 1.460-4(b)(6)(ii), the 10% deferral election cannot be combined with the simplified cost-to-cost method.

Download the live Excel calculator

Run these exact IRC Section 460 PCM, Form 8697 look-back, 10% deferral, and post-OBBBA residential CCM calculations with your own project data.

Free Section 460 PCM & Look-Back Calculator (.xlsx)