Articles

How do you calculate material price and usage variances?

Two formulas that must add back to the total, worked on one month of a moulding line, and the cheaper grade of material that cost more than it saved.

The material price variance is (actual price − standard price) × actual quantity, and the usage variance is (actual quantity − standard quantity for the output achieved) × standard price. The two always add up to actual cost minus standard cost. In the worked month below, buying a cheaper grade saved 4,680 on price and lost 5,040 on usage: the line was 360 worse off than standard, while the purchasing report showed a saving.

Worked in full in Cost Accounting by Julian R. Sterling, with every figure reproduced in a free workbook.Get the DRM-free PDF, $19.99 →or see it on Amazon

Variance analysis exists to put each part of a cost overrun in front of the person who controls it. Price belongs to purchasing, quantity to production. The formulas are designed so that the two never overlap, which is why the order of the terms, and the price used to value the quantity, are not a matter of taste.

The material variance formulas at a glance

AP, SP: actual and standard price per unit of material. AQ: actual quantity used. SQ: standard quantity for the output actually achieved.
VarianceFormulaWorked month
Material price variance(AP − SP) × AQ4,680 F
Material usage (quantity) variance(AQ − SQ) × SP5,040 A
Total material cost varianceAQ × AP − SQ × SP360 A

A negative result means the actual figure is below standard: the variance is favourable (F). A positive result is adverse (A). The usage variance is also called the material quantity or efficiency variance; the price variance, the direct materials price or rate variance. Same formulas, different names.

The assumptions

An illustrative injection moulding line, one month.
InputValue
Good units produced12,000
Standard resin per unit2.5 kg
Standard price of resin4.20 per kg
Resin actually used31,200 kg
Actual price paid4.05 per kg
Resin purchased in the month36,000 kg

Purchasing switched to a lower grade at 0.15 below standard. Production reports more short shots and regrind losses since the switch.

Material price variance formula, step by step

Step 1: the standard quantity for actual output. Not the budgeted volume, the volume actually produced: 12,000 × 2.5 = 30,000 kg, which at standard price is a standard cost of 126,000. Actual cost is 31,200 × 4.05 = 126,360. The total variance to explain is 360 adverse.

Step 2: split it.

The bridge between the two is the middle column every textbook draws: actual quantity at standard price, 31,200 × 4.20 = 131,040. Actual cost to that figure is the price variance; that figure to standard cost is the usage variance.

AQ × APAQ × SPSQ × SP
Amount126,360131,040126,000
VariancePrice 4,680 FUsage 5,040 A
Total360 A

The result

The line used 1,200 kg, or 4.0 per cent, more resin than standard. The saving on price would have survived an overrun of 0.15 ÷ (4.20 − 0.15) = 3.7 per cent of standard, 1,111 kg; at that point the 0.15 saved on 31,111 kg exactly pays for 1,111 extra kg at 4.20. The lower grade cost more in scrap than it saved at the invoice, and the monthly pack, if it reports the two variances on different pages, credits purchasing with 4,680 and charges production with 5,040 for the same decision.

A favourable price variance next to an adverse usage variance of similar size is the signature of a substituted material. Read the two lines together before rewarding either department.

Labour splits the same way. At a standard of 0.4 hours a unit and 22.00 an hour, the 12,000 units should have taken 4,800 hours costing 105,600. The line used 4,650 hours at 22.80, costing 106,020. The rate variance is 0.80 × 4,650 = 3,720 adverse and the efficiency variance is (4,650 − 4,800) × 22.00 = 3,300 favourable: more experienced operators, paid more, worked faster. Net, 420 adverse, and the four variances together are 780 adverse.

What if: the discount against the overrun

Net material variance for the month: negative is favourable.
Discount per kgOverrun 2%Overrun 4%Overrun 6%Break-even overrun
0.10−5401,9204,3802.4%
0.15−2,0703602,7903.7%
0.25−5,130−2,760−3906.3%

The break-even overrun is the discount divided by the standard price less the discount. A material with a high standard price and a thin discount has almost no room for extra scrap: at 0.10 off, an overrun of 2.4 per cent already wipes out the saving.

Two materials: splitting usage into mix and yield

When a product uses more than one material, the usage variance can be split in two: a mix variance, for using the materials in different proportions from standard, and a yield variance, for using more input in total than the output justifies. Take an illustrative compounding line next to the moulding line above. Its standard batch is 70 per cent resin at 4.20 a kg and 30 per cent glass fibre at 1.80, and 100 kg of input should give 90 kg of good compound. In the month it produced 18,000 kg.

