Hard Money Rehab Draw Schedules and ALTA 33 Lien Control

Disciplined hard money lenders disburse rehab holdbacks strictly in arrears against third-party inspections, lien waivers, and ALTA 33 title date-downs.

On a $476,000 RTL with a $140,000 rehab holdback released across 4 milestones ($35,000, $42,000, $38,000, $25,000), requiring $225 site inspections, conditional-to-unconditional lien waivers, and title date-down endorsements (ALTA 33 nationally, or TDI Form T-3 in Texas) prevents unpaid subcontractors from priming the lender's mortgage.

Why Institutional Lenders Fund Strictly in Arrears

Advancing renovation cash upfront invites fund diversion and breaks collateral loan-to-value ratios before work is installed. Under arrears reimbursement, the sponsor funds the first milestone from working capital ($165,000 verified post-closing liquidity in our Plano case) and receives wire reimbursement within 48 to 72 hours after independent inspection and title clearance.

Worked Four-Draw Schedule ($140,000 Holdback)

DrawTimingVerified ScopeDraw Amount
Draw 1End Month 1Demo, framing, architectural roof$35,000
Draw 2End Month 3HVAC, 200A electric, PEX plumbing, drywall$42,000
Draw 3End Month 5Kitchen cabinets/quartz, 2.5 baths, flooring$38,000
Draw 4End Month 6Exterior paint, landscape, final waivers$25,000

ALTA 32 and ALTA 33 Title Endorsements (and Texas TDI Equivalents)

In most U.S. states, mechanic's liens filed by unpaid contractors can relate back to the start of work or prime optional future construction advances. Title underwriters address this through two paired national ALTA endorsements: ALTA 32 Series (issued at closing to insure future construction advances) and ALTA 33 (issued at every draw after a county title search confirms zero intervening liens, advancing the Date of Coverage and increasing insured coverage up to $371,000, $413,000, $451,000, and $476,000). In promulgated-form jurisdictions such as Texas (where our Plano case sits), title insurers do not issue national ALTA 32/33 forms on residential properties; instead, equivalent construction protection is provided under the Texas Department of Insurance (TDI) Basic Manual via a Form T-2 Loan Policy (or Form T-13 Interim Construction Binder) with Procedural Rule P-8 pending-disbursement provisions and Form T-3 down-date endorsements under Rule P-9b(4), paired with Texas Property Code Chapter 53 statutory lien waivers.

The Trap (Broken Priority): Letting a borrower drop a dumpster or start demolition two days before recording the Deed of Trust breaks lien priority and can cause the title company to refuse ALTA 32 construction coverage (or Texas TDI P-8/T-3 down-date coverage). Model your full draw schedule with our Free Hard Money Loan Calculator.

Frequently Asked Questions

What is the difference between conditional and unconditional lien waivers?

A conditional lien waiver releases lien rights for the current draw once payment clears; an unconditional lien waiver proves subcontractors actually received funds from the previous draw before the lender releases the next wire.

What happens if remaining holdback is less than cost to complete?

The loan breaches the Loan-in-Balance covenant; the lender freezes draws until the borrower injects the cash shortfall out of pocket.

Sources: ALTA, Texas Department of Insurance (TDI) Basic Manual, First National Title, Chicago Title (verified 2026-11-24). Complete draw SOPs and checklists are included in The Hard Money Loan Handbook.