Same asset, same cash flow, two returns: the gap is the debt, and it is not the textbook leverage formula.
Project IRR is the internal rate of return of the total capital cost against the cash flow before any financing; equity IRR is the IRR of the equity cheque against the cash flow left after debt service. On an illustrative 200 concession that produces 20.0 in year one, the project IRR is 10.7 per cent and the equity IRR 19.3 per cent at 80 per cent gearing. The 8.6-point gap is the debt, and it is smaller than the textbook leverage formula predicts.
Free Excel workbook: A free debt sculpting model in Excel, on a toll road concession, the worked case from The Infrastructure Investment Analyst. Live formulas, no macros.Get the free workbook →
Worked in full in The Infrastructure Investment Analyst by Julian R. Sterling, with every figure reproduced in a free workbook.Get the DRM-free PDF, $19.99 →or see it on Amazon
A course built on one solar project, from P50 and P90 to construction funding, sculpting, reserves, cover ratios and stress tests, with Excel exercises, a 160-question quiz and the Project Finance Model, Pro Edition included ($149 at launch).
Project IRR is the internal rate of return on the total capital invested, measured on cash flow before any financing. Equity IRR is the return on the equity alone, measured on cash flow after debt service. The two differ only through the debt: when borrowing costs less than the asset earns, equity IRR is higher than project IRR.
| Measure | Year-0 outlay | Cash flow row | Compared with | Worked concession |
|---|---|---|---|---|
| Project IRR (PIRR) | Total capital, 200 | Before financing, 20.00 in year 1 | WACC | 10.71% |
| Equity IRR (EIRR) | Equity cheque, 40 | After debt service, 20.00 − 14.78 = 5.22 in year 1 | Cost of equity | 19.28% |
The formula is the same for both: the rate r that sets −outlay + Σ cash flowt ÷ (1 + r)t to zero. Only the outlay and the row of cash flows change, and the 8.6-point gap between the two results comes entirely from the 160 of debt at 6.0 per cent.
The asset is an illustrative availability-payment concession, already built, bought for 200 with 25 years left. Its cash flow before financing grows with indexation at 2.0 per cent a year. The senior loan is a level annuity. To keep the comparison clean the cash flow is post-tax and the interest tax shield is ignored; including it widens the gap a little. All figures are in millions.
| Input | Value |
|---|---|
| Purchase price (total capital) | 200 |
| Cash flow before financing, year 1 | 20.0 |
| Indexation, per year | 2.0% |
| Remaining concession, years | 25 |
| Gearing (debt / total capital) | 80% |
| Senior debt | 160 |
| Equity | 40 |
| Interest rate, all-in | 6.0% |
| Tenor, years | 18 |
Project IRR: solve for r in −200 + Σ CFt / (1 + r)t = 0, where CFt is cash flow before financing.
Debt service = debt / annuity factor = 160 / 10.83 = 14.78 a year for 18 years.
Equity cash flow = CFt − debt servicet; year 1: 20.00 − 14.78 = 5.22.
Equity IRR: solve for r in −40 + Σ equity CFt / (1 + r)t = 0.
In Excel, with the year-0 outflow in C5 and the 25 years in D5:AB5: =IRR(C5:AB5) on the project row, and the same formula on the equity row, where D7 is =D5-PMT(6%,18,-160) for the loan years and =D5 after maturity.
The two rows share the same top line. Only the first figure and the deduction differ: the project row starts at the full 200 and deducts nothing, the equity row starts at 40 and deducts every payment to the lender.
| Year | Project cash flow | Debt service | Equity cash flow |
|---|---|---|---|
| 0 | −200.00 | −40.00 | |
| 1 | 20.00 | 14.78 | 5.22 |
| 2 | 20.40 | 14.78 | 5.62 |
| 5 | 21.65 | 14.78 | 6.87 |
| 10 | 23.90 | 14.78 | 9.12 |
| 18 | 28.00 | 14.78 | 13.23 |
| 19 | 28.56 | 0.00 | 28.56 |
| 25 | 32.17 | 0.00 | 32.17 |
| Sum of years 1 to 25 | 640.6 | 266.0 | 374.6 |
The project row returns 10.71 per cent; the equity row returns 19.28 per cent. The minimum DSCR, the year-one cash flow divided by debt service (20.00 / 14.78), is 1.35 times, a level an availability-payment lender would accept in many markets, illustratively. The equity multiple is 9.37 times against 3.20 for the project, which says more about the small cheque and the long tail than about value: seven years of debt-free cash flow after maturity carry much of the equity return.
The equity IRR is higher only because the debt costs less than the asset earns. Borrow 160 at 6.0 per cent to fund an asset yielding 10.7, and the spread on 160 flows to 40 of equity. Reverse the inequality and gearing destroys equity return.