Mix and usage variances by material, at standard prices. A = adverse, F = favourable.
MaterialActual kgActual total in standard mixStandard for outputMix varianceUsage variance
Resin14,70014,49014,000882 A2,940 A
Glass fibre6,0006,2106,000378 F0
Total20,70020,70020,000504 A2,940 A

Mix variance = Σ (actual quantity − actual total quantity × standard mix %) × standard price

Yield variance = (actual total quantity − standard total quantity for the output) × standard weighted average price per kg of input

The line used 20,700 kg where the output justified 20,000: a yield variance of 700 kg at the standard average of 3.48 a kg, 2,436 A. It also ran slightly rich in resin, the dearer input, for a mix variance of 504 A. Together they make the usage variance of 2,940 A. The split matters because the two have different owners: mix is a recipe decision, yield is how well the line runs.

The common mistakes

Valuing the usage variance at actual price. (31,200 − 30,000) × 4.05 = 4,860 instead of 5,040. The 180 difference is the joint effect of paying less on the extra kilograms, a price effect, now hidden in production's line. The convention is AQ for price and SP for usage, so each manager is measured only on what they control.

Using standard quantity in the price variance. (4.05 − 4.20) × 30,000 = 4,500, which leaves 180 of the saving unexplained or pushes it into usage. The kilograms actually bought at the lower price are 31,200, and the variance should say so.

Mixing purchase and usage timing. The month bought 36,000 kg. If raw material is held at standard cost, the price variance is taken at purchase, 0.15 × 36,000 = 5,400 favourable, and the 4,800 kg left in stock sit in the balance sheet at the 4.20 standard, 20,160. Taking the variance at purchase one month and at usage the next double counts or loses part of it. Pick one and keep it.

Takeaway

Variances are only as good as the standard behind them. The free workbook on the Cost Accounting companion page builds a factory's unit costs from their inputs and shows how far the overhead allocation method moves the margin on each product family. For the overhead side of the same standard, see how to calculate activity-based costing per unit.

Questions readers ask

What is the material usage variance formula?

Material usage variance = (actual quantity used − standard quantity for the actual output) × standard price. In the worked month, (31,200 − 30,000) kg × 4.20 = 5,040 adverse: 1,200 kg more resin than the 12,000 units should have needed.

Is a negative material price variance favourable?

Yes. With the formula (AP − SP) × AQ, a negative result means the material was bought below standard price, a favourable variance. Paying 4.05 against a 4.20 standard on 31,200 kg gives −4,680, reported as 4,680 F.

Why is the usage variance valued at standard price?

So that each variance isolates one cause. Valuing the excess quantity at standard price keeps purchasing's price effect out of production's usage effect. In the worked case the 1,200 excess kilograms at the 4.20 standard give 5,040 adverse; valued at the actual 4.05 they would give 4,860, and the 180 difference would be a price effect wrongly credited to production.

Should the material price variance be calculated on purchase or on usage?

On purchase, if raw material stock is held at standard cost, because that isolates the buyer's decision when it is made. Buying 36,000 kg at 0.15 below standard gives a 5,400 favourable variance at purchase, against 4,680 on the 31,200 kg used. Either method works if applied consistently; mixing them double counts or loses part of the variance.

How much extra usage cancels a material price saving?

The break-even overrun is the discount per unit divided by the standard price less the discount. A saving of 0.15 a kilogram on a 4.20 standard is cancelled by 3.7 per cent more material, 1,111 kg on a 30,000 kg standard. The line used 4.0 per cent more, so the cheaper grade lost money.

How do you calculate the material mix and yield variances?

Mix: for each material, (actual quantity − total actual quantity × standard mix %) × standard price, summed. Yield: (total actual input − standard input for the actual output) × the standard weighted average price. In the compounding example they are 504 A and 2,436 A, and add up to the usage variance of 2,940 A.

Read the whole case

This article is one calculation from Cost Accounting. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99

Not on Amazon: 19 paperbacks by Julian R. Sterling on markets, funds and compliance, printed on demand and shipped worldwide. Browse the bookshop →

Also on this site

Reading guide: business operations: cost, contracts, pricing and supply chain → · All 3345 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.