Hard Money Rehab Draw Schedules and ALTA 33 Lien Control
Disciplined hard money lenders disburse rehab holdbacks strictly in arrears against third-party inspections, lien waivers, and ALTA 33 title date-downs.
Why Institutional Lenders Fund Strictly in Arrears
Advancing renovation cash upfront invites fund diversion and breaks collateral loan-to-value ratios before work is installed. Under arrears reimbursement, the sponsor funds the first milestone from working capital ($165,000 verified post-closing liquidity in our Plano case) and receives wire reimbursement within 48 to 72 hours after independent inspection and title clearance.
Worked Four-Draw Schedule ($140,000 Holdback)
| Draw | Timing | Verified Scope | Draw Amount |
|---|---|---|---|
| Draw 1 | End Month 1 | Demo, framing, architectural roof | $35,000 |
| Draw 2 | End Month 3 | HVAC, 200A electric, PEX plumbing, drywall | $42,000 |
| Draw 3 | End Month 5 | Kitchen cabinets/quartz, 2.5 baths, flooring | $38,000 |
| Draw 4 | End Month 6 | Exterior paint, landscape, final waivers | $25,000 |
ALTA 32 and ALTA 33 Title Endorsements (and Texas TDI Equivalents)
In most U.S. states, mechanic's liens filed by unpaid contractors can relate back to the start of work or prime optional future construction advances. Title underwriters address this through two paired national ALTA endorsements: ALTA 32 Series (issued at closing to insure future construction advances) and ALTA 33 (issued at every draw after a county title search confirms zero intervening liens, advancing the Date of Coverage and increasing insured coverage up to $371,000, $413,000, $451,000, and $476,000). In promulgated-form jurisdictions such as Texas (where our Plano case sits), title insurers do not issue national ALTA 32/33 forms on residential properties; instead, equivalent construction protection is provided under the Texas Department of Insurance (TDI) Basic Manual via a Form T-2 Loan Policy (or Form T-13 Interim Construction Binder) with Procedural Rule P-8 pending-disbursement provisions and Form T-3 down-date endorsements under Rule P-9b(4), paired with Texas Property Code Chapter 53 statutory lien waivers.
Frequently Asked Questions
What is the difference between conditional and unconditional lien waivers?
A conditional lien waiver releases lien rights for the current draw once payment clears; an unconditional lien waiver proves subcontractors actually received funds from the previous draw before the lender releases the next wire.
What happens if remaining holdback is less than cost to complete?
The loan breaches the Loan-in-Balance covenant; the lender freezes draws until the borrower injects the cash shortfall out of pocket.
Sources: ALTA, Texas Department of Insurance (TDI) Basic Manual, First National Title, Chicago Title (verified 2026-11-24). Complete draw SOPs and checklists are included in The Hard Money Loan Handbook.