The project IRR does not move with the financing; the equity IRR moves with every term of it.
| Gearing | Debt | Equity | Equity IRR | Minimum DSCR |
|---|---|---|---|---|
| 0% | 0 | 200 | 10.7% | n/a |
| 60% | 120 | 80 | 14.7% | 1.80 |
| 70% | 140 | 60 | 16.4% | 1.55 |
| 80% | 160 | 40 | 19.3% | 1.35 |
| 85% | 170 | 30 | 21.7% | 1.27 |
At 80 per cent gearing, a debt rate of 5.0 per cent lifts the equity IRR to 21.3 and the DSCR to 1.46; 7.0 per cent cuts them to 17.3 and 1.26; 8.0 per cent to 15.4 and 1.17. Gearing amplifies the downside too. A permanent 10 per cent fall in cash flow, 18.0 in year one instead of 20.0, costs the project 1.3 points of IRR, down to 9.5 per cent, and costs the equity 4.0 points, down to 15.3, with the DSCR at 1.22.
Hold the gearing at 80 per cent and the rate at 6.0 per cent, and change only the tenor of the senior loan. The project IRR does not move: it is the asset’s return, before any financing. The equity IRR and the year-one debt service cover ratio do.
| Tenor | Annual debt service | DSCR, year 1 | Project IRR | Equity IRR |
|---|---|---|---|---|
| 12 years | 19.08 | 1.05x | 10.7% | 15.6% |
| 15 years | 16.47 | 1.21x | 10.7% | 17.4% |
| 18 years | 14.78 | 1.35x | 10.7% | 19.3% |
| 20 years | 13.95 | 1.43x | 10.7% | 20.5% |
| 22 years | 13.29 | 1.51x | 10.7% | 21.6% |
At twelve years the annuity is 19.08, almost all of the year-one cash flow of 20.0: a DSCR of 1.05x leaves the lender almost no margin for a bad year, and a debt package on those terms would not be offered at this gearing. The longer the tenor, the lower the debt service and the higher the equity IRR, because the debt is repaid out of cash flows that grow with indexation. In practice the tenor is capped by the remaining concession, with a tail of a few years left after the last repayment, and the gearing is then set by the minimum DSCR the lender asks for. That is why sculpting the debt to the cash flow, rather than fixing a gearing first, is how project finance debt is sized.
The tempting shortcut is the corporate finance identity: equity return = project return + (project return − debt rate) × debt / equity. With 10.7, 6.0 and a ratio of 160 to 40, it gives 29.6 per cent, more than ten points above the 19.3 the cash flows actually produce. The formula assumes the debt-to-equity ratio stays at 4.0 forever. An amortising project loan does the opposite: gearing falls every year, reaches zero after 18 years, and the last seven years are earned on an unlevered asset. The only reliable equity IRR is the IRR of the equity cash flow row.
The second error is comparing the wrong pair of numbers. The project IRR is compared with a WACC, the equity IRR with the cost of equity. A 10.7 per cent project IRR set against a 12 per cent equity hurdle looks like a reject; the deal may in fact clear it comfortably once financed, or fail it once the lender's coverage floor caps the gearing.
Build two rows from one top line: the full capital cost against cash flow before financing, and the equity cheque against cash flow after debt service. Here they return 10.7 and 19.3 per cent. The debt sizing that sits between them, sculpted to a coverage floor on the book's toll road, is reproduced in the free workbooks for this book; for how the top line itself is built, see how to calculate CFADS, and for a full model, the project finance model template.
Equity IRR is the rate r that solves −equity invested + Σ equity cash flow ÷ (1 + r)^t = 0, where equity cash flow is the cash flow before financing less debt service. In Excel it is =IRR() on the equity row. On the worked concession, an outlay of 40 followed by 5.22 in year one, rising as the cash flow indexes and the loan matures, gives 19.28 per cent.
PIRR is the project IRR, the return on total capital before financing. EIRR is the equity IRR, the return to shareholders after debt service. On the worked concession the PIRR is 10.71 per cent and the EIRR 19.28 per cent at 80 per cent gearing. In development-bank appraisals EIRR can instead mean economic IRR, so check which one a document uses.
Because the debt costs less than the asset earns. Debt at 6.0 per cent funds 80 per cent of an asset returning 10.7 per cent, and the spread on 160 of borrowing accrues to 40 of equity. If the debt cost more than the project IRR, gearing would lower the equity IRR instead of raising it.
The equity IRR, because both describe the return on the equity cheque after debt. The project IRR is compared with the WACC. In the illustrative case the 19.3 per cent equity IRR is the figure set against an equity hurdle, the 10.7 per cent project IRR against a blended cost of capital.
Arithmetically yes while the project IRR exceeds the debt rate: moving from 60 to 85 per cent gearing takes the illustrative equity IRR from 14.7 to 21.7 per cent. The limit is the lender's coverage test, as the minimum DSCR falls from 1.80 to 1.27 over the same range.
At the same gearing and rate, yes. On the illustrative concession, 160 of debt over 22 years gives an equity IRR of 21.6% against 19.3% over 18 years, and the project IRR stays at 10.7%. Too short a tenor squeezes the cover ratio: over 12 years the year-one DSCR is 1.05x.
This article is one calculation from The Infrastructure Investment Analyst. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.
Get the book on Amazon →Free companion files
Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada
Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99
Not on Amazon: 36 paperbacks by Julian R. Sterling on how to read the documents, printed on demand and shipped worldwide. Browse the bookshop →
Reading guide: infrastructure, data centres and energy → · All 3345 articles →
If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.